Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › For developers › Point of interconnection

Find candidate POIs for your land

57 sourced entries · ERCOT first, with FERC-market notes · Checked October 18, 2026

Start with your land, county, and electricity market. Explore mapped transmission lines, review connection points named in the ERCOT queue, and open the serving operator’s resources. The reference guide below explains how to evaluate a candidate.

Explore POIs for your land

Choose your state and county, or open this page from your land report. Inspect mapped transmission lines and their named endpoints, then review connection points reported in the queue.

Click a transmission line to inspect its voltage, listed owner, and named endpoints where recorded. This map does not include a complete substation inventory or available connection capacity.

Connection points named in the ERCOT queue

September 2026 ERCOT queue snapshot. Names follow the published report; alternate spellings may refer to the same physical point. County is the project's reported county, and the POI can be outside it. These are reported queue locations, not an exhaustive list of possible or available POIs. ERCOT source reports.

Jump to: What the point of interconnection is · Public data for finding candidate lines and substations · Voltage class and the interconnection design · Getting capacity information before and after filing · Reading the queue around a candidate POI · The gen-tie, ownership on each side, and whether a certificate is needed · ERCOT-specific rules that touch the POI · The checklist, step by step

What this page cannot do. It cannot tell you whether a given line has room: in ERCOT that answer comes from the operator's studies after a request is filed, and the planning models are not public. It also does not state a megawatt limit per voltage class, because no operator or utility document does. The prose here carries no figures of its own; every number sits in a quoted entry with its document.

1. What the point of interconnection is

The POI is a contractual and physical point, not a line on a map: it is where the generator's facilities end and the transmission provider's begin, and it is defined in the interconnection agreement. ERCOT and FERC-jurisdictional markets define it in similar terms, and both separate it from the point where ownership changes hands. Everything else on this page follows from where that point is placed.

2. Public data for finding candidate lines and substations

Before anything is filed, the candidates come from public map and tabular data. Each source below does one job and has limits the entries state: the federal transmission layer shows lines, not room to connect; the EIA forms show existing and planned plants; ERCOT's monthly status report shows every request already in the queue with its POI; parcel data shows who holds the substation site. The planning models that would answer the capacity question directly are not public.

  • ERCOT publishes a monthly, public Generator Interconnection Status (GIS) Report (data product PG7-200-ER) covering planned generation resources in the interconnection process.
    “View the latest public interconnection information on planned generation resources in the ERCOT Region.”
    ERCOT Resource Adequacy page (GIS Report, data product PG7-200-ER) · 2026-10-18
  • Since March 2026 ERCOT's monthly GIS file series also includes TSP-reported interconnection costs for transmission-connected generators that received an initial energization date in the prior month (data product pg7-201-er).
    “Interconnection Cost Reporting for Transmission-Connected Generators in the ERCOT region.”
    ERCOT Resource Adequacy page (GIS Report for Transmission Interconnection Costs, pg7-201-er) · 2026-10-18
  • The monthly GIS report includes the financial security amount, added by PGRR088 ('Include Financial Security Amount in the Monthly Generator Interconnection Status Report').
    “Include Financial Security Amount in the Monthly Generator Interconnection Status Report”
    ERCOT approved PGRR list, PGRR088 (title) · 2020-09-28
  • ERCOT's SSWG steady-state base cases (the planning models used for interconnection screening) are available to registered Market Participants, not to the general public.
    “The base cases created by the Steady-State Working Group (SSWG) and System Protection Working Group (SPWG) are available for use by Market Participants.”
    ERCOT Planning Guide (complete PDF, August 1, 2026), Section 4.1(7) · 2026-08-01
  • The HIFLD transmission lines layer (Oak Ridge National Laboratory for the HIFLD Subcommittee) covers lines from 69 kV to 765 kV; where no authoritative source existed, geometry was digitized from imagery, and no topology tests were run.
    “Lines are operated at relatively high voltages varying from 69 kV up to 765 kV”
    HIFLD 'Transmission_Lines' ISO-19139 metadata (originator Oak Ridge National Laboratory; publication 2024-09-30) · 2024-09-30
  • Form EIA-860 collects generator-level data for existing and planned generators at plants of 1 MW or more; it is annual (final 2025 data released September 10, 2026) and its data files include Utility, Plant and Generator files, among others.
    “collects generator-level specific information about existing and planned generators”
    U.S. EIA, Form EIA-860 Annual Electric Generator Report · 2026-09-10
  • EIA-860M (Preliminary Monthly Electric Generator Inventory) tracks existing and proposed units monthly, but its capacities are preliminary estimates, not commitments.
    “reported capacities are EIA's preliminary estimates of capacity for that month.”
    U.S. EIA, Preliminary Monthly Electric Generator Inventory (EIA-860M) · 2026-09-24
  • The PUCT's published CCN GIS downloads cover only retail water and sewer service areas; electric transmission-line CCN routes are not offered as a statewide GIS layer on that page.
    “PUCT's official digital mapping data includes certificated service areas for retail water and sewer utilities.”
    PUCT, CCN Mapping Information · 2026-10-18
  • Texas statewide parcel data (TxGIO StratMap Land Parcels) is compiled from county appraisal districts, refreshed roughly annually, and is explicitly not survey grade.
    “They are not survey grade and should not be used for legal purposes.”
    Texas Geographic Information Office (TxGIO), StratMap Land Parcels · 2026-10-18
  • USGS 3DEP 1/3 arc-second DEMs (about 10 m resolution) provide seamless terrain elevation for the conterminous U.S., useful for gen-tie routing and site grading screens.
    “1/3 arc-second (approximately 10 m) resolution”
    USGS National Map 3DEP, 1/3rd arc-second Digital Elevation Models (DEMs) collection (data.gov record) · 2025-02-14

