Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › DeWitt County

DeWitt County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects5
Total capacity972MW
Signed agreements2of 5
New since August0requests

5 proposed energy projects from ERCOT's September 2026 report, plus who to call in DeWitt County and in TCEQ Region 14 before signing a solar, wind, or battery storage lease.

Check land in DeWitt CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for DeWitt County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in DeWitt County?

ERCOT's September 2026 interconnection report lists 5 proposed energy projects in DeWitt County (3 solar and 2 battery storage), about 972 MW in all. 2 of the 5 have a signed interconnection agreement.

What stands out in DeWitt County

By capacity, solar leads in DeWitt County with 616 MW across 3 projects, followed by battery storage (2 projects, 356 MW). The largest single project is Shaula I BESS, a 206 MW battery storage paired with solar project listed under Shaula Energy Project LLC, still in study, and its target online date is Jun 2028. Of the 5, 3 are still in ERCOT's study process and 2 have posted security or started construction. Connection points are mostly at 345 kV (4 projects) and 138 kV (1 project) (why the voltage matters). The single most-used connection point is tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1, shared by 3 projects. Each of the 5 projects is listed under a different company. Target online dates for the projects not yet running span Dec 2025 to Dec 2028. All of them fall in ERCOT's South load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Shaula I Solartap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1 · shared with 2 other requestsShaula Energy Project, LLCSolar205.2Jun 2028Signed; security posted
Shaula II Solartap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1 · shared with 2 other requestsShaula Energy Project II, LLCSolar205.2Jun 2028Signed; security posted
Shaula III Solartap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1 · shared with 2 other requestsShaula Energy Project III, LLCSolar205.2Dec 2025 date passed; status per ERCOTIn study
Shaula I BESS5380 Shaula 345kVShaula Energy Project LLCBattery storage (paired with solar)205.8Jun 2028In study
Yorktown BESS(#78575) LCRA Yorktown 138 kVNavitas Energy LLCBattery storage (stand-alone)150.5Dec 2028In study

Crowded connection points in DeWitt County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Elm Creek (5133) 345 kV 19 requests · 4,695 MW · 3 in DeWitt County, 16 in Wilson, Gonzales, Guadalupe12 in study, 7 signed; security posted
  • Clear Fork Creek Solar 23INR0027 · Solar · 602 MW · Signed; security posted · Wilson
  • Anila BESS 26INR0077 · Battery storage · 209 MW · Signed; security posted · Wilson
  • Shaula I Solar 22INR0251 · Solar · 205 MW · Signed; security posted
  • Shaula II Solar 22INR0267 · Solar · 205 MW · Signed; security posted
  • Nockenut Springs Solar 2 24INR0007 · Solar · 203 MW · Signed; security posted · Guadalupe
  • Nockenut Springs Solar 1 23INR0088 · Solar · 203 MW · Signed; security posted · Guadalupe
  • Anila Solar 26INR0074 · Solar · 201 MW · Signed; security posted · Wilson
  • Mojo Solar 28INR0250 · Solar · 528 MW · In study · Wilson
  • Wilson Gas Plant 28INR0494 · Gas engines · 403 MW · In study · Wilson
  • Columbine Wind 29INR0063 · Wind · 295 MW · In study · Gonzales
  • Nockenut Springs Storage 2 29INR0319 · Battery storage · 209 MW · In study · Wilson
  • Nockenut Springs Storage 3 29INR0320 · Battery storage · 209 MW · In study · Wilson
  • Nockenut Springs Storage 1 29INR0318 · Battery storage · 209 MW · In study · Wilson
  • Shaula III Solar 23INR0009 · Solar · 205 MW · In study
  • Marcelina Storage 23INR0318 · Battery storage · 203 MW · In study · Wilson
  • Nockenut Springs Solar 3 25INR0010 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 4 25INR0193 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 5 25INR0280 · Solar · 201 MW · In study · Gonzales
  • Cachena Storage SLF 23INR0077 · Battery storage · 0 MW · In study · Wilson
STP (5915) 345 kV 17 requests · 5,264 MW · 3 in DeWitt County, 14 in Matagorda, Gonzales, Guadalupe8 signed; security posted, 6 in study, 2 signed, 1 approved for synchronization
  • Charger Solar 23INR0047 · Solar · 397 MW · Approved for synchronization · Refugio
  • Duffy Solar 23INR0057 · Solar · 502 MW · Signed; security posted · Matagorda
  • Duffy BESS 26INR0250 · Battery storage · 241 MW · Signed; security posted · Matagorda
  • Shaula I Solar 22INR0251 · Solar · 205 MW · Signed; security posted
  • Shaula II Solar 22INR0267 · Solar · 205 MW · Signed; security posted
  • Nockenut Springs Solar 2 24INR0007 · Solar · 203 MW · Signed; security posted · Guadalupe
  • Nockenut Springs Solar 1 23INR0088 · Solar · 203 MW · Signed; security posted · Guadalupe
  • Eldora BESS 24INR0338 · Battery storage · 201 MW · Signed; security posted · Matagorda
  • Eldora Solar 24INR0337 · Solar · 201 MW · Signed; security posted · Matagorda
  • Oak Tree Energy Storage 27INR0091 · Battery storage · 310 MW · Signed May 2026 · Lavaca
  • Iguala Solar 23INR0090 · Solar · 250 MW · Signed Jul 2025 · Victoria
  • STP Unit2 High Pressure Turbine Upgrade 27INR0557 · Nuclear · 1,337 MW · In study · Matagorda
  • Shaula III Solar 23INR0009 · Solar · 205 MW · In study
  • Nockenut Springs Solar 3 25INR0010 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 4 25INR0193 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 5 25INR0280 · Solar · 201 MW · In study · Gonzales
  • Percy Farm Solar 24INR0020 · Solar · 199 MW · In study · Matagorda

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in DeWitt County

  • DeWitt County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 14, Corpus Christi: 500 North Shoreline Blvd, Ste 500, Corpus Christi TX 78401-0318, 361-881-6900; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • DeWitt County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for DeWitt County.

Permits and reviews for DeWitt County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in DeWitt County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in DeWitt County connects to the grid

DeWitt County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in DeWitt County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in DeWitt County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 14

Aransas · Bee · Calhoun · Goliad · Gonzales · Jackson · Jim Wells · Kleberg · Lavaca · Live Oak · Nueces · Refugio · San Patricio · Victoria

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.

Browse resources