Pecos County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
52 proposed energy projects from ERCOT's September 2026 report, plus who to call in Pecos County and in TCEQ Region 7 before signing a solar, wind, or battery storage lease.
Check land in Pecos CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Pecos County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Pecos County?
ERCOT's September 2026 interconnection report lists 52 proposed energy projects in Pecos County (22 solar, 8 wind, 15 battery storage and 7 gas), about 21,375 MW in all. 16 of the 52 have a signed interconnection agreement. The table also lists 5 changes to existing plants (repowers or capacity changes), not counted above. 2 are new since August.
What stands out in Pecos County
By capacity, solar leads in Pecos County with 8,875 MW across 22 projects, followed by gas (7 projects, 5,886 MW) and wind (8 projects, 4,658 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Big Canyon Wind, a 1,500 MW wind project listed under Longfellow Wind, LLC, with its agreement signed and security posted, and its target online date is Jul 2030. Of the 52, 36 are still in ERCOT's study process, 5 have a signed interconnection agreement but no security posted yet and 11 have posted security or started construction. Connection points are mostly at 138 kV (23 projects) and 345 kV (21 projects) (why the voltage matters). The single most-used connection point is Tap 345kV 60404 Solstice to 38441 Bottlebrush, shared by 5 projects. S&S Renewables, LLC is listed on the most projects here (6 of 52); 36 different companies appear in all. Target online dates for the projects not yet running span Mar 2027 to Feb 2031. All of them fall in ERCOT's West load zone. 2 are new since August and 1 that was listed in August has since dropped off.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Desert Sky repowertwo LCRA 138kV | DESERT SKY WIND FARM LLC | Wind | 7.2 | May 2023 | Approved for synchronization |
| Sherbino II Wind repower38430 TN White Baker 138kV | Sherbino II Wind Farm LLC | Wind | −18.0 capacity change to an existing plant | Aug 2026 | Approved for synchronization |
| Indian Mesa repower76019 Indian NWP 138kV | Nextera | Wind | 9.3 | Dec 2026 | Approved for synchronization |
| Woodward 2 repower60400 Lynx 138kV · shared with 3 other requests | Nextera | Wind | 0 no capacity change | Dec 2026 | Approved for synchronization |
| Woodward I repower60400 Lynx 138kV · shared with 3 other requests | Nextera | Wind | 0 no capacity change | Dec 2026 | Approved for synchronization |
| Alamo Street BESS2Alamo Street Sub TNP | Momentum Pilsner, LLC | Battery storage (stand-alone) | 10.0 | Mar 2027 | Signed; security posted |
| Sherbino II BESS SLF38430 TNMP White baker Switching Station 138kV | Phoenix Battery Storage, LLC | Battery storage (paired with wind) | 77.4 | Apr 2027 | Signed; security posted |
| Laurel Wind Energy CenterTap Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 2 and | LAUREL ENERGY CENTER, LLC | Wind | 306.6 | Dec 2027 | Signed; security posted |
| Longfellow BESS I38432 TNCENTRY1_1 138 KV | CENTURY GAS PROCESSING, LLC | Battery storage (paired with solar) | 55.0 | Mar 2028 | Signed; security posted |
| Longfellow BESS II38432 TNCENTRY2_1 138 KV · shared with 1 other request | CENTURY GAS PROCESSING, LLC | Battery storage (paired with solar) | 105.8 | Mar 2028 | Signed; security posted |
| Skyrider Wind138kV #38365 TNPINION | NextEra Energy Interconnection Holdings, LLC | Wind | 370.0 | Jul 2028 | Signed; security posted |
