Proposed projects17
Total capacity4,064MW
Signed agreements6of 17
New since August0requests

17 proposed energy projects from ERCOT's September 2026 report, plus who to call in Guadalupe County and in TCEQ Region 13 before signing a solar, wind, or battery storage lease.

Check land in Guadalupe CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Guadalupe County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Guadalupe County?

ERCOT's September 2026 interconnection report lists 17 proposed energy projects in Guadalupe County (4 solar, 4 battery storage and 9 gas), about 4,064 MW in all. 6 of the 17 have a signed interconnection agreement, and 3 have been approved for energization or synchronization.

What stands out in Guadalupe County

By capacity, gas leads in Guadalupe County with 2,460 MW across 9 projects, followed by battery storage (4 projects, 826 MW) and solar (4 projects, 778 MW). The largest single project is Calpine Guadalupe Peakers, a 450 MW gas turbine project listed under Guadalupe Peaking Energy Center, LLC, still in study, and its target online date is May 2030. Of the 17, 11 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet, 2 have posted security or started construction and 3 are approved for energization or synchronization. Connection points are mostly at 345 kV (13 projects) and 138 kV (2 projects) (why the voltage matters). The single most-used connection point is 345kV 7042 Zorn Substation, shared by 5 projects. Palomino Alpha, LLC is listed on the most projects here (5 of 17); 10 different companies appear in all. Target online dates for the projects not yet running span Jun 2028 to Dec 2032. All of them fall in ERCOT's South load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
CPS Rio Nogales CT201 Rotor Replacement5362 RIONOG 345kV · shared with 1 other requestCPS EnergyGas combined cycle3.1Aug 2026Approved for synchronization
CPS Rio Nogales CT301 Rotor Replacement5362 RIONOG 345kV · shared with 1 other requestCPS EnergyGas combined cycle3.1Aug 2026Approved for synchronization
Rio Nogales CT1 Rotor ReplacementRio Nogales SubstationCPS EnergyGas combined cycle3.1Aug 2026Approved for synchronization
Nockenut Springs Solar 1tap 345kV 5133 Elm Creek - 5915 STP ckt 1 · shared with 2 other requestsPecan Springs Energy, LLCSolar203.2Jun 2029Signed; security posted
Nockenut Springs Solar 2tap 345kV 5133 Elm Creek - 5915 STP ckt 1 · shared with 2 other requestsPecan Springs Energy, LLCSolar203.3Jun 2029Signed; security posted
Rockridge Solar7225 Hickory Forest 138kVMagnolia Solar Development, LLCSolar211.2Jun 2028Signed Mar 2025
Ruedrich BESSLINE TAP OF CIBOLO (7608) AND McQUEENEY (7606)Ruedrich BESSBattery storage (stand-alone)200.6Nov 2028In study
Roble BESS7180 L_ZORN__8_1Y 138kVFlexen USA LLCBattery storage (stand-alone)154.3Dec 2028In study
Alpha Power Phase 1345kV 7042 Zorn Substation · shared with 4 other requestsPalomino Alpha, LLCGas turbine400.1Dec 2028In study
Aster Solar7042 Zorn 345kVAster SolarSolar160.5Jun 2029In study
Enfinity Juniper StorageHickory Forest (7225)EG Juniper LLCBattery storage (stand-alone)261.1Dec 2029In study
Alpha Power Phase 2345kV 7042 Zorn Substation · shared with 4 other requestsPalomino Alpha, LLCGas turbine400.1Dec 2029In study
Calpine Guadalupe Peakers7044 Marion 345kVGuadalupe Peaking Energy Center, LLCGas turbine450.0May 2030In study
Guadalupe Battery Storage Project# 7044 Marion 345kVGuadalupe Power Partners, LPBattery storage (stand-alone)210.5May 2030In study
Alpha Power Phase 3345kV 7042 Zorn Substation · shared with 4 other requestsPalomino Alpha, LLCGas turbine400.1Dec 2030In study
Alpha Power Phase 4345kV 7042 Zorn Substation · shared with 4 other requestsPalomino Alpha, LLCGas turbine400.1Dec 2031In study
Alpha Power Phase 5345kV 7042 Zorn Substation · shared with 4 other requestsPalomino Alpha, LLCGas turbine400.1Dec 2032In study

