Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Wilbarger County

Wilbarger County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects21
Total capacity8,506MW
Signed agreements8of 21
New since August0requests

21 proposed energy projects from ERCOT's September 2026 report, plus who to call in Wilbarger County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.

Check land in Wilbarger CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Wilbarger County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Wilbarger County?

ERCOT's September 2026 interconnection report lists 21 proposed energy projects in Wilbarger County (9 solar, 1 wind, 6 battery storage and 5 gas), about 8,506 MW in all. 8 of the 21 have a signed interconnection agreement, and 1 has been approved for energization or synchronization.

What stands out in Wilbarger County

By capacity, gas leads in Wilbarger County with 5,208 MW across 5 projects, followed by solar (9 projects, 2,318 MW) and battery storage (6 projects, 835 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Limitless Energy Hub I, a 1,238 MW gas combined cycle project listed under Limitless Energy Hub I LLC, with an interconnection agreement signed in Dec 2025, and its target online date is Dec 2028. Of the 21, 13 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet, 6 have posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 345 kV (19 projects) and 138 kV (2 projects) (why the voltage matters). The single most-used connection point is Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B, shared by 3 projects. Felix 1, LLC is listed on the most projects here (3 of 21); 15 different companies appear in all. Target online dates for the projects not yet running span Jul 2027 to Feb 2032. All of them fall in ERCOT's West load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Blue Summit Energy Storage61001 JIM TREECE 345kVNextEra Energy Interconnection Holdings, LLCBattery storage100.0Jul 2026Approved for synchronization
Adamstown Solartap 345kV 1730 West Krum - 6111 Riley Ckt 2Adams Creek Solar Project, LLCSolar250.9Aug 2027Signed; security posted
Dundee West Wind345 kV Riley Substation (#6101); AEP · shared with 2 other requestsFelix 2, LLCWind146.5Dec 2027Signed; security posted
Limitless Energy Hub IITap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. · shared with 1 other requestLimitless Energy Hub II LLCGas combined cycle1,238.2Dec 2028Signed; security posted
Felix East SolarThe 345 kV Riley Substation (#6101); AEP · shared with 1 other requestFelix 1, LLCSolar200.9Dec 2028Signed; security posted
Felix North Solar6101 Riley 345kVCrescent Solar, LLCSolar201.0Dec 2028Signed; security posted
Felix West Solar6101 Riley 345 kV · shared with 1 other requestFelix 1, LLCSolar200.9Dec 2028Signed; security posted
Limitless Energy Hub ITap 345kV 6101 RILEY7A - 60505 EDITHCLA7B. · shared with 1 other requestLimitless Energy Hub I LLCGas combined cycle1,238.2Dec 2028Signed Dec 2025
Felix StorageThe 345 kV Riley Substation (#6101); AEP · shared with 1 other requestFelix 1, LLCBattery storage (paired with solar)100.5Jul 2027In study
TEXPO6101 Riley 345 kV · shared with 1 other requestOklaunion Power Station, LLCGas steam turbine680.0Oct 2027In study
Wander Waters BESS61001 JIMTREEC7A 345kVWander Waters BESS LLCBattery storage (stand-alone)303.5Oct 2027In study
Reunion SolarTap 345kV #60504 Tesla Road to #6111 Riley · shared with 1 other requestReunion Solar, LLCSolar600.9Jul 2028In study
Reunion StorageTap 345kV #60504 Tesla Road to #6111 Riley · shared with 1 other requestReunion Solar, LLCBattery storage (paired with solar)200.3Jul 2028In study
White Wing SolarTap 345 kV (#60504) Tesla - (#6111) Riley · shared with 1 other requestWhite Wing Solar, LLCSolar127.4Jul 2028In study
White Wing StorageTap 345 kV (#60504) Tesla - (#6111) Riley · shared with 1 other requestWhite Wing Solar, LLCBattery storage (paired with solar)130.4Jul 2028In study
Proteus Vernon Solar SLF6060 Vernon 138kV · shared with 1 other requestVernon Solar and Storage LLC (a Delaware LLC)Solar75.0Feb 2029In study
Proteus Vernon Storage SLF6060 Vernon 138kV · shared with 1 other requestVernon Solar and Storage LLC (a Delaware LLC)Battery storage (paired with solar)Self-limitingFeb 2029In study
Poco Trail SolarTap 345kV 6101 Riley - 1422 BowmanEastern Trail Solar Center, LLCSolar438.8Apr 2029In study
Grayback SolarTap 345kV 6101 RILEY7A - 60505 EDITHCLA7B · shared with 5 other requestsGrayback Solar, LLCSolar221.8Sep 2029In study
H&C WILBARGER POWER ITap 345kV 6101 RILEY7A - 60505 EDITHCLA7B · shared with 5 other requestsH&C WILBARGER POWER IGas combined cycle1,025.5Feb 2032In study
H&C WILBARGER POWER IITap 345kV 6101 RILEY7A - 60505 EDITHCLA7B · shared with 5 other requestsH&C WILBARGER POWER IGas combined cycle1,025.5Feb 2032In study

