Home › Texas › Comanche County
Comanche County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
8 proposed energy projects from ERCOT's September 2026 report, plus who to call in Comanche County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.
Check land in Comanche CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Comanche County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Comanche County?
ERCOT's September 2026 interconnection report lists 8 proposed energy projects in Comanche County (3 solar and 5 battery storage), about 2,446 MW in all. 4 of the 8 have a signed interconnection agreement.
What stands out in Comanche County
By capacity, battery storage leads in Comanche County with 1,781 MW across 5 projects, followed by solar (3 projects, 665 MW). The largest single project is Comanche BESS, a 614 MW stand-alone battery storage project listed under ENERGOS BESS, with an interconnection agreement signed in Mar 2026, and its target online date is May 2029. Of the 8, 4 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet and 3 have posted security or started construction. Connection points are mostly at 345 kV (6 projects), 69 kV (1 project) and 138 kV (1 project) (why the voltage matters). Mustang Creek Solar, LLC is listed on the most projects here (2 of 8); 7 different companies appear in all. Target online dates for the projects not yet running span Sep 2027 to Mar 2030. All of them fall in ERCOT's North load zone. 2 that were listed in August have since dropped off.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Darkwood SolarTap 345KV 1900 Comanche Peak to 1440 Comanche SS | Mustang Creek Solar, LLC | Solar | 152.0 | Sep 2027 | Signed; security posted |
| Lamkin Solartap 69kV 258 Hamilton - 273 Gustine | Commanche Solar, LLC | Solar | 101.5 | Nov 2027 | Signed; security posted |
| Darkwood BESSTap 345KV 1900 Comanche Peak - 1440 Comanche Switch | Mustang Creek Solar, LLC | Battery storage (paired with solar) | 150.5 | Jul 2028 | Signed; security posted |
| Comanche BESS#1440 Comanche Switching Station 345kV | ENERGOS BESS | Battery storage (stand-alone) | 614.4 | May 2029 | Signed Mar 2026 |
| Dragan Solar1440 Comanche 345kV · shared with 1 other request | Hecate Comanche Solar LLC | Solar | 411.0 | Sep 2027 | In study |
| Crios BESSTap 138 kV 1649 HASSE_P8 - 1684 SABANA_8 | BRP Crios BESS LLC | Battery storage (stand-alone) | 205.5 | Mar 2028 | In study |
| Merope BESS345 kV Corn Trail Switch Substation (#11441) | BRP Merope BESS LLC | Battery storage (stand-alone) | 402.4 | Mar 2028 | In study |
| Dragan Storage1440 Comanche 345kV · shared with 1 other request | Hecate Grid Dragan Storage LLC | Battery storage (paired with solar) | 408.3 | Mar 2030 | In study |
No longer listed since August
These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.
- Saddle Horn Station BESS SLF, battery storage, 177 MW (Saddle Horn Station BESS LLC)
- Saddle Horn Station Solar SLF, solar, 175 MW (Saddle Horn Station LLC)
Crowded connection points in Comanche County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Comanche (1440) 345 kV 6 requests · 2,043 MW · 5 in Comanche County, 1 in Erath2 in study, 2 signed, 2 signed; security posted
- Darkwood Solar 27INR0049 · Solar · 152 MW · Signed; security posted
- Darkwood BESS 27INR0050 · Battery storage · 150 MW · Signed; security posted
- Comanche BESS 27INR0365 · Battery storage · 614 MW · Signed Mar 2026
- McCrae Energy Storage 25INR0661 · Battery storage · 306 MW · Signed Dec 2025 · Erath
- Dragan Solar 22INR0237 · Solar · 411 MW · In study
- Dragan Storage 22INR0400 · Battery storage · 408 MW · In study
Comanche Peak (1900) 345 kV 5 requests · 1,382 MW · 2 in Comanche County, 3 in Somervell, Parker, Erath3 signed; security posted, 1 in study, 1 signed
- Yellow Viking Solar 21INR0520 · Solar · 171 MW · Signed; security posted · Somervell
- Darkwood Solar 27INR0049 · Solar · 152 MW · Signed; security posted
- Darkwood BESS 27INR0050 · Battery storage · 150 MW · Signed; security posted
- McCrae Energy Storage 25INR0661 · Battery storage · 306 MW · Signed Dec 2025 · Erath
- Rocking X Solar 23INR0368 · Solar · 602 MW · In study · Parker
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Comanche County
- Comanche County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Comanche County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Comanche County.
Permits and reviews for Comanche County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Comanche County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Comanche County connects to the grid
Comanche County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Comanche County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Comanche County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 3
Archer · Baylor · Brown · Callahan · Clay · Coleman · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young