| Selenite Springs SolarTap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Swit... | Selenite Springs Solar, LLC | Solar | 253.0 | Aug 2028 | Signed; security posted |
| Springfield SolarTap Leon Creek (#38355) to Woodhouse Station (#38308) 138kV line | BOULEVARD ASSOCIATES, LLC | Solar | 400.0 | Aug 2028 | Signed; security posted |
| Big Canyon Wind38441 Bottlebrush 345kV | Longfellow Wind, LLC | Wind | 1,500.0 | Jul 2030 | Signed; security posted |
| Elk Ridge SolarAEP Solstice Substation #60404 | Elk Ridge Solar, LLC | Solar | 503.0 | Jul 2030 | Signed; security posted |
| MRR SolarSolstice Substation #60384 -AEP | Antler Peak Solar, LLC | Solar | 500.0 | Jul 2030 | Signed; security posted |
| Wisdom BESS SLFTap 138 kV #38455 HOLIDAY SUB TNP - 138 kV #38450 SOAPTREE TNP | Wisdom Green Energy LLC | Battery storage (paired with solar) | 102.9 | Oct 2027 | Signed Mar 2026 |
| Wisdom Solar SLFTap 138 kV #38455 HOLIDAY SUB TNP - #38450 SOAPTREE TNP | Wisdom Green Energy LLC | Solar | 299.4 | Oct 2027 | Signed Mar 2026 |
| Pecos WindTap 345 kV 60404 Solstice (SOLSTICE7A) – 76002 Bakersfield (L_BAKER... | Midnight Energy Center, LLC | Wind | 193.8 | May 2028 | Signed Mar 2026 |
| Longfellow Solar I38431 TNCENTRY1_1 138 KV · shared with 1 other request | CENTURY GAS PROCESSING, LLC | Solar | 178.2 | Dec 2028 | Signed Apr 2025 |
| Longfellow Solar II38432 TNCENTRY2_1 138 KV · shared with 1 other request | CENTURY GAS PROCESSING, LLC | Solar | 207.4 | Dec 2028 | Signed Apr 2025 |
| Grand Mesa BESS76582 MESA VIEW SWITCH 138kV | PERRY GREEN POWER LLC | Battery storage (stand-alone) | 253.3 | Sep 2027 | In study |
| Rock House Draw Gas38431 TNCENTRY1_1 138 KV · shared with 1 other request | Longfellow Power LLC | Gas engines | 523.0 | Nov 2027 | In study |
| Comanche Creek generating stationTNCENTRY1_1 [138 kV] ( 38431) | Longfellow Power LLC | Gas engines | 107.0 | Dec 2027 | In study |
| Mensa BESS60718 Pecos Valley 138kV | BRP Mensa BESS LLC | Battery storage (stand-alone) | 309.0 | Jun 2028 | In study |
| st gall IIIA Storage38355 LEON_CRK 138kV · shared with 1 other request | Tempus Power Management LLC | Battery storage (stand-alone) | 200.7 | Jun 2028 | In study |
| st gall IIIB Storage38355 LEON_CRK 138kV · shared with 1 other request | Tempus Power Management LLC | Battery storage (stand-alone) | 200.7 | Jun 2028 | In study |
| Pecos Flats Solar IITap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5 · shared with 3 other requests | Glass Mountain Solar, LLC | Solar | 301.5 | Feb 2029 | In study |
| Pecos Flats Solar IIITap 345 kV 60404 SOLSTICE - 11098 SANDLAKE_5 · shared with 3 other requests | Glass Mountain Solar, LLC | Solar | 301.5 | Feb 2029 | In study |
| Glass Mountain BB Solar 1Tap 345kV 60404 Solstice to 38441 Bottlebrush · shared with 4 other requests | Glass Mountain Solar, LLC | Solar | 302.7 | Mar 2029 | In study |
| Glass Mountain BB Solar 2Tap 345kV 60404 Solstice to 38441 Bottlebrush · shared with 4 other requests | Glass Mountain Solar II, LLC | Solar | 302.7 | Mar 2029 | In study |
| Titus Sienta Solar NewTap 138kV 1239 Coyanosa - 11238 Blair Lake Sub · shared with 1 other request | Sol Sienta Solar, LLC | Solar | 501.9 | Apr 2029 | In study |
| Ashtrom Marigold BESS SLF860 GIRVINSW 345kV · shared with 1 other request | Marigold BESS LLC | Battery storage (stand-alone) | 153.9 | Apr 2029 | In study |
| Whitethorn Solar Project New345KV 860 GIRVINSW | Greasewood III LLC | Solar | 163.1 | Apr 2029 | In study |
