Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Zapata County

Zapata County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects27
Total capacity6,291MW
Signed agreements5of 27
New since August0requests

27 proposed energy projects from ERCOT's September 2026 report, plus who to call in Zapata County and in TCEQ Region 16 before signing a solar, wind, or battery storage lease.

Check land in Zapata CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Zapata County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Zapata County?

ERCOT's September 2026 interconnection report lists 27 proposed energy projects in Zapata County (10 solar, 9 wind and 8 battery storage), about 6,291 MW in all. 5 of the 27 have a signed interconnection agreement.

What stands out in Zapata County

By capacity, solar leads in Zapata County with 2,283 MW across 10 projects, followed by battery storage (8 projects, 2,034 MW) and wind (9 projects, 1,974 MW). The largest single project is Falcon BESS, a 517 MW battery storage paired with solar project listed under Falcon Energy Project, LLC, still in study, and its target online date is Dec 2029. Of the 27, 22 are still in ERCOT's study process and 5 have posted security or started construction. Connection points are mostly at 345 kV (20 projects) and 138 kV (7 projects) (why the voltage matters). Vaquero Wind Energy, LLC is listed on the most projects here (4 of 27); 17 different companies appear in all. Target online dates for the projects not yet running span Jan 2027 to Feb 2032. All of them fall in ERCOT's South load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Cascabel Wind 1345 kV Rapido Substation (New ETT Substation) tapping the existing...Vaquero Wind Energy, LLCWind197.8Dec 2027Signed; security posted
Cascabel Wind 2345 kV Rapido Substation (New ETT Substation) tapping the existing...Vaquero Wind Energy, LLCWind197.8Dec 2027Signed; security posted
Corralitos Wind 1Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation) · shared with 1 other requestVaquero Wind Energy, LLCWind196.1Dec 2027Signed; security posted
Corralitos Wind 2Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation) · shared with 1 other requestVaquero Wind Energy, LLCWind195.4Dec 2027Signed; security posted
Falcon Zapata Storage 138Tap 138kV 8299 Zapata - 8957 LopenoFalcon BESS, LLCBattery storage (stand-alone)200.8Mar 2028Signed; security posted
Vaquero 1 Windtap 345kV 8905 N Edinb - 8455 Lon HillEnerverseWind400.0Jan 2027In study
Sierra Madre Solartap 345kV 80307 Del Sol - 80225 CenizoSierra Madre Solar LLCSolar255.2Dec 2027In study
Zelus BESSthe 138 kV Zapata Substation (#8299; AEP)BRP Zelus BESS LLCBattery storage (stand-alone)201.0Dec 2027In study
Rancho Grande Solar345 kV Tiempo Substation #80224Bordas Renewable Energy, LLCSolar251.6May 2028In study
Barrosos Creek Wind 3#80227 Rapido 345 kV · shared with 1 other requestCascabel Wind Energy, LLCWind197.8May 2028In study
Barrosos Creek Wind 4#80227 Rapido 345 kV · shared with 1 other requestCascabel Wind Energy, LLCWind197.8May 2028In study
Corralitos Wind 3ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C -... · shared with 1 other requestLas Crestas Wind Energy, LLCWind196.1May 2028In study
Corralitos Wind 4ETT 345 kV Tiempo #80224 Substation (Tap on 345kV 80225 CENIZO7C -... · shared with 1 other requestLas Crestas Wind Energy, LLCWind195.4May 2028In study
Freedom Falcon BESSTap 345kV #80224 Tiempo - #80227 RapidoFalcon BESS, LLCBattery storage (stand-alone)501.9Aug 2028In study
Quarter Ranch Solar80223 Cenizo Substation 345kVGransolar Texas Three LLCSolar154.1Oct 2028In study
Big River BESStap 138kV 8299 Zapata - 8957 Lopeno4A · shared with 1 other requestRio Grande River Solar LLCBattery storage (paired with solar)51.3Dec 2028In study
Big River Solartap 138kV 8299 Zapata - 8957 Lopeno4A · shared with 1 other requestRio Grande River Solar LLCSolar104.3Dec 2028In study
La Morena Energy Center BESSTap 345 kV 80225 CENIZO7C - 80307 DELSOL7CAdapture Solar DevelopmentBattery storage (paired with solar)250.0May 2029In study
La Morena Energy Center SolarTap 345 kV (80225) CENIZO7C - (80307) DELSOL7CAdapture Solar DevelopmentSolar250.0May 2029In study
Tetris SolarTAP 345kV 80307 Del Sol 7C - 80225 Cenizo 7CNextEra Energy Interconnection Holdings LLCSolar359.0Jul 2029In study
Falcon BESSTap 345kV #80225 CENIZO to #80307 DEL SOLFalcon Energy Project, LLCBattery storage (paired with solar)516.7Dec 2029In study
Falcon SolarTap 345kV #80225 Cenizo7C to #80307 Del Sol7CFalcon Energy Project, LLCSolar502.0Dec 2029In study
Wallflower Energy StorageTap the 345 kV Cenizo (#80225) - Del Sol (#80307) lineWallflower Energy StorageBattery storage (paired with solar)209.2Dec 2029In study
Wallflower SolarTap the 345 kV Cenizo (#80225) - Del Sol (#80307) line.Wallflower Solar, LLCSolar201.2Dec 2029In study
Slate Solar ProjectTap 138kV 8646 Rio Bravo - 8985 San YgancioIgnis TX Solar Three LLCSolar104.9Jan 2030In study
Falcon II BESS8004 Revilla 138 kV · shared with 1 other requestFalcon Energy ProjectBattery storage (paired with solar)103.3Feb 2032In study
Falcon II Solar8004 Revilla 138 kV · shared with 1 other requestFalcon Energy ProjectSolar100.3Feb 2032In study

