Victoria County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
18 proposed energy projects from ERCOT's September 2026 report, plus who to call in Victoria County and in TCEQ Region 14 before signing a solar, wind, or battery storage lease.
Check land in Victoria CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Victoria County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Victoria County?
ERCOT's September 2026 interconnection report lists 18 proposed energy projects in Victoria County (4 solar, 1 wind, 10 battery storage, 2 gas and 1 nuclear), about 5,412 MW in all. 5 of the 18 have a signed interconnection agreement. 2 are new since August.
What stands out in Victoria County
By capacity, battery storage leads in Victoria County with 1,756 MW across 10 projects, followed by nuclear (1 project, 1,320 MW) and gas (2 projects, 1,110 MW). The largest single project is Blue Energy Center - Phase 3 – Steam Stage 2, a 1,320 MW nuclear project listed under Sister 1, LLC, still in study, and its target online date is Jun 2033. Of the 18, 13 are still in ERCOT's study process, 2 have a signed interconnection agreement but no security posted yet and 3 have posted security or started construction. Connection points are mostly at 138 kV (13 projects) and 345 kV (5 projects) (why the voltage matters). The single most-used connection point is Tap 345kV 80286 DULCE7A - 8676 STATIC7A, shared by 3 projects. Brother 1, LLC is listed on the most projects here (2 of 18); 17 different companies appear in all. Target online dates for the projects not yet running span Aug 2027 to Jun 2033. All of them fall in ERCOT's South load zone. 2 are new since August.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Crossroads Wind80090 Dokmai 138 KV | HyFuels Green Lake Wind LLC | Wind | 277.4 | Feb 2028 | Signed; security posted |
| Two Brothers ESS8911 BLKBYU4A 138kV | BRP Blue Topaz 2, LLC | Battery storage (stand-alone) | 154.7 | Feb 2028 | Signed; security posted |
| Leopard BESS8721 Beecher 138 kV | Bobcat Energy Center, LLC | Battery storage (stand-alone) | 264.2 | Feb 2029 | Signed; security posted |
| Brizo BESS138 kV Loop 463 Substation (#5680) | BRP Brizo BESS LLC | Battery storage (stand-alone) | 144.2 | Sep 2027 | Signed Mar 2025 |
| Iguala SolarAEP South Texas Project (#5915) to Static (#8676) 345kV line | Iguala Solar LLC | Solar | 250.0 | Feb 2029 | Signed Jul 2025 |
| Marcos BESSTo the 138 kV line from EDNA (#8118) to VICTORIA4A (#8172) · shared with 1 other request | GRS BESS Texas Eight LLC | Battery storage (paired with solar) | 115.9 | Aug 2027 | In study |
| Georgia-Lynn BESS80064 CHOCBAYU4A 138 kV | Georgia Lynn BESS LLC | Battery storage (stand-alone) | 108.7 | Feb 2028 | In study |
| Calico BESSTap 138 kV 8723 CANGREJO4A - 8721 BEECHER4A | Nova Clean Energy LLC | Battery storage (stand-alone) | 204.9 | Jun 2028 | In study |
| Marcos Solar SLFTo the 138 kV line from EDNA (#8118) to VICTORIA4A (#8172) · shared with 1 other request | GRS BESS Texas Eight | Solar | 216.1 | Aug 2028 | In study |
| Goldhill Energy StorageTap 138kV 8154 VISTRON4B – 8189 TUNGSTEN4A | Goldhill Energy Storage LLC | Battery storage (stand-alone) | 200.6 | Sep 2028 | In study |
| HyFuels Calhoun SolarTap 345kV 8715 RADIANT7A - 8728 COBRA7A | HyFuels Green Lake Solar LLC | Solar | 301.8 | Oct 2028 | In study |
| Tejano StorageTap 138kV 8125 Lolita - 8172 Victoria | Tejano Storage, LLC | Battery storage (stand-alone) | 152.3 | Jul 2029 | In study |
| Arpeggio BESS#80064 Chocolate Bayou 138kV | Arpeggio BESS, LLC | Battery storage (stand-alone) | 200.7 | Sep 2029 | In study |
| Oak Belt SolarTap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8 · shared with 1 other request | Oak Belt Solar, LLC | Solar | 181.0 | Mar 2030 | In study |
| Oak Belt StorageTap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8 · shared with 1 other request | Oak Belt Storage, LLC | Battery storage (paired with solar) | 209.7 | Mar 2030 | In study |
| Blue Energy Center- Phase 1a - Gas NewTap 345kV 80286 DULCE7A - 8676 STATIC7A · shared with 2 other requests | Brother 1, LLC | Gas turbine | 780.0 | May 2030 | In study |
