Runnels County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects8
Total capacity1,803MW
Signed agreements2of 8
New since August0requests

8 proposed energy projects from ERCOT's September 2026 report, plus who to call in Runnels County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.

Check land in Runnels CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Runnels County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Runnels County?

ERCOT's September 2026 interconnection report lists 8 proposed energy projects in Runnels County (5 solar and 3 battery storage), about 1,803 MW in all. 2 of the 8 have a signed interconnection agreement, and 1 has been approved for energization or synchronization.

What stands out in Runnels County

By capacity, solar leads in Runnels County with 1,234 MW across 5 projects, followed by battery storage (3 projects, 569 MW). The largest single project is Mistflower Energy Center Solar, a 402 MW solar project listed under Mistflower Energy Center LLC, still in study, and its target online date is Jun 2030. Of the 8, 6 are still in ERCOT's study process, 1 has posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 345 kV (6 projects) and 138 kV (2 projects) (why the voltage matters). Mistflower Energy Center LLC is listed on the most projects here (2 of 8); 7 different companies appear in all. Target online dates for the projects not yet running span Mar 2028 to Sep 2030. All of them fall in ERCOT's West load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Norton Solar60451 Garnet 138kVTAI Norton Solar, LLCSolar128.5Nov 2025Approved for synchronization
Rutile BESSTap 138kV 6340 BALLINGER - 60399 WEISSRutile BESS, LLCBattery storage (stand-alone)100.7Mar 2028Signed; security posted
Winters Glow Solartap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF · shared with 1 other requestWinters Glow Solar, LLCSolar301.6Apr 2029In study
Winters Glow Storagetap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF · shared with 1 other requestWinters Glow Storage, LLCBattery storage (paired with solar)155.2Apr 2029In study
Mistflower Energy Center SolarTap 345kV 60072 ODYSSEUS7A– 60040 BLF_CRK7AMistflower Energy Center LLCSolar401.6Jun 2030In study
Mistflower Energy Center StorageTap 345kV 60072 Odysseus – 60040 Bluff CreekMistflower Energy Center LLCBattery storage (paired with solar)312.9Jun 2030In study
Sawtooth SolarTap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) lineSawtooth Solar, LLCSolar201.4Aug 2030In study
Zuma SolarTap 345kV 11263 Fisk Switch - 11406 Central Bluff SwitchZuma Solar, LLCSolar201.4Sep 2030In study

Crowded connection points in Runnels County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Central Bluff (11406) 345 kV 8 requests · 1,873 MW · 3 in Runnels County, 5 in Taylor, Coleman, Nolan7 in study, 1 signed; security posted
  • Hanson Solar 23INR0086 · Solar · 399 MW · Signed; security posted · Coleman
  • Winters Glow Solar 28INR0198 · Solar · 302 MW · In study
  • Forts Trail BESS 24INR0341 · Battery storage · 209 MW · In study · Taylor
  • Forts Trail BESS 2 24INR0488 · Battery storage · 206 MW · In study · Taylor
  • Zuma Solar 30INR0076 · Solar · 201 MW · In study
  • Forts Trail Solar 24INR0308 · Solar · 201 MW · In study · Taylor
  • Sagebrush Wind 28INR0386 · Wind · 200 MW · In study · Nolan
  • Winters Glow Storage 28INR0199 · Battery storage · 155 MW · In study
Odysseus (60072) 345 kV 4 requests · 1,067 MW · 3 in Runnels County, 1 in Coke3 in study, 1 approved for energization
  • Ulysses Solar 21INR0253 · Solar · 151 MW · Approved for energization · Coke
  • Mistflower Energy Center Solar 30INR0088 · Solar · 402 MW · In study
  • Mistflower Energy Center Storage 30INR0089 · Battery storage · 313 MW · In study
  • Sawtooth Solar 29INR0210 · Solar · 201 MW · In study
Bluff Creek (60040) 345 kV 10 requests · 3,121 MW · 3 in Runnels County, 7 in Coleman, Taylor10 in study
  • Dog Star Solar I 27INR0503 · Solar · 499 MW · In study · Taylor
  • Dog Star Solar II 27INR0504 · Solar · 499 MW · In study · Taylor
  • Mistflower Energy Center Solar 30INR0088 · Solar · 402 MW · In study
  • Mistflower Energy Center Storage 30INR0089 · Battery storage · 313 MW · In study
  • Paintbrush PV1 28INR0469 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV2 28INR0470 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV3 29INR0220 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV4 29INR0221 · Solar · 252 MW · In study · Coleman
  • Sawtooth Solar 29INR0210 · Solar · 201 MW · In study
  • Paintbrush BESS1 29INR0222 · Battery storage · 201 MW · In study · Coleman
Brown (1444) 345 kV 19 requests · 4,694 MW · 2 in Runnels County, 17 in Brown, Coleman, Mills15 in study, 3 signed; security posted, 1 approved for synchronization
  • Priddy Wind 16INR0085 · Wind · 302 MW · Approved for synchronization · Mills
  • Hanson Solar 23INR0086 · Solar · 399 MW · Signed; security posted · Coleman
  • Chisme Storage 24INR0331 · Battery storage · 151 MW · Signed; security posted · Brown
  • Chisme Solar 24INR0333 · Solar · 147 MW · Signed; security posted · Brown
  • Brookesmith Storage 28INR0166 · Battery storage · 351 MW · In study · Brown
  • Mountaineer Solar 21INR0294 · Solar · 329 MW · In study · Brown
  • Soluce Bravo Storage 28INR0270 · Battery storage · 303 MW · In study · Brown
  • Winters Glow Solar 28INR0198 · Solar · 302 MW · In study
  • Horseshoe Bend Solar 19INR0075 · Solar · 301 MW · In study · Brown
  • Nouveau BESS 27INR0291 · Battery storage · 256 MW · In study · Brown
  • Paintbrush PV1 28INR0469 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV2 28INR0470 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV3 29INR0220 · Solar · 252 MW · In study · Coleman
  • Paintbrush PV4 29INR0221 · Solar · 252 MW · In study · Coleman
  • Clapton Storage 26INR0430 · Battery storage · 209 MW · In study · Mills
  • Paintbrush BESS1 29INR0222 · Battery storage · 201 MW · In study · Coleman
  • Clapton Solar 26INR0238 · Solar · 201 MW · In study · Mills
  • Winters Glow Storage 28INR0199 · Battery storage · 155 MW · In study
  • Soluce Bravo Solar 28INR0269 · Solar · 81 MW · In study · Brown

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Runnels County

  • Runnels County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Runnels County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Runnels County.

Permits and reviews for Runnels County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Runnels County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Runnels County connects to the grid

Runnels County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Runnels County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Runnels County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 3

Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.