Freestone County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects20
Total capacity5,357MW
Signed agreements8of 20
New since August0requests

20 proposed energy projects from ERCOT's September 2026 report, plus who to call in Freestone County and in TCEQ Region 9 before signing a solar, wind, or battery storage lease.

Check land in Freestone CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Freestone County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Freestone County?

ERCOT's September 2026 interconnection report lists 20 proposed energy projects in Freestone County (8 solar, 10 battery storage and 2 gas), about 5,357 MW in all. 8 of the 20 have a signed interconnection agreement, and 1 has been approved for energization or synchronization. The table also lists 2 changes to existing plants (repowers or capacity changes), not counted above.

What stands out in Freestone County

By capacity, gas leads in Freestone County with 2,265 MW across 2 projects, followed by solar (8 projects, 1,715 MW) and battery storage (10 projects, 1,377 MW); 2 self-limiting projects (reported at 0 MW because the resource limits its own output) are listed without a capacity. The largest single project is Jewett Energy Center 1 Gas, a 1,274 MW gas combined cycle project listed under Jewett Energy Center LLC, with an interconnection agreement signed in Jul 2026, and its target online date is Nov 2029. Of the 20, 12 are still in ERCOT's study process, 3 have a signed interconnection agreement but no security posted yet, 4 have posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 345 kV (7 projects) and 138 kV (6 projects) (why the voltage matters). Amerada Solar, LLC, Freestone Solar, LLC and Piedra Solar, LLC are each listed on 2 projects; 16 different companies appear in all. Target online dates for the projects not yet running span Jun 2027 to Nov 2029. All of them fall in ERCOT's North load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Piedra SolarTap 345-kV line Navarro (68091) – Limestone (46020))Piedra Solar, LLCSolar281.7Jan 2027Approved for synchronization
Fairway StorageTap 138kV 3503 FAIRWPOD_8 - 196 FAIRFIELDFairway Storage LLCBattery storage (stand-alone)120.3Sep 2027Signed; security posted
Piedra BESSTap 345-kV line Navarro (68091) – Limestone (46020)Piedra Solar, LLCBattery storage (paired with solar)103.7Dec 2027Signed; security posted
Douie SolarTap 138 kV 3501 Sea way Teague - 3394 JewettBuffalo Spring Solar LLCSolar221.2Apr 2028Signed; security posted
Utley SolarTap 345kV 3381 Big Brown Switch - 3391 JewettPalmera Solar Development, LLCSolar221.8May 2028Signed; security posted
Bar Candela Solar SLFLong Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279) · shared with 1 other requestBar Candela Solar Project LLCSolar200.3May 2029Signed May 2025
Bar Candela Storage SLFLong Lake Sub (Bus 3280) – Long Lake Tap Switch (Bus 3279) · shared with 1 other requestBar Candela Storage Project LLCBattery storage (paired with solar)Self-limitingMay 2029Signed May 2025
Jewett Energy Center 1 GasTap #3391 JEWETT_N5 - #46020 LMEST_POI_5 and Tap #3390 JEWETT_S5 -...Jewett Energy Center LLCGas combined cycle1,274.0Nov 2029Signed Jul 2026
Timber Cove Solar SLFTap 138 kV 212 Winkler - 3510 Pin Oak · shared with 1 other requestFreestone Solar, LLCSolar100.5Jun 2027In study
Timber Cove Storage SLFTap 138 kV 212 Winkler - 3510 Pin Oak · shared with 1 other requestFreestone Solar, LLCBattery storage (paired with solar)Self-limitingJun 2027In study
Three Canes Gas P1#3344 Tarantula Switching StationCleanAI, LLCGas engines0 no capacity changeNov 2027In study
Three Canes Gas P2Tap on the 345 kV Outlaw Switch (bus #3386) to Limestone Plant Stat...CleanAI, LLCGas engines0 no capacity changeNov 2027In study
Turtle Rock StorageTap 138 kV 13501 Clayhill to 13681 ReedTurtle Rock Energy Center, LLCBattery storage (stand-alone)135.6Jul 2028In study
Amerada StorageTap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5 · shared with 1 other requestAmerada Solar, LLCBattery storage (paired with solar)150.8Jul 2028In study
Freestone Battery Storage Project3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)Freestone Power Generation, LLCBattery storage (stand-alone)210.5Dec 2028In study
Amerada SolarTap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5 · shared with 1 other requestAmerada Solar, LLCSolar301.6Dec 2028In study
Simsboro StorageTap Outlaw (3386) – Limestone (46020)Simsboro Storage LLCBattery storage (stand-alone)301.6Mar 2029In study
Ratcliff SolarTap 138kV 3279 Long Lake Tap Switch - 3280 Long LakeGreenalia Solar Power RatcliffSolar85.7Apr 2029In study
Avant Prairie BESSTap 345kV BIGBRNE (#3380) - JEWETT (#3390) CKT 1Avant Prairie ESS LLCBattery storage (stand-alone)201.7Apr 2029In study
BM Freestone Energy CenterLoop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Brown W t...Black Mountain Energy Storage IIGas combined cycle990.6Sep 2029In study
Silver Dollar SolarTap 345 kV Big Brown 3380 to Navarro 68091 ckt#2 · shared with 1 other requestSilver Dollar Solar Project, LLCSolar301.9Oct 2029In study
Silver Dollar StorageTap 345 kV Big Brown 3380 to Navarro 68091 ckt#2 · shared with 1 other requestSilver Dollar Solar Project, LLCBattery storage (paired with solar)153.1Oct 2029In study

