Cameron County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
26 proposed energy projects from ERCOT's September 2026 report, plus who to call in Cameron County and in TCEQ Region 15 before signing a solar, wind, or battery storage lease.
Check land in Cameron CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Cameron County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Cameron County?
ERCOT's September 2026 interconnection report lists 26 proposed energy projects in Cameron County (5 solar, 1 wind, 18 battery storage, 1 gas and 1 hydro), about 5,766 MW in all. 5 of the 26 have a signed interconnection agreement, and 2 have been approved for energization or synchronization.
What stands out in Cameron County
By capacity, battery storage leads in Cameron County with 2,942 MW across 18 projects, followed by gas (1 project, 1,536 MW) and solar (5 projects, 908 MW). The largest single project is Aegle Power, a 1,536 MW gas combined cycle project listed under Aegle Power LLC, still in study, and its target online date is Jul 2027. Of the 26, 21 are still in ERCOT's study process, 3 have posted security or started construction and 2 are approved for energization or synchronization. Connection points are mostly at 345 kV (14 projects), 138 kV (9 projects) and 69 kV (3 projects) (why the voltage matters). BT Cantwell Solar, LLC, Gransolar Texas Four LLC and PUERTO DEL SOL, LLC are each listed on 2 projects; 23 different companies appear in all. Target online dates for the projects not yet running span Dec 2026 to Apr 2030. All of them fall in ERCOT's Coastal load zone. 2 that were listed in August have since dropped off.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Harlingen #1 BESS 1Harlingen #1 | Harlingen ESS Assets LLC | Battery storage (stand-alone) | 10.0 | Aug 2026 | Approved for synchronization |
| Arroyo StorageTap 345kV 8318 Rio Hondo - 8317 La Palma (New Gulch Substation ) | BT Cantwell Solar, LLC | Battery storage (paired with solar) | 183.8 | Oct 2026 | Approved for synchronization |
| Arroyo Solar345 KV Tap #8318 Rio Hondo - #8317 La Palma | BT Cantwell Solar, LLC | Solar | 100.0 | Feb 2028 | Signed; security posted |
| Resaca Oasis Storage# 79601 Stillman Substation 138 kV | Resaca Oasis Storage, LLC | Battery storage (stand-alone) | 200.7 | Sep 2028 | Signed; security posted |
| Eval Storage80229 Cavazos 138kV | Hecate Grid East Valley Storage LLC | Battery storage (stand-alone) | 251.8 | Apr 2029 | Signed; security posted |
| Puerto Del Sol 1Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1 · shared with 1 other request | PUERTO DEL SOL, LLC | Solar | 213.8 | Dec 2026 | In study |
| Aegle Power(#79501) Kingfisher 345 kV | Aegle Power LLC | Gas combined cycle | 1,536.4 | Jul 2027 | In study |
| Bobcat Cameron BESS5764 East Rio Hondo Substation 138kV | Bobcat BESS, LLC | Battery storage (stand-alone) | 200.8 | Dec 2027 | In study |
| Puerto Del Sol 2Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1 · shared with 1 other request | PUERTO DEL SOL, LLC | Solar | 213.8 | Dec 2027 | In study |
| Amberjack2 BESS79501 KINGFISHER 345KV | Hunt Energy Network, LLC | Battery storage (stand-alone) | 180.0 | Apr 2028 | In study |
| Harryoung SolarTap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV | Gransolar Texas Four LLC | Solar | 190.0 | May 2028 | In study |
