Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Webb County

Webb County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects19
Total capacity4,271MW
Signed agreements6of 19
New since August0requests

19 proposed energy projects from ERCOT's September 2026 report, plus who to call in Webb County and in TCEQ Region 16 before signing a solar, wind, or battery storage lease.

Check land in Webb CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Webb County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Webb County?

ERCOT's September 2026 interconnection report lists 19 proposed energy projects in Webb County (7 solar, 2 wind and 10 battery storage), about 4,271 MW in all. 6 of the 19 have a signed interconnection agreement, and 1 has been approved for energization or synchronization.

What stands out in Webb County

By capacity, battery storage leads in Webb County with 1,644 MW across 10 projects, followed by solar (7 projects, 1,642 MW) and wind (2 projects, 986 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Outpost Storage, a 508 MW battery storage paired with solar project listed under Hecate Energy Outpost Storage LLC, still in study, and its target online date is Mar 2028. Of the 19, 13 are still in ERCOT's study process, 2 have a signed interconnection agreement but no security posted yet, 3 have posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 345 kV (17 projects) and 138 kV (2 projects) (why the voltage matters). The single most-used connection point is 80219 Lobo 345kV, shared by 3 projects. DGC Renewables, LLC is listed on the most projects here (4 of 19); 14 different companies appear in all. Target online dates for the projects not yet running span Dec 2027 to Dec 2029. All of them fall in ERCOT's South load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Torrecillas BESS161257 Torrecillas 345kVTorrecillas Interconnect, LLCBattery storage (stand-alone)9.9Dec 2026Approved for synchronization
Corvus SolarTap 345kV Cenzio (#80219) - Lobo (#80220)Corvus Solar, LLCSolar201.5Nov 2028Signed; security posted
Cuchillas Solar80219 Lobo 345kV · shared with 2 other requestsGransolar Texas Two, LLCSolar305.6Dec 2028Signed; security posted
Siete345kV 8718 Triada · shared with 1 other requestApex Clean EnergyWind492.8Mar 2029Signed; security posted
Corazon Solar Phase II80219 Lobo 345kV · shared with 2 other requestsBAYWA R.E. SOLAR PROJECTSSolar203.9Jun 2028Signed Aug 2020
Cenizo SolarTap 345 kV 80220 Cenizo - 80079 Cruce Ckt 2Cenizo Energy Center LLCSolar301.4Dec 2029Signed Sep 2026
Becerra Creek Storage 1345 kV Cenizo Substation (#80220) · shared with 1 other requestBordas Renewable Energy, LLCBattery storage (stand-alone)125.6Dec 2027In study
Becerra Creek Storage 2345 kV Cenizo Substation (#80220) · shared with 1 other requestBordas Renewable Energy, LLCBattery storage (stand-alone)125.6Dec 2027In study
Bravo BESSTap 345kV 80220 CENIZO7A - 80224 TIEMPO7ABravo BESS LLCBattery storage (stand-alone)207.4Dec 2027In study
Siete Wind345kV 8718 Triada · shared with 1 other requestSiete Wind, LLCWind492.8Jan 2028In study
Outpost Storage345kv Avanzada7A (80235)Hecate Energy Outpost Storage LLCBattery storage (paired with solar)508.1Mar 2028In study
Diamond Sage BESS 1tap 345kV 80219 LOBO7A - 5709 FOWLERTONSW5 CKT2DGC Renewables, LLCBattery storage (paired with solar)103.5Oct 2028In study
Diamond Sage BESS 2Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709) · shared with 1 other requestDGC Renewables, LLCBattery storage (paired with solar)103.5Oct 2028In study
Diamond Sage Solar 1tap 345kV 80219 LOBO7A - 5709 FOWLERDGC Renewables, LLCSolar214.0Oct 2028In study
Diamond Sage Solar 2Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709) · shared with 1 other requestDGC Renewables, LLCSolar214.0Oct 2028In study
Cuchillas BESS80219 Lobo 345kV · shared with 2 other requestsGransolar Texas TwoBattery storage (paired with solar)306.9Dec 2028In study
Pradera Storagetap 345 kV Lobo 80219 - Fowlerton 5709 ckt #2Pradera Storage, LLCBattery storage (stand-alone)153.1Jun 2029In study
El Molino Solar SLFTap 138kV 80439 LaQuinta - 8297 Bruni 8297 · shared with 1 other requestEl Molino Solar, LLCSolar201.3Sep 2029In study
El Molino Storage SLFTap 138kV 80439 LaQuinta - 8297 Bruni 8297 · shared with 1 other requestEl Molino Solar, LLCBattery storage (paired with solar)Self-limitingSep 2029In study