Crowded connection points in Freestone County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Navarro (68091) 345 kV 22 requests · 5,873 MW · 5 in Freestone County, 17 in Navarro, Ellis, Hill13 in study, 6 signed; security posted, 2 approved for synchronization, 1 approved for energization
  • Aquilla Lake 3 Wind 22INR0499 · Wind · 297 MW · Approved for synchronization · Hill
  • Piedra Solar 25INR0168 · Solar · 282 MW · Approved for synchronization
  • Oystercatcher Solar 21INR0362 · Solar · 198 MW · Approved for energization · Ellis
  • Tehuacana Creek Solar 24INR0188 · Solar · 505 MW · Signed; security posted · Navarro
  • TORMES SOLAR 22INR0437 · Solar · 357 MW · Signed; security posted · Navarro
  • Yellow Cat Wind 25INR0018 · Wind · 262 MW · Signed; security posted · Navarro
  • Glasgow Solar 24INR0206 · Solar · 204 MW · Signed; security posted · Navarro
  • Piedra BESS 25INR0169 · Battery storage · 104 MW · Signed; security posted
  • Glasgow Storage 24INR0207 · Battery storage · 101 MW · Signed; security posted · Navarro
  • Kickstart Energy Storage VI 29INR0218 · Battery storage · 1,026 MW · In study · Ellis
  • BM Freestone Energy Center 29INR0298 · Gas combined cycle · 991 MW · In study
  • Two Step Solar 29INR0196 · Solar · 402 MW · In study · Ellis
  • Silver Dollar Solar 27INR0186 · Solar · 302 MW · In study
  • Oak Valley Solar 28INR0335 · Solar · 251 MW · In study · Navarro
  • Silver Dollar Storage 27INR0187 · Battery storage · 153 MW · In study
  • Santa Monica Solar 26INR0228 · Solar · 106 MW · In study · Navarro
  • Pisgah Ridge Solar 2 24INR0086 · Solar · 102 MW · In study · Navarro
  • Kennedy Solar 24INR0256 · Solar · 102 MW · In study · Navarro
  • Pisgah Ridge Storage 3 24INR0087 · Battery storage · 101 MW · In study · Navarro
  • Kennedy Storage 24INR0391 · Battery storage · 25 MW · In study · Navarro
  • Kickstart Energy Storage III 27INR0471 · Battery storage · 1 MW · In study · Ellis
  • Kickstart Energy Storage IV 27INR0472 · Battery storage · 1 MW · In study · Ellis
Limestone (46020) 345 kV 12 requests · 5,105 MW · 4 in Freestone County, 7 in Leon, Navarro, Madison8 in study, 2 signed, 1 approved for synchronization, 1 signed; security posted
  • Piedra Solar 25INR0168 · Solar · 282 MW · Approved for synchronization
  • Piedra BESS 25INR0169 · Battery storage · 104 MW · Signed; security posted
  • Jewett Energy Center 1 Gas 29INR0150 · Gas combined cycle · 1,274 MW · Signed Jul 2026
  • Great Rock BESS 25INR0230 · Battery storage · 301 MW · Signed Aug 2024 · Leon
  • BM Great Rock Energy Center 30INR0091 · Gas combined cycle · 1,981 MW · In study · Leon
  • Simsboro Storage 29INR0119 · Battery storage · 302 MW · In study
  • Masava Storage 25INR0176 · Battery storage · 257 MW · In study · Madison
  • Savannah Oaks Solar 25INR0286 · Solar · 201 MW · In study · Madison
  • Kahla Storage 25INR0513 · Battery storage · 201 MW · In study · Leon
  • Pisgah Ridge Solar 2 24INR0086 · Solar · 102 MW · In study · Navarro
  • Pisgah Ridge Storage 3 24INR0087 · Battery storage · 101 MW · In study · Navarro
  • Three Canes Gas P2 27INR0652 · Gas engines · 0 MW · In study
