Duval County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects14
Total capacity3,653MW
Signed agreements0of 14
New since August0requests

14 proposed energy projects from ERCOT's September 2026 report, plus who to call in Duval County and in TCEQ Region 16 before signing a solar, wind, or battery storage lease.

Check land in Duval CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Duval County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Duval County?

ERCOT's September 2026 interconnection report lists 14 proposed energy projects in Duval County (5 solar, 2 wind, 5 battery storage and 2 gas), about 3,653 MW in all. None has a signed interconnection agreement yet.

What stands out in Duval County

By capacity, solar leads in Duval County with 1,489 MW across 5 projects, followed by battery storage (5 projects, 964 MW) and gas (2 projects, 694 MW). The largest single project is Cielo Vista Solar, a 503 MW solar project listed under Cielo Vista Solar, LLC, still in study, and its target online date is Mar 2029. Of the 14, 14 are still in ERCOT's study process. Connection points are mostly at 345 kV (9 projects) and 138 kV (4 projects) (why the voltage matters). The single most-used connection point is Tap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1, shared by 3 projects. ALLTHORN SOLAR, LLC, Apricot Sun Energy Center, LLC and Dove Wing Energy Center, LLC are each listed on 2 projects; 11 different companies appear in all. Target online dates for the projects not yet running span Sep 2028 to Dec 2030. All of them fall in ERCOT's South load zone. 2 that were listed in August have since dropped off.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Guajillo WindTap 345 kV 80079 Cruce - 5901 San Miguel CKT 01Guajillo Wind LLCWind199.9Sep 2028In study
Allthorn BESSTap 138 kV BRUNI44A (#8297) - CRESTONI4A (#8695)ALLTHORN SOLAR, LLCBattery storage (paired with solar)205.2Jan 2029In study
Allthorn SolarTap 138 kV BRUNI4A (#8297) - CRESTONI4A (#8695)ALLTHORN SOLAR, LLCSolar231.5Jan 2029In study
Cielo Vista Power Gas PlantTap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1 · shared with 2 other requestsCielo Vista Power, LLCGas engines343.8Mar 2029In study
Cielo Vista Power IITAP 345 kV BUS # 5901 MIGUEL5 - BUS #80280Cielo Vista Power II, LLCGas engines350.4Mar 2029In study
Cielo Vista SolarTap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1 · shared with 2 other requestsCielo Vista Solar, LLCSolar503.3Mar 2029In study
Cielo Vista StorageTap 345kV Bus #5901 Miguel5 - Bus #80079 Cruce7A Ckt 1 · shared with 2 other requestsCielo Vista Storage, LLCBattery storage (paired with solar)310.8Mar 2029In study
Cazadores SolarTap 345 kV (80079) CRUCE7A – (5901) MIGUEL5 CKT 2OCI Energy LLCSolar301.6Apr 2029In study
Estrella Dorada WindTap 345 kV 80079 Cruce - 5901 San Miguel Ckt 2Estrella Dorada Wind Farm, LLCWind306.0Jul 2029In study
Apricot Sun SolarTap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1 · shared with 1 other requestApricot Sun Energy Center, LLCSolar200.8Sep 2029In study
Apricot Sun StorageTap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1 · shared with 1 other requestApricot Sun Energy Center, LLCBattery storage (paired with solar)200.8Sep 2029In study
Dove Wing Storage138 kV Zenaida Bus# 80043 · shared with 1 other requestDove Wing Energy Center, LLCBattery storage (stand-alone)122.2Sep 2029In study
Jumping Cactus Storage138 kV Zenaida Bus# 80043 · shared with 1 other requestDove Wing Energy Center, LLCBattery storage (stand-alone)125.3Sep 2029In study
Black Hawk SolarSan Miguel (5901) - Cruce (80079) double circuit transmission line....ACE DevCo NC, LLCSolar251.3Dec 2030In study

No longer listed since August

These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.

  • Realitos Solar SLF, solar, 150 MW (Mesquite Creek LLC)
  • Realitos Storage SLF, battery storage (Mesquite Creek LLC)

Crowded connection points in Duval County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