Crowded connection points in Webb County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Lobo (80219) 345 kV 11 requests · 2,827 MW · 9 in Webb County, 2 in La Salle7 in study, 3 signed; security posted, 1 signed
  • La Salle Solar 26INR0088 · Solar · 513 MW · Signed; security posted · La Salle
  • Cuchillas Solar 24INR0059 · Solar · 306 MW · Signed; security posted
  • Corvus Solar 27INR0126 · Solar · 202 MW · Signed; security posted
  • Corazon Solar Phase II 22INR0257 · Solar · 204 MW · Signed Aug 2020
  • Crescent C BESS 26INR0089 · Battery storage · 508 MW · In study · La Salle
  • Cuchillas BESS 27INR0077 · Battery storage · 307 MW · In study
  • Diamond Sage Solar 1 27INR0390 · Solar · 214 MW · In study
  • Diamond Sage Solar 2 27INR0395 · Solar · 214 MW · In study
  • Pradera Storage 23INR0183 · Battery storage · 153 MW · In study
  • Diamond Sage BESS 1 27INR0414 · Battery storage · 104 MW · In study
  • Diamond Sage BESS 2 27INR0444 · Battery storage · 104 MW · In study
Fowlerton (5709) 345 kV 12 requests · 2,773 MW · 5 in Webb County, 7 in Atascosa, La Salle, McMullen10 in study, 2 signed; security posted
  • La Salle Solar 26INR0088 · Solar · 513 MW · Signed; security posted · La Salle
  • Miranda Solar Project 24INR0161 · Solar · 262 MW · Signed; security posted · McMullen
  • Crescent C BESS 26INR0089 · Battery storage · 508 MW · In study · La Salle
  • Diamond Sage Solar 1 27INR0390 · Solar · 214 MW · In study
  • Diamond Sage Solar 2 27INR0395 · Solar · 214 MW · In study
  • Amphion Solar Phase 2 28INR0343 · Solar · 206 MW · In study · Atascosa
  • Amphion Storage 29INR0214 · Battery storage · 200 MW · In study · Atascosa
  • Amphion Solar Phase 1 29INR0050 · Solar · 181 MW · In study · Atascosa
  • Pradera Storage 23INR0183 · Battery storage · 153 MW · In study
  • Amphion Solar Phase 3 28INR0344 · Solar · 115 MW · In study · Atascosa
  • Diamond Sage BESS 1 27INR0414 · Battery storage · 104 MW · In study
  • Diamond Sage BESS 2 27INR0444 · Battery storage · 104 MW · In study
Cenizo (80220) 345 kV 7 requests · 1,807 MW · 5 in Webb County, 2 in Jim Hogg3 in study, 3 signed; security posted, 1 signed
  • Mirando Valley Wind 28INR0072 · Wind · 479 MW · Signed; security posted · Jim Hogg
  • Viento Bravo Wind 28INR0434 · Wind · 367 MW · Signed; security posted · Jim Hogg
  • Corvus Solar 27INR0126 · Solar · 202 MW · Signed; security posted
  • Cenizo Solar 29INR0219 · Solar · 301 MW · Signed Sep 2026
  • Bravo BESS 27INR0398 · Battery storage · 207 MW · In study
  • Becerra Creek Storage 1 26INR0024 · Battery storage · 126 MW · In study
  • Becerra Creek Storage 2 27INR0003 · Battery storage · 126 MW · In study
Triada (8718) 345 kV 2 requests · 986 MW1 signed; security posted, 1 in study
  • Siete 20INR0047 · Wind · 493 MW · Signed; security posted
  • Siete Wind 27INR0536 · Wind · 493 MW · In study
Laquinta (80439) 138 kV 2 requests · 201 MW2 in study
  • El Molino Solar SLF 25INR0321 · Solar · 201 MW · In study
  • El Molino Storage SLF 25INR0322 · Battery storage · 0 MW · In study
Bruni (8297) 138 kV 4 requests · 638 MW · 2 in Webb County, 2 in Duval4 in study
  • Allthorn Solar 28INR0229 · Solar · 232 MW · In study · Duval
  • Allthorn BESS 28INR0230 · Battery storage · 205 MW · In study · Duval
  • El Molino Solar SLF 25INR0321 · Solar · 201 MW · In study
  • El Molino Storage SLF 25INR0322 · Battery storage · 0 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Webb County

  • Webb County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 16, Laredo: 707 E Calton Rd, Ste 304, Laredo TX 78041-3887, 956-791-6611; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Webb County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Webb County.

Permits and reviews for Webb County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Webb County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Recent local action: The Webb County Commissioners Court's March 25, 2024 agenda packet included a draft order designating the Webb County Cedro Hill Wind Reinvestment Zone Number 1, with adoption language dated March 25, 2024. The posted order is unsigned and does not name a developer or record a vote. (Webb County commissioners court agenda document (reinvestment zone order); checked October 17, 2026).

How a project in Webb County connects to the grid

Webb County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Webb County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Webb County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 16

Dimmit · Duval · Kinney · La Salle · Maverick · McMullen · Val Verde · Zapata · Zavala

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.