Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Robertson County

Robertson County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects20
Total capacity3,889MW
Signed agreements6of 20
New since August0requests

20 proposed energy projects from ERCOT's September 2026 report, plus who to call in Robertson County and in TCEQ Region 9 before signing a solar, wind, or battery storage lease.

Check land in Robertson CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Robertson County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Robertson County?

ERCOT's September 2026 interconnection report lists 20 proposed energy projects in Robertson County (4 solar and 16 battery storage), about 3,889 MW in all. 6 of the 20 have a signed interconnection agreement.

What stands out in Robertson County

By capacity, battery storage leads in Robertson County with 2,599 MW across 16 projects, followed by solar (4 projects, 1,291 MW). The largest single project is Big Rooter East Solar, a 555 MW solar project listed under Big Rooter East, LLC, with an interconnection agreement signed in Jun 2025, and its target online date is May 2029. Of the 20, 14 are still in ERCOT's study process, 3 have a signed interconnection agreement but no security posted yet and 3 have posted security or started construction. Connection points are mostly at 345 kV (17 projects) and 69 kV (2 projects) (why the voltage matters). The single most-used connection point is Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2, shared by 8 projects. Tempus Power management LLC is listed on the most projects here (8 of 20); 9 different companies appear in all. Target online dates for the projects not yet running span Oct 2026 to Dec 2029. All of them fall in ERCOT's North load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Barton Branch IATap 345kV 3400 Twin Oak - 39950 TNP One · shared with 1 other requestBarton Branch IA LLCBattery storage (stand-alone)203.6Oct 2026 date passed; status per ERCOTSigned; security posted
Tidwell Prairie II BattTap 345kV 3400 Twin Oak - 39950 TNP One · shared with 1 other requestTidwell Prairie IIA LLCBattery storage (stand-alone)203.6Dec 2026Signed; security posted
Bee Branch IATap TNP ONE 39950 and Twin Oak 3400Bee Branch IA LLCBee Branch IA LLCBattery storage (stand-alone)203.8Jun 2027Signed; security posted
Big Rooter West Solar39950# TNTNP_ONE_3 345 KV · shared with 1 other requestBig Rooter West, LLCSolar403.2May 2028Signed Feb 2025
Big Rooter East Solar39950 TNP One Plant 345 kV · shared with 1 other requestBig Rooter East, LLCSolar554.7May 2029Signed Jun 2025
Big Rooter East Storage39950 TNP One Plant 345 kV · shared with 1 other requestBig Rooter East, LLCBattery storage (paired with solar)201.0Dec 2029Signed Jun 2025
Stegall SolarElliott (Bus #53) to Franklin (Bus #57) 69kV Transmission LineBT Martin Solar, LLCSolar81.6May 2027In study
Stegall StorageTap connection to a new switching station on the Elliott (Bus #53)...BT Martin Solar, LLCBattery storage (paired with solar)50.5May 2027In study
BRP Mekong BESSTap 345 kV line from Twin Oak Switch (#3400) to TPN One Plant Switc...BRP Mekong BESS LLCBattery storage (stand-alone)409.9Dec 2027In study
Pioneer Path Energy Storage 1Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Pioneer Path Energy Storage 2Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Pioneer Path Energy Storage 3Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Pioneer Path Energy Storage 4Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Prairie Horizon Energy Storage 1Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Prairie Horizon Energy Storage 2Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Prairie Horizon Energy Storage 3Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Prairie Horizon Energy Storage 4Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 · shared with 7 other requestsTempus Power management LLCBattery storage (stand-alone)102.1Dec 2027In study
Buffalo Meadow SolarTap Jack Creek (975) - Twin Oak (3400) 345kV lineBuffalo Meadow Energy Center, LLCSolar251.3Sep 2028In study
Buffalo Prairie StorageTap 345kV 975 Jack Creek - 3400 Twin OakBuffalo Meadow Energy Center, LLCBattery storage (paired with solar)308.0Sep 2028In study
Big Rooter West Storage39950# TNTNP_ONE_3 345 KV · shared with 1 other requestBig Rooter West, LLCBattery storage (paired with solar)201.1Dec 2028In study

