The ERCOT Queue Brief
Issue 2026-10November 2026Covers the October 2026 GIS report, against September 2026
October: 44 new requests (17,385 MW), 67 withdrawals (10,311 MW), 31 moved forward. Net +7,074 MW in the queue.
What changed in ERCOT's generation interconnection queue this month, county by county, from ERCOT's own report and nothing else.
What changed in the ERCOT generation interconnection queue this month, county by county: new requests, withdrawals, stage changes, the crowded points of interconnection, slipping schedules, and the rules and dates that moved. Every figure is from ERCOT's own report or the document linked; every county links to its page on this site for the full table.
Jump to: Numbers · New · Withdrawn · Moved forward · Crowded POIs · Slipping · Rules · Dates
Download the PDF Excel: every active request, by county The spreadsheet has the issue's tables and all 1,766 active requests with stage and this month's change.
The month in numbers
Between ERCOT's September 2026 and October 2026 reports: 44 new requests (17,385 MW), 67 withdrawn (10,311 MW), net +7,074 MW; 31 requests moved to a later stage: 7 went from study to a signed interconnection agreement, 11 posted financial security (3 did both in one month), and 16 were approved for energization or synchronization. The report lists 1,766 active requests in all.
New requests by type: 17 battery storage, 16 solar, 9 gas combined cycle, 1 gas engines, 1 gas steam turbine. Withdrawn by type: 36 battery storage, 29 solar, 2 wind. Counties with the most new requests: Jones (4), Atascosa (3), Knox (3), Cameron (3), La Salle (2), Mitchell (2), Cottle (2), Howard (2), Comanche (2), Leon (2), Freestone (2), Callahan (2), Live Oak (2).
New requests
The largest of the 44 requests that appear for the first time in the October 2026 report, as ERCOT lists them. A new request is a study position, not a project.
Scroll the table sideways to see every column.
| Request and point of interconnection | County | Type | MW | Target date |
|---|---|---|---|---|
| Ironwood Energy Center30INR0106 · 68051 Reata Station 345kV | Callahan | Gas combined cycle | 1,485 | Jul 2032 |
| TempleCloud Gas28INR0508 · Tap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line | Bell | Gas engines | 1,140 | Oct 2029 |
| Rattler Combined Cycle Energy Center I29INR0410 · 345kV 8318 RIOHONDO7A Substation | Cameron | Gas combined cycle | 991 | May 2029 |
| Rattler Combined Cycle Energy Center II29INR0415 · 345kV 8318 RIOHONDO7A Substation | Cameron | Gas combined cycle | 991 | May 2029 |
| Rattler Combined Cycle Energy Center III29INR0416 · 345kV 8318 RIOHONDO7A Substation | Cameron | Gas combined cycle | 991 | May 2029 |
| Great Rock Energy Center II29INR0417 · Tap 345kV 79011 IRONHORSE TO 46020 LIMEST_POI_5 Ckt 18 and 345kV 79… | Leon | Gas combined cycle | 991 | May 2029 |
| Great Rock Energy Center III29INR0418 · Tap 345kV 79011 IRONHORSE TO 46020 LIMEST_POI_5 Ckt 18 and 345kV 79… | Leon | Gas combined cycle | 991 | May 2029 |
| BM Freestone Energy Center II29INR0419 · Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W t… | Freestone | Gas combined cycle | 991 | May 2029 |
| BM Freestone Energy Center III29INR0420 · Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W t… | Freestone | Gas combined cycle | 991 | May 2029 |
| Ironwood Energy Center II30INR0107 · 68051 Reata Station 345kV | Callahan | Gas combined cycle | 742 | Jul 2031 |
| River Boat Solar28INR0132 · Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek | Mitchell | Solar | 502 | Apr 2029 |
| Blue Energy Center - Phase 2b – Steam32INR0009 · Tap 345kV 80286 DULCE7A - 8676 STATIC7A | Victoria | Gas steam turbine | 475 | Dec 2032 |
Withdrawn
The largest of the 67 requests in the September 2026 report that are absent from October 2026. ERCOT does not publish the reason; a withdrawal frees a study position at that point of interconnection.