San Miguel (5901) 345 kV 20 requests · 5,476 MW · 10 in Duval County, 10 in Wilson, Atascosa, McMullen17 in study, 3 signed; security posted
  • Miranda Solar Project 24INR0161 · Solar · 262 MW · Signed; security posted · McMullen
  • Anila BESS 26INR0077 · Battery storage · 209 MW · Signed; security posted · Wilson
  • Anila Solar 26INR0074 · Solar · 201 MW · Signed; security posted · Wilson
  • Mojo Solar 28INR0250 · Solar · 528 MW · In study · Wilson
  • Cielo Vista Solar 27INR0150 · Solar · 503 MW · In study
  • Wilson Gas Plant 28INR0494 · Gas engines · 403 MW · In study · Wilson
  • Cielo Vista Power II 28INR0497 · Gas engines · 350 MW · In study
  • Cielo Vista Power Gas Plant 28INR0325 · Gas engines · 344 MW · In study
  • Cielo Vista Storage 29INR0115 · Battery storage · 311 MW · In study
  • Estrella Dorada Wind 29INR0146 · Wind · 306 MW · In study
  • Cazadores Solar 29INR0160 · Solar · 302 MW · In study
  • Black Hawk Solar 28INR0040 · Solar · 251 MW · In study
  • Amphion Solar Phase 2 28INR0343 · Solar · 206 MW · In study · Atascosa
  • Marcelina Storage 23INR0318 · Battery storage · 203 MW · In study · Wilson
  • Apricot Sun Solar 29INR0124 · Solar · 201 MW · In study
  • Apricot Sun Storage 29INR0125 · Battery storage · 201 MW · In study
  • Amphion Storage 29INR0214 · Battery storage · 200 MW · In study · Atascosa
  • Guajillo Wind 28INR0168 · Wind · 200 MW · In study
  • Amphion Solar Phase 1 29INR0050 · Solar · 181 MW · In study · Atascosa
  • Amphion Solar Phase 3 28INR0344 · Solar · 115 MW · In study · Atascosa
Cruce (80079) 345 kV 21 requests · 6,554 MW · 9 in Duval County, 12 in Jim Hogg, Starr, Webb15 in study, 5 signed; security posted, 1 signed
  • Mirando Valley Wind 28INR0072 · Wind · 479 MW · Signed; security posted · Jim Hogg
  • Viento Bravo Wind 28INR0434 · Wind · 367 MW · Signed; security posted · Jim Hogg
  • Bullring Wind 2 28INR0038 · Wind · 304 MW · Signed; security posted · Starr
  • Bullring Wind 1 28INR0037 · Wind · 304 MW · Signed; security posted · Starr
  • Bullring Wind 3 28INR0039 · Wind · 190 MW · Signed; security posted · Starr
  • Cenizo Solar 29INR0219 · Solar · 301 MW · Signed Sep 2026 · Webb
  • Las Mujeres Solar 29INR0154 · Solar · 684 MW · In study · Jim Hogg
  • Cielo Vista Solar 27INR0150 · Solar · 503 MW · In study
  • Sendero Solar 28INR0043 · Solar · 503 MW · In study · Starr
  • Cielo Vista Power Gas Plant 28INR0325 · Gas engines · 344 MW · In study
  • Cielo Vista Storage 29INR0115 · Battery storage · 311 MW · In study
  • Estrella Dorada Wind 29INR0146 · Wind · 306 MW · In study
  • Cazadores Solar 29INR0160 · Solar · 302 MW · In study
  • Ciervo Wind 28INR0242 · Wind · 302 MW · In study · Jim Hogg
  • Black Hawk Solar 28INR0040 · Solar · 251 MW · In study
  • Apricot Sun Solar 29INR0124 · Solar · 201 MW · In study
  • Apricot Sun Storage 29INR0125 · Battery storage · 201 MW · In study
  • Guajillo Wind 28INR0168 · Wind · 200 MW · In study
  • Bell Song Solar 30INR0041 · Solar · 168 MW · In study · Jim Hogg
  • Bell Song Solar 2 30INR0049 · Solar · 168 MW · In study · Jim Hogg
  • Bell Song Solar 3 31INR0009 · Solar · 168 MW · In study · Jim Hogg
Zenaida (80043) 138 kV 2 requests · 248 MW2 in study
  • Jumping Cactus Storage 26INR0391 · Battery storage · 125 MW · In study
  • Dove Wing Storage 26INR0393 · Battery storage · 122 MW · In study
Bruni (8297) 138 kV 4 requests · 638 MW · 2 in Duval County, 2 in Webb4 in study
  • Allthorn Solar 28INR0229 · Solar · 232 MW · In study
  • Allthorn BESS 28INR0230 · Battery storage · 205 MW · In study
  • El Molino Solar SLF 25INR0321 · Solar · 201 MW · In study · Webb
  • El Molino Storage SLF 25INR0322 · Battery storage · 0 MW · In study · Webb
Bus 8695 (8695) 138 kV 2 requests · 437 MW2 in study
  • Allthorn Solar 28INR0229 · Solar · 232 MW · In study
  • Allthorn BESS 28INR0230 · Battery storage · 205 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Duval County

  • Duval County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 16, Laredo: 707 E Calton Rd, Ste 304, Laredo TX 78041-3887, 956-791-6611; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Duval County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Duval County.

Permits and reviews for Duval County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Duval County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Duval County connects to the grid

Duval County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Duval County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Duval County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 16

Dimmit · Kinney · La Salle · Maverick · McMullen · Val Verde · Webb · Zapata · Zavala