Crowded connection points in Zapata County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

CENIZO7C (80225) 345 kV 16 requests · 4,321 MW · 14 in Zapata County, 2 in Jim Hogg12 in study, 4 signed; security posted
  • Cascabel Wind 2 23INR0561 · Wind · 198 MW · Signed; security posted
  • Cascabel Wind 1 24INR0424 · Wind · 198 MW · Signed; security posted
  • Corralitos Wind 1 24INR0505 · Wind · 196 MW · Signed; security posted
  • Corralitos Wind 2 24INR0506 · Wind · 195 MW · Signed; security posted
  • Falcon BESS 29INR0169 · Battery storage · 517 MW · In study
  • Falcon Solar 28INR0317 · Solar · 502 MW · In study
  • Tetris Solar 28INR0005 · Solar · 359 MW · In study
  • Barranca Wind 1 28INR0375 · Wind · 301 MW · In study · Jim Hogg
  • Barranca Wind 2 28INR0376 · Wind · 299 MW · In study · Jim Hogg
  • Sierra Madre Solar 23INR0006 · Solar · 255 MW · In study
  • La Morena Energy Center BESS 30INR0042 · Battery storage · 250 MW · In study
  • La Morena Energy Center Solar 30INR0043 · Solar · 250 MW · In study
  • Wallflower Energy Storage 30INR0093 · Battery storage · 209 MW · In study
  • Wallflower Solar 30INR0092 · Solar · 201 MW · In study
  • Corralitos Wind 3 28INR0339 · Wind · 196 MW · In study
  • Corralitos Wind 4 28INR0340 · Wind · 195 MW · In study
Del Sol (80307) 345 kV 14 requests · 3,930 MW · 12 in Zapata County, 2 in Jim Hogg10 in study, 4 signed; security posted
  • Cascabel Wind 2 23INR0561 · Wind · 198 MW · Signed; security posted
  • Cascabel Wind 1 24INR0424 · Wind · 198 MW · Signed; security posted
  • Corralitos Wind 1 24INR0505 · Wind · 196 MW · Signed; security posted
  • Corralitos Wind 2 24INR0506 · Wind · 195 MW · Signed; security posted
  • Falcon BESS 29INR0169 · Battery storage · 517 MW · In study
  • Falcon Solar 28INR0317 · Solar · 502 MW · In study
  • Tetris Solar 28INR0005 · Solar · 359 MW · In study
  • Barranca Wind 1 28INR0375 · Wind · 301 MW · In study · Jim Hogg
  • Barranca Wind 2 28INR0376 · Wind · 299 MW · In study · Jim Hogg
  • Sierra Madre Solar 23INR0006 · Solar · 255 MW · In study
  • La Morena Energy Center BESS 30INR0042 · Battery storage · 250 MW · In study
  • La Morena Energy Center Solar 30INR0043 · Solar · 250 MW · In study
  • Wallflower Energy Storage 30INR0093 · Battery storage · 209 MW · In study
  • Wallflower Solar 30INR0092 · Solar · 201 MW · In study
Zapata (8299) 138 kV 4 requests · 557 MW3 in study, 1 signed; security posted
  • Falcon Zapata Storage 138 26INR0116 · Battery storage · 201 MW · Signed; security posted
  • Zelus BESS 24INR0131 · Battery storage · 201 MW · In study
  • Big River Solar 23INR0215 · Solar · 104 MW · In study
  • Big River BESS 23INR0237 · Battery storage · 51 MW · In study
Tiempo (80224) 345 kV 5 requests · 1,352 MW · 4 in Zapata County, 1 in Webb5 in study