| Tierra Bonita BESS SLF860 GIRVINSW 345kV · shared with 1 other request | Greasewood II BESS LLC | Battery storage (stand-alone) | Self-limiting | Jun 2029 | In study |
| Star Of Texas Solar60152 Fort Stockton Switch 345kV | BOULEVARD ASSOCIATES, LLC | Solar | 415.0 | Jul 2029 | In study |
| Larrea SolarTap 345kV 76002 Bakerfield - 60404 Solstice CKT#1 | Greasewood IV LLC | Solar | 231.6 | Sep 2029 | In study |
| Glass Mountain BB Solar 3Tap 345kV 60404 Solstice to 38441 Bottlebrush · shared with 4 other requests | Glass Mountain Solar III, LLC | Solar | 302.6 | Oct 2029 | In study |
| Glass Mountain BB Solar 4Tap 345kV 60404 Solstice to 38441 Bottlebrush · shared with 4 other requests | Glass Mountain Solar IV, LLC | Solar | 302.6 | Oct 2029 | In study |
| Glass Mountain BB Solar 5Tap 345kV 60404 Solstice to 38441 Bottlebrush · shared with 4 other requests | Glass Mountain Solar V, LLC | Solar | 302.6 | Oct 2029 | In study |
| Pecos Flats Solar60404 SOLSTICE 345 kV | Glass Mountain Solar, LLC | Solar | 302.4 | Oct 2029 | In study |
| BRP Octans BESS6671 Tombstone 138kV | BRP OCTANS BESS LLC | Battery storage (stand-alone) | 129.6 | Dec 2029 | In study |
| The Giant Arc IBus #60404 SOLSTICE CKT 01 | Powering Knowledge, LLC | Gas engines | 1,300.0 | Apr 2030 | In study |
| The Giant Arc-IIBus #60404 SOLSTICE CKT 02 | Powering Knowledge, LLC | Gas engines | 1,300.0 | Apr 2030 | In study |
| Pecos Flats Wind ITap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP) | Pecos Flats Wind, LLC | Wind | 506.9 | Jun 2030 | In study |
| Pecos Flats Wind IITap 345kV 38441 Bottlebrush to 38435 White Baker 345kV line (TNMP) | Pecos Flats Wind II, LLC | Wind | 507.9 | Jun 2030 | In study |
| Gravitas I Natural GasTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit line · shared with 2 other requests | S&S Renewables, LLC | Gas engines | 1,247.0 | Jun 2030 | In study |
| Gravitas I SolarTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit line · shared with 2 other requests | S&S Renewables, LLC | Solar | 1,124.8 | Jun 2030 | In study |
| Gravitas I WindTap 345kV Solstice (60404) - Bakersfield (76002) Double circuit line · shared with 2 other requests | S&S Renewables, LLC | Wind | 636.5 | Jun 2030 | In study |
| Pentarise BESS138 kV Pig Creek (#60393) | Pentarise BESS, LLC | Battery storage (stand-alone) | 150.6 | Jun 2030 | In study |
| Permian I Natural GasTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit · shared with 2 other requests | S&S Renewables, LLC | Gas engines | 1,247.0 | Jun 2030 | In study |
| Permian I SolarTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit · shared with 2 other requests | S&S Renewables, LLC | Solar | 1,125.7 | Jun 2030 | In study |
| Permian I WindTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit · shared with 2 other requests | S&S Renewables, LLC | Wind | 636.5 | Jun 2030 | In study |
| Rio Vista SolarTap 138kV #60393 PigCreek4A – #60385 Solstice4A · shared with 1 other request | Rio Vista Solar, LLC | Solar | 553.7 | Sep 2030 | In study |
| Rio Vista StorageTap 138kV #60393 Pigcreek4A – #60385 Solstice4A · shared with 1 other request | Rio Vista Storage, LLC | Battery storage (paired with solar) | 103.4 | Sep 2030 | In study |
| Gatsby Energy StorageFort Lancaster 138 kV Substation (PSSE Bus #76579) | Gatsby Energy Storage LLC | Battery storage (stand-alone) | 103.4 | Dec 2030 | In study |
| Valentine Energy Center60400 Lynx 138kV · shared with 3 other requests | Valentine Energy Center, LLC | Gas engines | 162.3 | Feb 2031 | In study |
No longer listed since August
These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.
