Clay County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
4 proposed energy projects from ERCOT's September 2026 report, plus who to call in Clay County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.
Check land in Clay CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Clay County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Clay County?
ERCOT's September 2026 interconnection report lists 4 proposed energy projects in Clay County (2 solar and 2 battery storage), about 1,866 MW in all. 1 of the 4 has a signed interconnection agreement.
What stands out in Clay County
By capacity, solar leads in Clay County with 1,055 MW across 2 projects, followed by battery storage (2 projects, 811 MW). The largest single project is Hiru Solar, a 604 MW solar project listed under Hecate Energy Hazel LLC, still in study, and its target online date is Apr 2029. Of the 4, 3 are still in ERCOT's study process and 1 has posted security or started construction. Every listed connection point is on the 345 kV system (why the voltage matters). Hecate Energy Hazel LLC is listed on the most projects here (2 of 4); 3 different companies appear in all. Target online dates for the projects not yet running span Dec 2028 to Apr 2029. All of them fall in ERCOT's West load zone. 1 that was listed in August has since dropped off.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Soleil SolarTap 345 kV 1730 Krum West Switch - 6111 Riley ckt 2 | Soleil Solar, LLC | Solar | 451.7 | Dec 2028 | Signed; security posted |
| Hiru SolarTap 345kV 6111 Riley - 1730 West Krum ckt 1 · shared with 1 other request | Hecate Energy Hazel LLC | Solar | 603.7 | Apr 2029 | In study |
| Hiru StorageTap 345kV 6111 Riley - 1730 West Krum ckt 1 · shared with 1 other request | Hecate Energy Hazel LLC | Battery storage (paired with solar) | 503.6 | Apr 2029 | In study |
| Clay County Yang Storage1458 Cobb Switching Station 345 kV · shared with 1 other request | DM-CCY, LLC | Battery storage (stand-alone) | 307.5 | Apr 2029 | In study |
No longer listed since August
These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.
- Lutum Wind, wind, 242 MW (RWE)
Crowded connection points in Clay County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Riley (6111) 345 kV 15 requests · 4,272 MW · 3 in Clay County, 12 in Wilbarger, Wichita, Montague11 in study, 4 signed; security posted
- Soleil Solar 25INR0097 · Solar · 452 MW · Signed; security posted
- Adamstown Solar 21INR0210 · Solar · 251 MW · Signed; security posted · Wilbarger
- Nymphaea Solar 25INR0154 · Solar · 121 MW · Signed; security posted · Wichita
- Nymphaea Storage 25INR0155 · Battery storage · 61 MW · Signed; security posted · Wichita
- Hiru Solar 23INR0228 · Solar · 604 MW · In study
- Reunion Solar 28INR0332 · Solar · 601 MW · In study · Wilbarger
- Hiru Storage 24INR0444 · Battery storage · 504 MW · In study
- Prairie Branch BESS 28INR0423 · Battery storage · 310 MW · In study · Montague
- Gilleys Energy Storage 25INR0656 · Battery storage · 306 MW · In study · Wise
- Prairie Branch Solar 28INR0422 · Solar · 301 MW · In study · Montague
- Wichita Creek Storage 28INR0378 · Battery storage · 300 MW · In study · Wichita
- Reunion Storage 28INR0333 · Battery storage · 200 MW · In study · Wilbarger
- White Wing Storage 27INR0333 · Battery storage · 130 MW · In study · Wilbarger
- White Wing Solar 27INR0332 · Solar · 127 MW · In study · Wilbarger
- Wichita Creek Solar 28INR0377 · Solar · 3 MW · In study · Wichita
Krum West (1730) 345 kV 13 requests · 3,688 MW · 3 in Clay County, 10 in Wichita, Montague, Cooke7 in study, 4 signed; security posted, 1 approved for synchronization, 1 signed
- WILDWIND 20INR0033 · Wind · 180 MW · Approved for synchronization · Cooke
- Soleil Solar 25INR0097 · Solar · 452 MW · Signed; security posted
- Adamstown Solar 21INR0210 · Solar · 251 MW · Signed; security posted · Wilbarger
- Nymphaea Solar 25INR0154 · Solar · 121 MW · Signed; security posted · Wichita
- Nymphaea Storage 25INR0155 · Battery storage · 61 MW · Signed; security posted · Wichita
- Fortuna Wind 22INR0301 · Wind · 295 MW · Signed Aug 2024 · Jack
- Hiru Solar 23INR0228 · Solar · 604 MW · In study
- Hiru Storage 24INR0444 · Battery storage · 504 MW · In study
- Prairie Branch BESS 28INR0423 · Battery storage · 310 MW · In study · Montague
- Gilleys Energy Storage 25INR0656 · Battery storage · 306 MW · In study · Wise
- Prairie Branch Solar 28INR0422 · Solar · 301 MW · In study · Montague
- Wichita Creek Storage 28INR0378 · Battery storage · 300 MW · In study · Wichita
- Wichita Creek Solar 28INR0377 · Solar · 3 MW · In study · Wichita
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Clay County
- Clay County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Clay County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Clay County.
Permits and reviews for Clay County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Clay County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Clay County connects to the grid
Clay County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Clay County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Clay County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 3
Archer · Baylor · Brown · Callahan · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young