| Blue Energy Center - Phase 1b – SteamTap 345kV 80286 DULCE7A - 8676 STATIC7A · shared with 2 other requests | Brother 1, LLC | Gas combined cycle | 330.0 | Oct 2031 | In study |
| Blue Energy Center - Phase 3 – Steam Stage 2 NewTap 345kV 80286 DULCE7A - 8676 STATIC7A · shared with 2 other requests | Sister 1, LLC | Nuclear | 1,320.0 | Jun 2033 | In study |
Crowded connection points in Victoria County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
STATIC7A (8676) 345 kV 6 requests · 4,217 MW · 4 in Victoria County, 2 in Refugio3 signed, 3 in study
- Ross Solar 26INR0155 · Solar · 1,026 MW · Signed Jun 2024 · Refugio
- Ross Storage 26INR0156 · Battery storage · 511 MW · Signed Jun 2024 · Refugio
- Iguala Solar 23INR0090 · Solar · 250 MW · Signed Jul 2025
- Blue Energy Center - Phase 3 – Steam Stage 2 33INR0007 · Nuclear · 1,320 MW · In study
- Blue Energy Center- Phase 1a - Gas 30INR0150 · Gas turbine · 780 MW · In study
- Blue Energy Center - Phase 1b – Steam 29INR0248 · Gas combined cycle · 330 MW · In study
Victoria (8172) 138 kV 5 requests · 871 MW · 3 in Victoria County, 2 in Goliad5 in study
- Kuy Creek Solar 1 SLF 28INR0303 · Solar · 235 MW · In study · Goliad
- Marcos Solar SLF 27INR0169 · Solar · 216 MW · In study
- Tejano Storage 24INR0168 · Battery storage · 152 MW · In study
- Kuy Creek Storage 1 SLF 28INR0304 · Battery storage · 151 MW · In study · Goliad
- Marcos BESS 27INR0170 · Battery storage · 116 MW · In study
DULCE7A (80286) 345 kV 3 requests · 2,430 MW3 in study
- Blue Energy Center - Phase 3 – Steam Stage 2 33INR0007 · Nuclear · 1,320 MW · In study
- Blue Energy Center- Phase 1a - Gas 30INR0150 · Gas turbine · 780 MW · In study
- Blue Energy Center - Phase 1b – Steam 29INR0248 · Gas combined cycle · 330 MW · In study
CHOCBAYU4A (80064) 138 kV 2 requests · 309 MW2 in study
- Arpeggio BESS 28INR0356 · Battery storage · 201 MW · In study
- Georgia-Lynn BESS 26INR0559 · Battery storage · 109 MW · In study
Bus 8118 (8118) 138 kV 2 requests · 332 MW2 in study
- Marcos Solar SLF 27INR0169 · Solar · 216 MW · In study
- Marcos BESS 27INR0170 · Battery storage · 116 MW · In study
Beecher (8721) 138 kV 2 requests · 469 MW1 signed; security posted, 1 in study
- Leopard BESS 27INR0224 · Battery storage · 264 MW · Signed; security posted
- Calico BESS 27INR0382 · Battery storage · 205 MW · In study
Bus 5506 (5506) 138 kV 2 requests · 391 MW2 in study
- Oak Belt Storage 29INR0244 · Battery storage · 210 MW · In study
- Oak Belt Solar 29INR0243 · Solar · 181 MW · In study
Bus 5584 (5584) 138 kV 2 requests · 391 MW2 in study
- Oak Belt Storage 29INR0244 · Battery storage · 210 MW · In study
- Oak Belt Solar 29INR0243 · Solar · 181 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Victoria County
- Victoria County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 14, Corpus Christi: 500 North Shoreline Blvd, Ste 500, Corpus Christi TX 78401-0318, 361-881-6900; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Victoria County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Victoria County.
Permits and reviews for Victoria County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Victoria County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Recent local action: Victoria County posted notice that its Commissioners Court would hold a public hearing on August 12, 2024 to consider Portside Energy Center, LLC's tax abatement application for a proposed battery energy storage system and solar generating facility in the Port of Victoria County Reinvestment Zone #2. (Victoria County public hearing notice; checked October 17, 2026).
How a project in Victoria County connects to the grid
Victoria County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Victoria County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Victoria County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 14
Aransas · Bee · Calhoun · DeWitt · Goliad · Gonzales · Jackson · Jim Wells · Kleberg · Lavaca · Live Oak · Nueces · Refugio · San Patricio