Crowded connection points in Wilbarger County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

RILEY7A (6101) 345 kV 22 requests · 9,936 MW · 12 in Wilbarger County, 10 in Wichita, Foard, Baylor12 in study, 9 signed; security posted, 1 signed
  • Limitless Energy Hub II 27INR0582 · Gas combined cycle · 1,238 MW · Signed; security posted
  • Short Creek Solar 24INR0201 · Solar · 628 MW · Signed; security posted · Wichita
  • Dundee East A Wind 27INR0005 · Wind · 524 MW · Signed; security posted · Baylor
  • Dundee East B Wind 27INR0011 · Wind · 261 MW · Signed; security posted · Baylor
  • Felix North Solar 22INR0209 · Solar · 201 MW · Signed; security posted
  • Felix West Solar 27INR0012 · Solar · 201 MW · Signed; security posted
  • Felix East Solar 27INR0007 · Solar · 201 MW · Signed; security posted
  • Short Creek BESS 27INR0029 · Battery storage · 156 MW · Signed; security posted · Wichita
  • Dundee West Wind 27INR0004 · Wind · 146 MW · Signed; security posted
  • Limitless Energy Hub I 27INR0581 · Gas combined cycle · 1,238 MW · Signed Dec 2025
  • H&C WILBARGER POWER I 32INR0006 · Gas combined cycle · 1,026 MW · In study
  • H&C WILBARGER POWER II 32INR0008 · Gas combined cycle · 1,026 MW · In study
  • TEXPO 22INR0497 · Gas steam turbine · 680 MW · In study
  • Big Field Solar 29INR0148 · Solar · 506 MW · In study · Foard
  • Poco Trail Solar 23INR0273 · Solar · 439 MW · In study
  • Copperleaf Energy Storage 28INR0118 · Battery storage · 306 MW · In study · Wichita
  • Pease River Solar 28INR0476 · Solar · 276 MW · In study · Foard
  • Grayback Solar 28INR0464 · Solar · 222 MW · In study
  • Supra Wind 27INR0063 · Wind · 206 MW · In study · Hardeman
  • Daisy Solar 28INR0535 · Solar · 201 MW · In study · Foard
  • Wichita County Mawson Storage 26INR0613 · Battery storage · 154 MW · In study · Wichita
  • Felix Storage 27INR0009 · Battery storage · 101 MW · In study
Riley (6111) 345 kV 15 requests · 4,272 MW · 5 in Wilbarger County, 10 in Wichita, Clay, Montague11 in study, 4 signed; security posted
  • Soleil Solar 25INR0097 · Solar · 452 MW · Signed; security posted · Clay
  • Adamstown Solar 21INR0210 · Solar · 251 MW · Signed; security posted
  • Nymphaea Solar 25INR0154 · Solar · 121 MW · Signed; security posted · Wichita
  • Nymphaea Storage 25INR0155 · Battery storage · 61 MW · Signed; security posted · Wichita
  • Hiru Solar 23INR0228 · Solar · 604 MW · In study · Clay
  • Reunion Solar 28INR0332 · Solar · 601 MW · In study
  • Hiru Storage 24INR0444 · Battery storage · 504 MW · In study · Clay
  • Prairie Branch BESS 28INR0423 · Battery storage · 310 MW · In study · Montague
  • Gilleys Energy Storage 25INR0656 · Battery storage · 306 MW · In study · Wise
  • Prairie Branch Solar 28INR0422 · Solar · 301 MW · In study · Montague
  • Wichita Creek Storage 28INR0378 · Battery storage · 300 MW · In study · Wichita
  • Reunion Storage 28INR0333 · Battery storage · 200 MW · In study
  • White Wing Storage 27INR0333 · Battery storage · 130 MW · In study
  • White Wing Solar 27INR0332 · Solar · 127 MW · In study