Scroll the table sideways to see every column.
| Request | County | Type | MW |
|---|---|---|---|
| Ross Solar26INR0155 | Refugio | Solar | 1,026 |
| Ross Storage26INR0156 | Refugio | Battery storage | 511 |
| Sendero Solar28INR0043 | Starr | Solar | 503 |
| HyFuels Calhoun Solar26INR0028 | Victoria | Solar | 302 |
| Roseland Solar20INR0205 | Falls | Solar | 254 |
| Roseland Solar II22INR0506 | Falls | Solar | 254 |
| Little Ridge Storage25INR0238 | Collin | Battery storage | 252 |
| Black Hawk Solar28INR0040 | Duval | Solar | 251 |
| Clutch City Solar Phase II25INR0330 | Brazoria | Solar | 251 |
| Hill Valley BESS26INR0285 | Grimes | Battery storage | 246 |
| Misty Hollow BESS26INR0324 | Grimes | Battery storage | 246 |
| Calico BESS27INR0382 | Victoria | Battery storage | 205 |
Moved forward
Requests whose stage advanced between the two reports, largest first. Stage labels follow ERCOT's report: approved for energization and approved for synchronization are ERCOT's milestones; agreement signed and security posted are read from its agreement and security columns.
Scroll the table sideways to see every column.
| Request | County | Type | MW | Stage change |
|---|---|---|---|---|
| Sitges Wind28INR0017 | Motley | Wind | 600 | in study → signed, security posted |
| Sequoia II Solar22INR0262 | Callahan | Solar | 417 | signed, security posted → Approved for energization |
| Funston Solar29INR0015 | Jones | Solar | 351 | signed, security posted → Approved for energization |
| Drake BESS25INR0101 | Collin | Battery storage | 257 | signed, security posted → Approved for energization |
| Tall Saddle Solar27INR0309 | Kenedy | Solar | 252 | in study → agreement signed |
| Star Dairy Storage25INR0334 | Lamar | Battery storage | 205 | agreement signed → signed, security posted |
| Tidwell Prairie II Batt22INR0503 | Robertson | Battery storage | 204 | signed, security posted → Approved for synchronization |
| Trenno BESS27INR0173 | Johnson | Battery storage | 203 | agreement signed → signed, security posted |
| Willow Beach Wind25INR0494 | Brazoria | Wind | 202 | agreement signed → signed, security posted |
| Dry Creek Solar II27INR0488 | Rusk | Solar | 201 | in study → signed, security posted |
| Apache Hill BESS25INR0231 | Hood | Battery storage | 201 | Approved for energization → Approved for synchronization |
| Oystercatcher Solar21INR0362 | Ellis | Solar | 198 | Approved for energization → Approved for synchronization |
| Paloma Energy Center27INR0147 | Colorado | Solar | 194 | in study → agreement signed |
| Nightfall Solar21INR0334 | Uvalde | Solar | 181 | Approved for energization → Approved for synchronization |
Crowded points of interconnection
The substations with the most active requests in the October 2026 report, matched on ERCOT's PSS/E bus number rather than the exact wording of the POI column, so a tap off a line counts toward both of its ends and "60404 SOLSTICE" and "AEP Solstice Substation #60404" count together. Direct = requests naming the bus itself; the rest are on tap lines into it. Requests on the same bus compete for the same transmission capacity and each one's study carries the others' assumptions, but in ERCOT every request has its own study and generators do not share network-upgrade costs: the transmission provider builds the upgrades and recovers them through transmission rates. Each county page lists the requests behind its own crowded buses.