Crowded connection points in Robertson County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Tnp One (39950) 345 kV 22 requests · 3,995 MW · 16 in Robertson County, 6 in Milam, Bell10 in study, 5 approved for synchronization, 4 signed; security posted, 3 signed
  • Eastbell Milam Solar 21INR0203 · Solar · 245 MW · Approved for synchronization · Milam
  • Yaupon Solar SLF 24INR0042 · Solar · 201 MW · Approved for synchronization · Milam
  • Eastbell Milam Solar II 24INR0208 · Solar · 151 MW · Approved for synchronization · Milam
  • Hermes Storage 24INR0365 · Battery storage · 100 MW · Approved for synchronization · Bell
  • Hermes Solar 23INR0344 · Solar · 100 MW · Approved for synchronization · Bell
  • Bee Branch IA 23INR0421 · Battery storage · 204 MW · Signed; security posted
  • Tidwell Prairie II Batt 22INR0503 · Battery storage · 204 MW · Signed; security posted
  • Barton Branch IA 22INR0504 · Battery storage · 204 MW · Signed; security posted
  • Yaupon Storage SLF 24INR0169 · Battery storage · 0 MW · Signed; security posted · Milam
  • Big Rooter East Solar 29INR0017 · Solar · 555 MW · Signed Jun 2025
  • Big Rooter West Solar 26INR0431 · Solar · 403 MW · Signed Feb 2025
  • Big Rooter East Storage 29INR0018 · Battery storage · 201 MW · Signed Jun 2025
  • BRP Mekong BESS 24INR0135 · Battery storage · 410 MW · In study
  • Big Rooter West Storage 26INR0432 · Battery storage · 201 MW · In study
  • Pioneer Path Energy Storage 1 27INR0418 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 2 27INR0423 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 3 27INR0424 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 4 27INR0425 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 1 27INR0426 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 2 27INR0427 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 3 27INR0428 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 4 27INR0429 · Battery storage · 102 MW · In study
Twin Oak (3400) 345 kV 14 requests · 2,397 MW11 in study, 3 signed; security posted
  • Bee Branch IA 23INR0421 · Battery storage · 204 MW · Signed; security posted
  • Tidwell Prairie II Batt 22INR0503 · Battery storage · 204 MW · Signed; security posted
  • Barton Branch IA 22INR0504 · Battery storage · 204 MW · Signed; security posted
  • BRP Mekong BESS 24INR0135 · Battery storage · 410 MW · In study
  • Buffalo Prairie Storage 25INR0288 · Battery storage · 308 MW · In study
  • Buffalo Meadow Solar 25INR0331 · Solar · 251 MW · In study
  • Pioneer Path Energy Storage 1 27INR0418 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 2 27INR0423 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 3 27INR0424 · Battery storage · 102 MW · In study
  • Pioneer Path Energy Storage 4 27INR0425 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 1 27INR0426 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 2 27INR0427 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 3 27INR0428 · Battery storage · 102 MW · In study
  • Prairie Horizon Energy Storage 4 27INR0429 · Battery storage · 102 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Robertson County

  • Robertson County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 9, Waco: 6801 Sanger Ave, Ste 2500, Waco TX 76710-7826, 254-751-0335; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Robertson County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Robertson County.

Permits and reviews for Robertson County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Robertson County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Recent local action: At its March 31, 2026 meeting, the Robertson County Commissioners Court held public discussion on a Chapter 312 tax abatement agreement for Buffalo Meadow Energy Center, LLC and then tabled the agreement. At the same meeting the court unanimously approved a resolution requesting the Texas Legislature to grant counties authority to regulate solar, wind, battery storage and data center development. (Robertson County commissioners court minutes; checked October 17, 2026).

How a project in Robertson County connects to the grid

Robertson County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Robertson County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Robertson County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 9

Bell · Bosque · Brazos · Burleson · Coryell · Falls · Freestone · Grimes · Hamilton · Hill · Lampasas · Leon · Limestone · Madison · McLennan · Milam · Mills · San Saba · Washington

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.