Harris County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects33
Total capacity6,843MW
Signed agreements11of 33
New since August2requests

33 proposed energy projects from ERCOT's September 2026 report, plus who to call in Harris County and in TCEQ Region 12 before signing a solar, wind, or battery storage lease.

Check land in Harris CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Harris County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Harris County?

ERCOT's September 2026 interconnection report lists 33 proposed energy projects in Harris County (1 solar, 28 battery storage, 3 gas and 1 other), about 6,843 MW in all. 11 of the 33 have a signed interconnection agreement, and 2 have been approved for energization or synchronization. 2 are new since August.

What stands out in Harris County

By capacity, battery storage leads in Harris County with 6,243 MW across 28 projects, followed by gas (3 projects, 500 MW) and solar (1 project, 50 MW). The largest single project is Hobby BESS I, a 603 MW stand-alone battery storage project listed under Airport Storage II LLC, still in study, and its target online date is Oct 2027. Of the 33, 22 are still in ERCOT's study process, 4 have a signed interconnection agreement but no security posted yet, 5 have posted security or started construction and 2 are approved for energization or synchronization. Connection points are mostly at 138 kV (29 projects) and 345 kV (3 projects) (why the voltage matters). AES Distributed Energy, Inc is listed on the most projects here (2 of 33); 32 different companies appear in all. Target online dates for the projects not yet running span Feb 2026 to Dec 2030. All of them fall in ERCOT's Houston load zone. 2 are new since August.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Kegans BESS (Houston IV BESS)44140 CLODINE 138kVSMT Houston IV LLCBattery storage (stand-alone)164.6Sep 2026Approved for synchronization
Little York BESSStation Name (TDSP Station Code): Little York (LK)ESTX-PLD-HOUSTON5, LLCBattery storage (stand-alone)10.0Nov 2026Approved for synchronization
Enchanted Rock NEWPP40475 Deusen 138kVGenerate ER-NG, LLCGas engines30.0Feb 2026 date passed; status per ERCOTSigned; security posted
Callisto II Energy Center47150 HO Clarke 138kVCallisto II Energy Center LLCBattery storage (stand-alone)203.2Dec 2026Signed; security posted
Pamela Heights I#47150 HOC 138kVPamela heights I Energy Center LLCBattery storage (stand-alone)101.7Dec 2026Signed; security posted
Hockley BESS New30.021619, -95.846315Regis Hockley LLCBattery storage10.0Mar 2027Signed; security posted
NRG Greens Bayou 6 (TEF-Due Diligence)Position 1/0 PSSE 40710, Greens Bayou Substation, 138 kVNRG Greens Bayou 6 LLCGas turbine445.0May 2028Signed; security posted
Dori BQ BESS138kV line Holmes (#47210) - Garden Villas (#42680); CNPSunnyside Energy LLCBattery storage (paired with solar)154.0Aug 2027Signed May 2023
Dori BQ Solartap 138kV 47210 Holmes – 42680 Garden VillasSunnyside Energy, LLCSolar50.4Aug 2027Signed Dec 2022
Megamouth Energy Storage New42750 Mykawa 138 kVGCI Megamouth, LLCBattery storage101.3Dec 2028Signed Nov 2025
Pez Rojo BESSTap 138 kV #40260 Chamon - #40912 KingPez Rojo BESS, LLCBattery storage (stand-alone)217.2Feb 2029Signed May 2026
SANJAC BESS40270 Riverside 138kVCastleman PowerBattery storage (stand-alone)202.4Apr 2027In study
NET Power Demonstration plant42360 Mirage POI 8 138kVNET Power LLCGas turbine25.5Aug 2027In study
Hobby BESS IDouble Tap 138kV 42680 Garden Villas – 48250 Hall & 42680 Garden Vi...Airport Storage II LLCBattery storage (stand-alone)602.6Oct 2027In study
Knight Airport BESS ITap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas...Airport Storage I LLCBattery storage (stand-alone)522.5Oct 2027In study
Outer Loop BESS40700 Greens Bayou 345kVBlack Mountain Energy Storage IIBattery storage (stand-alone)201.2Dec 2027In study
Claire BESS40011 Cedar Bayou 138kVBRP Blue Topaz 3, LLCBattery storage (stand-alone)406.0Dec 2027In study
Houston BESSTap 138 kV LAUDER (#46002) - RITTENHOUSE (#46282) ckt 95SMT HoustonBattery storage (stand-alone)227.9Jan 2028In study
Massey StorageTap 138kV Chevron_NewSub(#99300) and Cedar Bayou Tap(#48065) circu...Massey Storage, LLCBattery storage (stand-alone)102.9Jan 2028In study
Stinger Energy StorageTap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #...Stinger Energy Storage LLCBattery storage (stand-alone)200.8Mar 2028In study
High Plains Storage45880 Hockley 138kVROBP Holdings, LLCBattery storage (stand-alone)157.7May 2028In study
Callisto ID Energy Center47170 (H_O_C__B138) 138kVTempus Power management LLCBattery storage (stand-alone)100.0Jun 2028In study
Barcelona TxHSR TPSS HN-4tap 138kV 45885 HocklyC - 46220 PetersTexas Central Rail Holdings, LLCOther50.0Jul 2028In study
Furay Battery Energy Storage SystemTap 138kV 45660 Jonte substation – 46332 Scenic WoodsBlue Topaz 1, LLCBattery storage (stand-alone)304.0Sep 2028In study
Rex StorageTap 138 kV 48096 El Dorado - 43610 Scarsdale CKT 92Rex BESS, LLCBattery storage (stand-alone)256.4Oct 2028In study
Bluegill BESSTap 138 kV 40130 Atascocita - 40690 East GateBluegill BESS, LLCBattery storage (stand-alone)251.0Oct 2028In study
Texas Deepwater BESS#40881 Parkes Substation 138 kVTDWP Partners LLCBattery storage (stand-alone)313.3Mar 2029In study
Burnet Bay Storagetap 138kV 40390 Crosby - 40790 HaneyTOCE TX BESS 4, LLCBattery storage (stand-alone)207.8Jun 2029In study
Coati Energy StorageBus # 40830, Humble, 138 kVPowerPulse LLCBattery storage (stand-alone)202.8Jun 2029In study
Pinnacle Point Energy StorageTap Highlands (Bus # 40812) - HANEY ( BUS # 40790) 138 kVGCI Pinnacle Point, LLCBattery storage (stand-alone)101.3Jul 2029In study
Beacon Storage40450 Deepwater 345kVAES Distributed Energy, IncBattery storage (stand-alone)408.7Oct 2029In study
Sigma Storage40460 Deepwater 138kVAES Distributed Energy, IncBattery storage (stand-alone)408.4Oct 2029In study
Hyacinth Storage46500 Tomball 345 kVHyacinth Storage, LLCBattery storage (stand-alone)103.0Dec 2030In study

