Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Uvalde County

Uvalde County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects3
Total capacity223MW
Signed agreements1of 3
New since August0requests

3 proposed energy projects from ERCOT's September 2026 report, plus who to call in Uvalde County and in TCEQ Region 13 before signing a solar, wind, or battery storage lease.

Check land in Uvalde CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Uvalde County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Uvalde County?

ERCOT's September 2026 interconnection report lists 3 proposed energy projects in Uvalde County (2 solar and 1 battery storage), about 223 MW in all. 1 of the 3 has a signed interconnection agreement, and 1 has been approved for energization or synchronization.

What stands out in Uvalde County

By capacity, solar leads in Uvalde County with 221 MW across 2 projects, followed by battery storage (1 project, 2 MW). The largest single project is Nightfall Solar, a 181 MW solar project listed under BDPU SOLAR NIGHTFALL, LLC, approved for energization, and its target online date is Dec 2026. Of the 3, 2 are still in ERCOT's study process and 1 is approved for energization or synchronization. Connection points are mostly at 69 kV (2 projects) and 138 kV (1 project) (why the voltage matters). Ashra Solar, LLC is listed on the most projects here (2 of 3); 2 different companies appear in all. The target online date reported for all of them is Jun 2028. All of them fall in ERCOT's South load zone. 6 that were listed in August have since dropped off.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Nightfall Solar138 kV Tap 8707 Dryfrio - 8234 Uvalde (new 138 kV Meil station)BDPU SOLAR NIGHTFALL, LLCSolar180.9Dec 2026Approved for energization
Ashra Solar SLFTap 69kV bus#5823 UVALDE Switch (UVALDESW9) to bus#5820 UVALDE SUB...Ashra Solar, LLCSolar40.2Jun 2028In study
Ashra Storage SLFTap 69kV 5823 UVALDE Switch - 5820 UVALDE SUBAshra Solar, LLCBattery storage (paired with solar)1.6Jun 2028In study

No longer listed since August

These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.

  • PHOTO BESS 1, battery storage, 75 MW (CED Development Inc.)
  • PHOTO BESS 2, battery storage, 150 MW (CED Development Inc.)
  • Photo BESS 3, battery storage, 100 MW (CED Development Inc.)
  • Photo Solar 1, solar, 150 MW (CED Development Inc.)
  • Photo Solar 2, solar, 300 MW (CED Development Inc.)
  • SUNSETTER BESS, battery storage, 100 MW (CED Development Inc.)

Crowded connection points in Uvalde County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Uvalde (5823) 69 kV 2 requests · 42 MW2 in study
  • Ashra Solar SLF 28INR0188 · Solar · 40 MW · In study
  • Ashra Storage SLF 28INR0190 · Battery storage · 2 MW · In study
Uvalde (5820) 69 kV 2 requests · 42 MW2 in study
  • Ashra Solar SLF 28INR0188 · Solar · 40 MW · In study
  • Ashra Storage SLF 28INR0190 · Battery storage · 2 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Uvalde County

  • Uvalde County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 13, San Antonio: 14250 Judson Rd, San Antonio TX 78233-4480, 210-490-3096; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Uvalde County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Uvalde County.

Permits and reviews for Uvalde County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Uvalde County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Uvalde County connects to the grid

Uvalde County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Uvalde County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Uvalde County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 13

Atascosa · Bandera · Bexar · Comal · Edwards · Frio · Gillespie · Guadalupe · Karnes · Kendall · Kerr · Medina · Real · Wilson

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.