3. Voltage class and the interconnection design

ERCOT's transmission system starts at the voltage its planning criteria set, and the utilities build interconnections at three nominal classes. No ERCOT or utility document states a rule of thumb for how many megawatts each class can take; the capacity is fixed in the agreement after study. What the utility standards do say is how the connection is built: a radial dead-end at a utility-owned structure in one territory, a loop-in to a new ring-bus substation in a real agreement in another, and breakers rated for the fault current at the point.

4. Getting capacity information before and after filing

In ERCOT the capacity answer comes from the operator's own studies, in a fixed order, after a request is accepted; the request itself asks for the POI as a county, coordinates, a description and a voltage, with proof of site control. Utilities will not begin design on their side until the agreement is signed, so early conversations with the utility are informational. FERC-jurisdictional markets took a different path after Order 2023: public heat maps and screening tools that show headroom before a cluster window opens, with the caveats each tool states.

5. Reading the queue around a candidate POI

A request joins whatever is already studied at that point. ERCOT treats interconnection-driven transmission work differently from other grid projects, two projects can share one POI under a contractual cap, and screening constraints can rule a point out before capacity is even the question. The county pages on this site list every ERCOT request by POI and stage, which is where this reading starts.

6. The gen-tie, ownership on each side, and whether a certificate is needed

The agreement decides who builds and owns what on each side of the POI and who provides right-of-way. In Texas, whether a generator's own line needs a certificate of convenience and necessity comes from reading several provisions together rather than one sentence; the entries below give each provision so the combination can be checked.

7. ERCOT-specific rules that touch the POI

Three sets of rules change how a POI is used after it is chosen: the commissioning time limit that runs from synchronization approval, the large-load law and its study process for data centers that want to sit at a generator's point, and the notice required before a co-location arrangement. Batteries follow the same section as generators.

8. The checklist, step by step

The order a developer follows, each step pointing at the sourced entries above. The entries in this section are the few steps that carry a sourced statement of their own; the rest of the procedure is in the numbered list that follows them.

  1. Fix the site, then look outward. With the parcel outline known, run the land report for the point and open the map with the transmission layer on. Note every mapped line within a few miles and its listed voltage, remembering the layer's vintage (section 2).
  2. Sort the candidates by voltage class. Keep the lines at or above the transmission floor and name each one's nominal class from the utility's own standard, not from the federal map alone (section 3).
  3. Find the substations and who owns them. Use the existing-plant and planned-plant data for interconnections already built nearby, and the parcel layer for the substation site owner, which tells you which utility to call (section 2).
  4. Read the queue at each candidate. Open the county page and list every request on the same POI with its stage and size; a crowded point is studied as a group and the agreement at a shared point can cap combined output (section 5).
  5. Screen out the constraints that are not about capacity. Screening-stage constraints can remove a point before capacity is studied (the Security Screening Study entry in section 4); the large-load rules matter if a data center is part of the plan (section 7).
  6. Talk to the utility, knowing what it can and cannot say. The utility's standard describes how it will build the connection; it will not design until the agreement is signed, and the planning cases it works from are not public (section 4).
  7. Price the gen-tie and the right-of-way. Decide the route from the plant to each candidate POI, who owns each side, and what easements the agreement will ask you to provide; check the certificate question for your own line against the provisions listed (section 6).
  8. File with the POI stated the way the form asks, with site control in hand, and let the operator's studies settle the capacity and the cost; keep the schedule in view, including the time limit that runs after synchronization (section 4, section 7).
  9. In a FERC-jurisdictional market, do steps 1–7 against that operator's heat map or screening tool before the cluster window, and meet the site-control and deposit rules the window requires (section 4).

How this page was made

Each entry is one claim tied to one document (ERCOT's Planning Guide and market notices, interconnection agreements filed at the PUCT, utility interconnection standards, FERC's pro forma procedures and explainer, operator tool guides, Texas statutes and rules, and federal data documentation), with the document's words quoted beneath it. A second, independent pass loaded every linked document and kept only the entries it supports. Several ERCOT documents are published as Word files that could not be read for this pass, so the Planning Guide's Section 5 is quoted only from its table of contents, and the fee schedule and the status report's column legend are described, not quoted; the links lead to them. Nothing here is legal or engineering advice. Found an error? Say so.

Related: Interconnection by market · Development schedule with leads and lags · ERCOT queue by county · Substation vs. transmission line · How close to power lines.