Arizona: solar, wind, and storage projects and rules

EIA data: August 2026 file · Rules checked October 7, 2026

Arizona has no state permit for solar, wind, or battery plants, so counties, the State Land Department, and each utility's own interconnection process do most of the deciding. Here is what is planned in each county and the rules for landowners, businesses, and homeowners.

Jump to: Projects by county · State permits · Taxes · Trust land · Lease rates · Water · Batteries · Grid · Homes · Businesses

How many power plants are planned in Arizona?

EIA's August 2026 survey lists 41 planned plants in Arizona, about 15,413 MW (27 with battery storage, 26 with solar, 3 with gas (combustion turbine), 1 with solar thermal, 1 with gas (combined cycle)). Plants that pair solar with batteries count once.

CountyPlanned plantsMW
Maricopa103,792
La Paz113,013
Coconino42,700
Pinal62,272
Navajo31,900
Yuma31,118
Cochise2351
Mohave2267
Apache00
Gila00
Graham00
Greenlee00
Pima00
Santa Cruz00
Yavapai00

Source: U.S. Energy Information Administration, Form EIA-860M, August 2026 file, planned generators. Stages, from EIA's status codes: planned with approvals not started, approvals pending, approvals received, under construction (up to or over half done), and built but not yet operating. EIA lists generators that owners have reported as planned, from early planning through construction; utilities' own interconnection queues list many more requests that may never be built. The balancing authority code shows whose grid the plant joins (AZPS = APS, SRP = Salt River Project, TEPC = Tucson Electric Power, WALC = WAPA Desert Southwest, CISO = California ISO). Parcel & Grid is not affiliated with EIA.

Does Arizona require a state permit for solar, wind, or storage?

Property taxes on solar, wind, and storage

State trust land and federal land

What are developers paying Arizona landowners?

We found no published survey of private-land solar or wind lease rates in Arizona. The only official figures are State Land Department auction terms, like the example above. Compare any offer with the questions in is my offer fair? Record the lease or a memorandum of it with the county recorder: an unrecorded instrument does not give notice to later buyers (A.R.S. 33-411; 33-412).

Water

Arizona has eight Active Management Areas, where groundwater use is regulated (ADWR). The newest include Willcox, designated January 8, 2025 (ADWR: Willcox AMA). Water for construction and dust control can be a real constraint; ask the developer where it will come from.

Battery storage safety

State and federal offices a project deals with

How projects connect to the grid in Arizona

Arizona has no regional grid operator running a shared queue. Each transmission owner runs its own interconnection process under its federal tariff:

APS (2016), SRP (2020), and TEP (2022) trade in the Western Energy Imbalance Market (CAISO WEIM report). In November 2024, APS, SRP, TEP, and UNS Electric announced plans to join SPP's Markets+ (ACC), which targets an October 2027 start (SPP Markets+). See the western timeline and utility application links.

Solar and batteries for Arizona homes

What you are paid for extra solar depends on whether your utility is regulated by the Arizona Corporation Commission (APS, Tucson Electric Power, UniSource Energy, and the co-ops) or is SRP, which sets its own prices.

Solar and batteries for Arizona businesses

Federal tax credits after the July 2025 law

Tax rules depend on your situation; ask a tax professional before relying on any credit.

Check before you sign. Laws, county ordinances, and utility rates change. General information, not a substitute for the advice of an attorney. Found an error? Let us know.