Scroll the table sideways to see every column.
| Substation (PSS/E bus) | Counties | Requests | Direct | MW |
|---|---|---|---|---|
| Navarro (68091) 345 kV | Navarro, Freestone, Ellis, Hill | 24 | 1 | 7,854 |
| Solstice (60404) 345 kV | Pecos, Reeves | 23 | 8 | 13,000 |
| RILEY7A (6101) 345 kV | Wilbarger, Wichita, Foard, Baylor and 1 more | 22 | 8 | 9,880 |
| Tnp One (39950) 345 kV | Robertson, Milam | 20 | 4 | 3,794 |
| Cruce (80079) 345 kV | Duval, Jim Hogg, Starr, Webb | 19 | 1 | 5,800 |
| San Miguel (5901) 345 kV | Duval, Wilson, Atascosa, McMullen | 19 | 0 | 5,234 |
| Elm Creek (5133) 345 kV | Wilson, Gonzales, DeWitt, Guadalupe | 19 | 0 | 4,695 |
| Brown (1444) 345 kV | Brown, Coleman, Mills, Runnels | 19 | 2 | 4,694 |
| Cottonwood (59904) 345 kV | Dickens, Cottle, Motley, King and 2 more | 18 | 3 | 4,246 |
| STP (5915) 345 kV | Matagorda, DeWitt, Gonzales, Guadalupe and 3 more | 17 | 1 | 5,266 |
| CENIZO7C (80225) 345 kV | Zapata, Jim Hogg | 16 | 0 | 4,321 |
| Riley (6111) 345 kV | Wilbarger, Wichita, Clay, Montague and 1 more | 15 | 0 | 4,272 |
Schedules slipping
16 active requests (1,900 MW) carry a target commercial-operation date that had passed by the end of October 2026 without approval for energization. ERCOT keeps the developer's last reported date until the developer changes it, so these are schedules that moved, not projects that were built. Most in: Upton (2), Reeves (2), Kent (1), Harris (1), Castro (1), Henderson (1).
Rules that moved
Changes a developer in ERCOT should have on file this month, each linked to the document.
- ERCOT paused the Batch Zero study process on Aug. 3, 2026 and plans to file its Batch Zero Eligibility Verification Report Dec. 10, 2026. (ERCOT, Batch Zero Verification and Audit PUCT presentation, Aug. 20, 2026)
- Only ~18% of 290 large-load dynamic models ERCOT reviewed were acceptable on first review. (ERCOT, Batch Zero Verification and Audit PUCT presentation, Aug. 20, 2026)
- PUCT adopted the final large-load interconnection rule on Sept. 18, 2026 (Project 58481), standardizing requirements for loads of 75 MW or more; the draft's non-refundable $50,000/MW fee was dropped in favor of a flat $100,000 study fee, with $50,000 per MW of requested capacity posted as financial security before studies begin. (White & Case client alert, September 2026)
- The final PUCT rule gives large loads a 24-month grace period spanning the energization schedule. (White & Case client alert, September 2026)
- On Sept. 21, 2026 the Governor directed TCEQ to pause permits related to data center projects; on Oct. 19, 2026, TCEQ told the Governor it had paused all permits related to building infrastructure directly supporting data centers. (TCEQ letter to Gov. Abbott, Oct. 19, 2026)
- All SGIAs executed on or after January 1, 2026 use the updated form approved in PUCT Project 58211; amendments to earlier SGIAs use the old form. (ERCOT market notice M-A120125-02)
- Interconnecting entities above 20 MVA have 300 days from ERCOT's synchronization approval to reach commercial operation unless ERCOT grants a good-cause exception (PGRR103 as filed said 180 days; TAC raised it to 300 before approval). (ERCOT PGRR103)
Dates to watch
- 2026-12-10 · ERCOT: Batch Zero large-load eligibility verification report due to the PUCT (ERCOT presentation, Aug 20, 2026)
- 2027-02-15 · El Paso Electric: Annual 45-day large-generator interconnection window opens (El Paso Electric tariff, Attachment M)
- 2028-03-05 · Texas (TCEQ): Construction General Permit TXR150000 expires; TCEQ renews it (TCEQ)
- 2029-09-01 · Texas (Legislature): Tax Code Chapter 312 expires unless the Legislature continues it, ending the authority to enter new abatement agreements; ask counsel about agreements already signed (Tax Code §312.006)
Full calendar, subscribable: interconnection page.
Where to verify
Past issues
Every row above comes from ERCOT's monthly Generator Interconnection Status report (October 2026 file), compared mechanically with the September 2026 file by interconnection request number; the method is on the methodology page. Names, developers and points of interconnection are as ERCOT lists them. This brief reports changes; it takes no position on any project or company and is not advice.