  • Freedom Falcon BESS 26INR0107 · Battery storage · 502 MW · In study
  • Rancho Grande Solar 28INR0503 · Solar · 252 MW · In study
  • Bravo BESS 27INR0398 · Battery storage · 207 MW · In study · Webb
  • Corralitos Wind 3 28INR0339 · Wind · 196 MW · In study
  • Corralitos Wind 4 28INR0340 · Wind · 195 MW · In study
LOPENO4A (8957) 138 kV 4 requests · 489 MW · 3 in Zapata County, 1 in Starr3 in study, 1 signed; security posted
  • Falcon Zapata Storage 138 26INR0116 · Battery storage · 201 MW · Signed; security posted
  • Halcon Storage 25INR0241 · Battery storage · 133 MW · In study · Starr
  • Big River Solar 23INR0215 · Solar · 104 MW · In study
  • Big River BESS 23INR0237 · Battery storage · 51 MW · In study
Rapido (80227) 345 kV 7 requests · 1,752 MW · 3 in Zapata County, 4 in Starr7 in study
  • Freedom Falcon BESS 26INR0107 · Battery storage · 502 MW · In study
  • Mandolin Solar II SLF 29INR0223 · Solar · 304 MW · In study · Starr
  • Mandolin Solar SLF 26INR0527 · Solar · 300 MW · In study · Starr
  • Mandolin Solar III SLF 29INR0224 · Solar · 250 MW · In study · Starr
  • Barrosos Creek Wind 3 28INR0337 · Wind · 198 MW · In study
  • Barrosos Creek Wind 4 28INR0338 · Wind · 198 MW · In study
  • Mandolin Storage SLF 26INR0528 · Battery storage · 0 MW · In study · Starr
Revilla (8004) 138 kV 2 requests · 204 MW2 in study
  • Falcon II BESS 28INR0483 · Battery storage · 103 MW · In study
  • Falcon II Solar 28INR0482 · Solar · 100 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Zapata County

  • Zapata County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 16, Laredo: 707 E Calton Rd, Ste 304, Laredo TX 78041-3887, 956-791-6611; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Zapata County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Zapata County.

Permits and reviews for Zapata County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Zapata County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Recent local action: On June 10, 2024, the Zapata County Commissioners Court voted to authorize the county judge to enter into tax abatement agreements with Ignis Texas Solar Three, LLC and with Falcon BESS, LLC, each pending review by the county attorney. Both motions were approved by the affirmative vote of all members of the court. (Zapata County commissioners court minutes; checked October 17, 2026).

How a project in Zapata County connects to the grid

Zapata County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Zapata County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Zapata County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 16

Dimmit · Duval · Kinney · La Salle · Maverick · McMullen · Val Verde · Webb · Zavala

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.