Crowded connection points in Harris County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Garden Villas (42680) 138 kV 3 requests · 807 MW2 signed, 1 in study
  • Dori BQ BESS 24INR0196 · Battery storage · 154 MW · Signed May 2023
  • Dori BQ Solar 23INR0040 · Solar · 50 MW · Signed Dec 2022
  • Hobby BESS I 26INR0546 · Battery storage · 603 MW · In study
Ho Clarke (47150) 138 kV 2 requests · 305 MW2 signed; security posted
  • Callisto II Energy Center 22INR0558 · Battery storage · 203 MW · Signed; security posted
  • Pamela Heights I 28INR0154 · Battery storage · 102 MW · Signed; security posted
Holmes (47210) 138 kV 2 requests · 204 MW2 signed
  • Dori BQ BESS 24INR0196 · Battery storage · 154 MW · Signed May 2023
  • Dori BQ Solar 23INR0040 · Solar · 50 MW · Signed Dec 2022
Atascocita (40130) 138 kV 2 requests · 452 MW2 in study
  • Bluegill BESS 25INR0434 · Battery storage · 251 MW · In study
  • Stinger Energy Storage 26INR0343 · Battery storage · 201 MW · In study
Haney (40790) 138 kV 2 requests · 309 MW2 in study
  • Burnet Bay Storage 26INR0548 · Battery storage · 208 MW · In study
  • Pinnacle Point Energy Storage 26INR0317 · Battery storage · 101 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Harris County

  • Harris County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 12, Houston: 5425 Polk St, Ste H, Houston TX 77023-1452, 713-767-3500; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Harris County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Harris County.

Permits and reviews for Harris County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Harris County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Recent local action: On March 19, 2026, Harris County Commissioners Court authorized county staff to execute solar power and battery energy storage projects under the county's Solar for All initiative, at roughly six to 10 locations. The $88.3 million upfront investment comes from the county's CIP fund. (Community Impact; checked October 17, 2026).

How a project in Harris County connects to the grid

Harris County is on the ERCOT grid. The projects listed above are in ERCOT's Houston load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Harris County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Harris County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 12

Austin · Brazoria · Chambers · Colorado · Fort Bend · Galveston · Liberty · Matagorda · Montgomery · Walker · Waller · Wharton

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.