Crowded connection points in Guadalupe County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Zorn (7042) 345 kV 14 requests · 4,993 MW · 6 in Guadalupe County, 8 in Caldwell, Bastrop9 in study, 5 signed
  • SCHNEIDER COMBINED CYCLE 30INR0054 · Gas combined cycle · 880 MW · Signed Dec 2025 · Caldwell
  • Waterloo Solar 1 25INR0422 · Solar · 201 MW · Signed Sep 2024 · Bastrop
  • Waterloo BESS 1 25INR0447 · Battery storage · 120 MW · Signed Sep 2024 · Bastrop
  • SCHNEIDER GAS RICE 29INR0176 · Gas engines · 113 MW · Signed Dec 2025 · Caldwell
  • SCHNEIDER GAS RICE PHASE 2 31INR0013 · Gas engines · 113 MW · Signed Dec 2025 · Caldwell
  • Fort Worth Power Core Bastrop Gas Plant 26INR0560 · Gas combined cycle · 506 MW · In study · Bastrop
  • Bobcat Generating Station 29INR0340 · Gas engines · 450 MW · In study · Caldwell
  • Big Watt Power Austin-1 29INR0167 · Gas combined cycle · 449 MW · In study · Caldwell
  • Alpha Power Phase 1 28INR0532 · Gas turbine · 400 MW · In study
  • Alpha Power Phase 2 29INR0363 · Gas turbine · 400 MW · In study
  • Alpha Power Phase 3 30INR0143 · Gas turbine · 400 MW · In study
  • Alpha Power Phase 4 31INR0025 · Gas turbine · 400 MW · In study
  • Alpha Power Phase 5 32INR0007 · Gas turbine · 400 MW · In study
  • Aster Solar 24INR0115 · Solar · 160 MW · In study
Elm Creek (5133) 345 kV 19 requests · 4,695 MW · 2 in Guadalupe County, 17 in Wilson, Gonzales, DeWitt12 in study, 7 signed; security posted
  • Clear Fork Creek Solar 23INR0027 · Solar · 602 MW · Signed; security posted · Wilson
  • Anila BESS 26INR0077 · Battery storage · 209 MW · Signed; security posted · Wilson
  • Shaula I Solar 22INR0251 · Solar · 205 MW · Signed; security posted · DeWitt
  • Shaula II Solar 22INR0267 · Solar · 205 MW · Signed; security posted · DeWitt
  • Nockenut Springs Solar 2 24INR0007 · Solar · 203 MW · Signed; security posted
  • Nockenut Springs Solar 1 23INR0088 · Solar · 203 MW · Signed; security posted
  • Anila Solar 26INR0074 · Solar · 201 MW · Signed; security posted · Wilson
  • Mojo Solar 28INR0250 · Solar · 528 MW · In study · Wilson
  • Wilson Gas Plant 28INR0494 · Gas engines · 403 MW · In study · Wilson
  • Columbine Wind 29INR0063 · Wind · 295 MW · In study · Gonzales
  • Nockenut Springs Storage 2 29INR0319 · Battery storage · 209 MW · In study · Wilson
  • Nockenut Springs Storage 3 29INR0320 · Battery storage · 209 MW · In study · Wilson
  • Nockenut Springs Storage 1 29INR0318 · Battery storage · 209 MW · In study · Wilson
  • Shaula III Solar 23INR0009 · Solar · 205 MW · In study · DeWitt
  • Marcelina Storage 23INR0318 · Battery storage · 203 MW · In study · Wilson
  • Nockenut Springs Solar 3 25INR0010 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 4 25INR0193 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 5 25INR0280 · Solar · 201 MW · In study · Gonzales
  • Cachena Storage SLF 23INR0077 · Battery storage · 0 MW · In study · Wilson
STP (5915) 345 kV 17 requests · 5,264 MW · 2 in Guadalupe County, 15 in Matagorda, DeWitt, Gonzales8 signed; security posted, 6 in study, 2 signed, 1 approved for synchronization
  • Charger Solar 23INR0047 · Solar · 397 MW · Approved for synchronization · Refugio
  • Duffy Solar 23INR0057 · Solar · 502 MW · Signed; security posted · Matagorda
  • Duffy BESS 26INR0250 · Battery storage · 241 MW · Signed; security posted · Matagorda
  • Shaula I Solar 22INR0251 · Solar · 205 MW · Signed; security posted · DeWitt
  • Shaula II Solar 22INR0267 · Solar · 205 MW · Signed; security posted · DeWitt
  • Nockenut Springs Solar 2 24INR0007 · Solar · 203 MW · Signed; security posted
  • Nockenut Springs Solar 1 23INR0088 · Solar · 203 MW · Signed; security posted
  • Eldora BESS 24INR0338 · Battery storage · 201 MW · Signed; security posted · Matagorda
  • Eldora Solar 24INR0337 · Solar · 201 MW · Signed; security posted · Matagorda
  • Oak Tree Energy Storage 27INR0091 · Battery storage · 310 MW · Signed May 2026 · Lavaca
  • Iguala Solar 23INR0090 · Solar · 250 MW · Signed Jul 2025 · Victoria
  • STP Unit2 High Pressure Turbine Upgrade 27INR0557 · Nuclear · 1,337 MW · In study · Matagorda
  • Shaula III Solar 23INR0009 · Solar · 205 MW · In study · DeWitt
  • Nockenut Springs Solar 3 25INR0010 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 4 25INR0193 · Solar · 201 MW · In study · Gonzales
  • Nockenut Springs Solar 5 25INR0280 · Solar · 201 MW · In study · Gonzales
  • Percy Farm Solar 24INR0020 · Solar · 199 MW · In study · Matagorda
Marion (7044) 345 kV 2 requests · 660 MW2 in study
  • Calpine Guadalupe Peakers 24INR0145 · Gas turbine · 450 MW · In study
  • Guadalupe Battery Storage Project 27INR0093 · Battery storage · 210 MW · In study
Hickory Forest (7225) 138 kV 2 requests · 472 MW1 signed, 1 in study
  • Rockridge Solar 24INR0287 · Solar · 211 MW · Signed Mar 2025
  • Enfinity Juniper Storage 29INR0211 · Battery storage · 261 MW · In study
Rionog (5362) 345 kV 2 requests · 6 MW2 approved for synchronization
  • CPS Rio Nogales CT301 Rotor Replacement 24INR0602 · Gas combined cycle · 3 MW · Approved for synchronization
  • CPS Rio Nogales CT201 Rotor Replacement 25INR0665 · Gas combined cycle · 3 MW · Approved for synchronization

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Guadalupe County

  • Guadalupe County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 13, San Antonio: 14250 Judson Rd, San Antonio TX 78233-4480, 210-490-3096; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Guadalupe County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Guadalupe County.

Permits and reviews for Guadalupe County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Guadalupe County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Guadalupe County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.

How a project in Guadalupe County connects to the grid

Guadalupe County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Guadalupe County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Guadalupe County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 13

Atascosa · Bandera · Bexar · Comal · Edwards · Frio · Gillespie · Karnes · Kendall · Kerr · Medina · Real · Uvalde · Wilson

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.

Browse resources