Big Brown (3380) 345 kV 4 requests · 1,647 MW4 in study
  • BM Freestone Energy Center 29INR0298 · Gas combined cycle · 991 MW · In study
  • Silver Dollar Solar 27INR0186 · Solar · 302 MW · In study
  • Avant Prairie BESS 27INR0316 · Battery storage · 202 MW · In study
  • Silver Dollar Storage 27INR0187 · Battery storage · 153 MW · In study
BIGBRNW_5 (3381) 345 kV 5 requests · 1,285 MW · 3 in Freestone County, 2 in Navarro3 in study, 2 signed; security posted
  • Tehuacana Creek Solar 24INR0188 · Solar · 505 MW · Signed; security posted · Navarro
  • Utley Solar 24INR0117 · Solar · 222 MW · Signed; security posted
  • Amerada Solar 26INR0082 · Solar · 302 MW · In study
  • Amerada Storage 26INR0084 · Battery storage · 151 MW · In study
  • Santa Monica Solar 26INR0228 · Solar · 106 MW · In study · Navarro
Long Lake (3280) 138 kV 3 requests · 286 MW2 signed, 1 in study
  • Bar Candela Solar SLF 24INR0269 · Solar · 200 MW · Signed May 2025
  • Bar Candela Storage SLF 24INR0271 · Battery storage · 0 MW · Signed May 2025
  • Ratcliff Solar 24INR0289 · Solar · 86 MW · In study
Long Lake (3279) 138 kV 3 requests · 286 MW2 signed, 1 in study
  • Bar Candela Solar SLF 24INR0269 · Solar · 200 MW · Signed May 2025
  • Bar Candela Storage SLF 24INR0271 · Battery storage · 0 MW · Signed May 2025
  • Ratcliff Solar 24INR0289 · Solar · 86 MW · In study
Jewett (3391) 345 kV 2 requests · 1,496 MW1 signed; security posted, 1 signed
  • Utley Solar 24INR0117 · Solar · 222 MW · Signed; security posted
  • Jewett Energy Center 1 Gas 29INR0150 · Gas combined cycle · 1,274 MW · Signed Jul 2026
Pin Oak (3510) 138 kV 2 requests · 100 MW2 in study
  • Timber Cove Solar SLF 24INR0532 · Solar · 100 MW · In study
  • Timber Cove Storage SLF 26INR0394 · Battery storage · 0 MW · In study
RICHLND2_5 (3133) 345 kV 2 requests · 452 MW2 in study
  • Amerada Solar 26INR0082 · Solar · 302 MW · In study
  • Amerada Storage 26INR0084 · Battery storage · 151 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Freestone County

  • Freestone County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 9, Waco: 6801 Sanger Ave, Ste 2500, Waco TX 76710-7826, 254-751-0335; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Freestone County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Freestone County.

Permits and reviews for Freestone County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Freestone County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Recent local action: At its June 18, 2025 meeting, the Freestone County Commissioners Court unanimously approved Reinvestment Zone 10, to be used for solar power generation by Freestone Solar LLC, a designation that allows the county to enter into tax abatement agreements. County Judge Linda Grant was directed to send notice of intent to enter into the proposed tax abatement agreement. (Freestone County Times; checked October 17, 2026).

How a project in Freestone County connects to the grid

Freestone County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Freestone County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Freestone County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 9