- Hovey Solar 2, solar, 8 MW (BARILLA SOLAR, LLC)
Crowded connection points in Pecos County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Solstice (60404) 345 kV 23 requests · 13,000 MW · 17 in Pecos County, 6 in Reeves20 in study, 2 signed; security posted, 1 signed
- Elk Ridge Solar 28INR0114 · Solar · 503 MW · Signed; security posted
- Laurel Wind Energy Center 27INR0056 · Wind · 307 MW · Signed; security posted
- Pecos Wind 27INR0510 · Wind · 194 MW · Signed Mar 2026
- The Giant Arc-II 30INR0105 · Gas engines · 1,300 MW · In study
- The Giant Arc I 30INR0113 · Gas engines · 1,300 MW · In study
- Gravitas I Natural Gas 30INR0084 · Gas engines · 1,247 MW · In study
- Gravitas I Solar 30INR0083 · Solar · 1,125 MW · In study
- Kilby1 Part 6 Large Block Combined Cycle 29INR0199 · Gas turbine · 1,056 MW · In study · Reeves
- Kilby1 Part 4 Large Block Simple Cycle 28INR0459 · Gas turbine · 950 MW · In study · Reeves
- Gravitas I Wind 30INR0085 · Wind · 637 MW · In study
- Glass Mountain Wind 2 28INR0468 · Wind · 519 MW · In study · Reeves
- Glass Mountain Wind 1 29INR0194 · Wind · 512 MW · In study · Reeves
- Kilby1 Part 1 Small Block Simple Cycle 27INR0572 · Gas turbine · 371 MW · In study · Reeves
- Kilby1 Part 2 Tier1 BESS 28INR0457 · Battery storage · 330 MW · In study · Reeves
- Glass Mountain BB Solar 1 29INR0347 · Solar · 303 MW · In study
- Glass Mountain BB Solar 2 29INR0348 · Solar · 303 MW · In study
- Glass Mountain BB Solar 5 29INR0349 · Solar · 303 MW · In study
- Glass Mountain BB Solar 3 29INR0357 · Solar · 303 MW · In study
- Glass Mountain BB Solar 4 29INR0358 · Solar · 303 MW · In study
- Pecos Flats Solar 29INR0181 · Solar · 302 MW · In study
- Pecos Flats Solar II 29INR0182 · Solar · 302 MW · In study
- Pecos Flats Solar III 29INR0183 · Solar · 302 MW · In study
- Larrea Solar 27INR0146 · Solar · 232 MW · In study
Bottlebrush (38441) 345 kV 11 requests · 7,037 MW10 in study, 1 signed; security posted
- Big Canyon Wind 30INR0018 · Wind · 1,500 MW · Signed; security posted
- Permian I Natural Gas 31INR0019 · Gas engines · 1,247 MW · In study
- Permian I Solar 31INR0018 · Solar · 1,126 MW · In study
- Permian I Wind 30INR0086 · Wind · 637 MW · In study
- Pecos Flats Wind II 30INR0132 · Wind · 508 MW · In study
- Pecos Flats Wind I 30INR0131 · Wind · 507 MW · In study
- Glass Mountain BB Solar 1 29INR0347 · Solar · 303 MW · In study
- Glass Mountain BB Solar 2 29INR0348 · Solar · 303 MW · In study
- Glass Mountain BB Solar 5 29INR0349 · Solar · 303 MW · In study
- Glass Mountain BB Solar 3 29INR0357 · Solar · 303 MW · In study
- Glass Mountain BB Solar 4 29INR0358 · Solar · 303 MW · In study
Bakerfield (76002) 345 kV 6 requests · 3,740 MW4 in study, 1 signed; security posted, 1 signed
- Laurel Wind Energy Center 27INR0056 · Wind · 307 MW · Signed; security posted
- Pecos Wind 27INR0510 · Wind · 194 MW · Signed Mar 2026
- Gravitas I Natural Gas 30INR0084 · Gas engines · 1,247 MW · In study
- Gravitas I Solar 30INR0083 · Solar · 1,125 MW · In study
- Gravitas I Wind 30INR0085 · Wind · 637 MW · In study
- Larrea Solar 27INR0146 · Solar · 232 MW · In study
White Baker (38435) 345 kV 5 requests · 4,024 MW5 in study
- Permian I Natural Gas 31INR0019 · Gas engines · 1,247 MW · In study
- Permian I Solar 31INR0018 · Solar · 1,126 MW · In study
- Permian I Wind 30INR0086 · Wind · 637 MW · In study
- Pecos Flats Wind II 30INR0132 · Wind · 508 MW · In study
- Pecos Flats Wind I 30INR0131 · Wind · 507 MW · In study
LEON_CRK (38355) 138 kV 4 requests · 1,054 MW2 in study, 2 signed; security posted
- Springfield Solar 30INR0058 · Solar · 400 MW · Signed; security posted
