The MISO Queue Brief
Latest: issue 2026-11November 2026MISO queue as of November 3, 2026
November 2026: 1 new request (135 MW), 5 withdrawals (701 MW). 1,081 active requests, 250 GW.
Once a month, this brief takes a snapshot of MISO's public interconnection queue, the list of every generator and storage request across the 15 MISO states and Manitoba, and reports what changed: new requests, withdrawals, requests that moved to a later study phase, the points of interconnection filling up, and the schedules that slipped. The Texas edition is the ERCOT Queue Brief.
What each issue covers
- The month in numbers. New requests, withdrawals and net capacity by type and state.
- New requests and withdrawals. The largest, with point of interconnection, transmission owner, county, size and requested in-service date, as MISO lists them.
- Moved forward. Requests whose study phase or post-agreement status changed since the last snapshot.
- The active queue. Requests and MW by state, by MISO study region, by type and by stage.
- Crowded points of interconnection and schedules slipping.
How the counts are made
Each issue reads MISO's interactive generator interconnection queue on the first of the month and compares it with the previous month's snapshot by MISO project number. MISO publishes no coordinates and no developer names; county and state are as the developer entered them, and are often blank on new requests. A request is a study position, not a project. Illinois counties link to this site's Illinois county pages.
Issues
Subscribing
The ERCOT and MISO briefs go out by the same free email, once a month each.