  • Wichita Creek Solar 28INR0377 · Solar · 3 MW · In study · Wichita
EDITHCLA7B (60505) 345 kV 13 requests · 6,946 MW · 5 in Wilbarger County, 8 in Hardeman, Foard11 in study, 1 signed, 1 signed; security posted
  • Limitless Energy Hub II 27INR0582 · Gas combined cycle · 1,238 MW · Signed; security posted
  • Limitless Energy Hub I 27INR0581 · Gas combined cycle · 1,238 MW · Signed Dec 2025
  • H&C WILBARGER POWER I 32INR0006 · Gas combined cycle · 1,026 MW · In study
  • H&C WILBARGER POWER II 32INR0008 · Gas combined cycle · 1,026 MW · In study
  • Big Field Solar 29INR0148 · Solar · 506 MW · In study · Foard
  • Pease River Solar 28INR0476 · Solar · 276 MW · In study · Foard
  • Lazy U Solar 1 26INR0171 · Solar · 252 MW · In study · Hardeman
  • Lazy U Solar 2 26INR0172 · Solar · 252 MW · In study · Hardeman
  • Juniper Ridge BESS 1 26INR0173 · Battery storage · 252 MW · In study · Hardeman
  • Juniper Ridge BESS 2 26INR0174 · Battery storage · 252 MW · In study · Hardeman
  • Grayback Solar 28INR0464 · Solar · 222 MW · In study
  • Supra Wind 27INR0063 · Wind · 206 MW · In study · Hardeman
  • Daisy Solar 28INR0535 · Solar · 201 MW · In study · Foard
Tesla (60504) 345 kV 6 requests · 1,936 MW · 4 in Wilbarger County, 2 in Hardeman6 in study
  • Reunion Solar 28INR0332 · Solar · 601 MW · In study
  • Tabor Solar 23INR0055 · Solar · 506 MW · In study · Hardeman
  • Earthwise Solar 23INR0233 · Solar · 370 MW · In study · Hardeman
  • Reunion Storage 28INR0333 · Battery storage · 200 MW · In study
  • White Wing Storage 27INR0333 · Battery storage · 130 MW · In study
  • White Wing Solar 27INR0332 · Solar · 127 MW · In study
Vernon (6060) 138 kV 2 requests · 75 MW2 in study
  • Proteus Vernon Solar SLF 25INR0377 · Solar · 75 MW · In study
  • Proteus Vernon Storage SLF 25INR0416 · Battery storage · 0 MW · In study
Jim Treece (61001) 345 kV 4 requests · 1,280 MW · 2 in Wilbarger County, 2 in Hardeman3 in study, 1 approved for synchronization
  • Blue Summit Energy Storage 25INR0492 · Battery storage · 100 MW · Approved for synchronization
  • Tabor Solar 23INR0055 · Solar · 506 MW · In study · Hardeman
  • Earthwise Solar 23INR0233 · Solar · 370 MW · In study · Hardeman
  • Wander Waters BESS 27INR0207 · Battery storage · 304 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Wilbarger County

  • Wilbarger County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Wilbarger County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Wilbarger County.

Permits and reviews for Wilbarger County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Wilbarger County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Wilbarger County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.

How a project in Wilbarger County connects to the grid

Wilbarger County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Wilbarger County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Wilbarger County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 3

Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Young

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.

Browse resources