- Selenite Springs Solar 29INR0147 · Solar · 253 MW · Signed; security posted
- st gall IIIA Storage 27INR0620 · Battery storage · 201 MW · In study
- st gall IIIB Storage 27INR0621 · Battery storage · 201 MW · In study
TNCENTRY1_1 (38431) 138 kV 3 requests · 808 MW2 in study, 1 signed
- Longfellow Solar I 24INR0452 · Solar · 178 MW · Signed Apr 2025
- Rock House Draw Gas 27INR0653 · Gas engines · 523 MW · In study
- Comanche Creek generating station 26INR0537 · Gas engines · 107 MW · In study
TNCENTRY2_1 (38432) 138 kV 3 requests · 368 MW2 signed; security posted, 1 signed
- Longfellow BESS II 24INR0455 · Battery storage · 106 MW · Signed; security posted
- Longfellow BESS I 24INR0453 · Battery storage · 55 MW · Signed; security posted
- Longfellow Solar II 24INR0454 · Solar · 207 MW · Signed Apr 2025
Girvinsw (860) 345 kV 3 requests · 317 MW3 in study
- Whitethorn Solar Project 29INR0263 · Solar · 163 MW · In study
- Ashtrom Marigold BESS SLF 29INR0324 · Battery storage · 154 MW · In study
- Tierra Bonita BESS SLF 26INR0715 · Battery storage · 0 MW · In study
PIGCREEK4A (60393) 138 kV 3 requests · 808 MW3 in study
- Rio Vista Solar 28INR0260 · Solar · 554 MW · In study
- Pentarise BESS 30INR0100 · Battery storage · 151 MW · In study
- Rio Vista Storage 28INR0261 · Battery storage · 103 MW · In study
Holiday Tnp (38455) 138 kV 2 requests · 402 MW2 signed
- Wisdom Solar SLF 27INR0438 · Solar · 299 MW · Signed Mar 2026
- Wisdom BESS SLF 27INR0440 · Battery storage · 103 MW · Signed Mar 2026
Soaptree Tnp (38450) 138 kV 2 requests · 402 MW2 signed
- Wisdom Solar SLF 27INR0438 · Solar · 299 MW · Signed Mar 2026
- Wisdom BESS SLF 27INR0440 · Battery storage · 103 MW · Signed Mar 2026
SOLSTICE4A (60385) 138 kV 2 requests · 657 MW2 in study
- Rio Vista Solar 28INR0260 · Solar · 554 MW · In study
- Rio Vista Storage 28INR0261 · Battery storage · 103 MW · In study
Woodhouse (38308) 138 kV 2 requests · 653 MW2 signed; security posted
- Springfield Solar 30INR0058 · Solar · 400 MW · Signed; security posted
- Selenite Springs Solar 29INR0147 · Solar · 253 MW · Signed; security posted
SANDLAKE_5 (11098) 345 kV 5 requests · 1,842 MW · 2 in Pecos County, 3 in Reeves, Ward5 in study
- Glass Mountain Wind 2 28INR0468 · Wind · 519 MW · In study · Reeves
- Glass Mountain Wind 1 29INR0194 · Wind · 512 MW · In study · Reeves
- Pecos Flats Solar II 29INR0182 · Solar · 302 MW · In study
- Pecos Flats Solar III 29INR0183 · Solar · 302 MW · In study
- New Minglewood Energy Center 27INR0255 · Battery storage · 208 MW · In study · Ward
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Pecos County
- Pecos County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 7, Midland: 10 Desta Dr, Ste 350E, Midland TX 79705-4530, 432-570-1359; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Pecos County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Pecos County.
Permits and reviews for Pecos County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Pecos County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Recent local action: In May 2025 the Pecos County Commissioners Court approved a series of wind energy initiatives involving Skyrider Wind, LLC and Big Canyon Wind, LLC. (Fort Stockton Pioneer; checked October 17, 2026).
How a project in Pecos County connects to the grid
Pecos County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Pecos County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Pecos County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 7
Andrews · Borden · Crane · Dawson · Ector · Gaines · Glasscock · Howard · Loving · Martin · Midland · Reeves · Terrell · Upton · Ward · Winkler