| HarryoungBESS8319 Rio Hondo sub 138kV | Gransolar Texas Four LLC | Battery storage (paired with solar) | 190.0 | May 2028 | In study |
| Ouroboros Grid BESS 1POIB: #88337 Chalybe 345 kV | Ouroboros Grid BESS Unit 1 | Battery storage (stand-alone) | 200.8 | Jun 2028 | In study |
| Ouroboros Grid BESS 288337 Chalybe 345 kV · shared with 1 other request | Ouroboros Grid BESS Unit 2 | Battery storage (stand-alone) | 200.8 | Jun 2028 | In study |
| Ouroboros Grid BESS 388337 Chalybe 345 kV · shared with 1 other request | Ouroboros Grid BESS Unit 3 | Battery storage (stand-alone) | 200.7 | Jun 2028 | In study |
| Rio Hondo BESSTap 138kV #80309 Las Pulgas - #8319 Rio Hondo | SBESS TX25 LLC | Battery storage (stand-alone) | 200.8 | Jun 2028 | In study |
| Megacharge BESS8320 WEST HARLINGEN 69kV | SMT Harlingen III LLC | Battery storage (stand-alone) | 110.0 | Jul 2028 | In study |
| Burro Loco Energy Storage8626 Resaca 69kV | VESI | Battery storage (stand-alone) | 25.1 | Sep 2028 | In study |
| Harper Energy StorageTap 138kV 8314 La Palma - 80229 Villa Cavazos | VESI 31 LLC | Battery storage (stand-alone) | 82.4 | Sep 2028 | In study |
| Rio Grand Valley Element Fuels PowerTap 138kV 59450 Waterport Substation - 5789 Southmost Sub | Element H2Gen, LLC | Hydro | 79.6 | Dec 2028 | In study |
| Solar Star Frontier BESS8656 Luna 138kV | Solar Star Frontier BESS, LLC | Battery storage (stand-alone) | 101.0 | Feb 2029 | In study |
| Accalia Point SolarTap 345kV 8383 North Edingburg – 79501 Kingfisher | Accalia Point Solar LLC | Solar | 190.5 | May 2029 | In study |
| Ouroboros Grid BESS 479500 Palmito 345kV · shared with 2 other requests | Ouroboros Grid BESS Unit 4 | Battery storage (stand-alone) | 201.1 | Jun 2029 | In study |
| Ouroboros Grid BESS 579500 Palmito 345KV · shared with 2 other requests | Ouroboros Grid BESS Unit 5 | Battery storage (stand-alone) | 201.0 | Jun 2029 | In study |
| Ouroboros Grid BESS 679500 Palmito 345KV · shared with 2 other requests | Ouroboros Grid BESS Unit 6 | Battery storage (stand-alone) | 200.9 | Jun 2029 | In study |
| Pachanga Windtap 345kV 5966 Palmito - 80137 Stewart Rd | Pachanga Wind LLC | Wind | 300.0 | Apr 2030 | In study |
No longer listed since August
These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.
- Alexandrite Storage, battery storage, 203 MW (Johnson Energy Storage, LLC)
- Mesquite BESS2, battery storage, 10 MW (Mesquite Clean Energy Center, LLC)
Crowded connection points in Cameron County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Kingfisher (79501) 345 kV 5 requests · 2,334 MW5 in study
- Aegle Power 27INR0084 · Gas combined cycle · 1,536 MW · In study
- Puerto Del Sol 1 26INR0008 · Solar · 214 MW · In study
- Puerto Del Sol 2 27INR0002 · Solar · 214 MW · In study
- Accalia Point Solar 23INR0066 · Solar · 190 MW · In study
- Amberjack2 BESS 26INR0640 · Battery storage · 180 MW · In study
Palmito (79500) 345 kV 5 requests · 1,031 MW5 in study
- Puerto Del Sol 1 26INR0008 · Solar · 214 MW · In study
- Puerto Del Sol 2 27INR0002 · Solar · 214 MW · In study
- Ouroboros Grid BESS 4 28INR0427 · Battery storage · 201 MW · In study
- Ouroboros Grid BESS 5 28INR0428 · Battery storage · 201 MW · In study
- Ouroboros Grid BESS 6 28INR0429 · Battery storage · 201 MW · In study
Rio Hondo (8319) 138 kV 4 requests · 766 MW · 3 in Cameron County, 1 in Willacy4 in study
- Rio Hondo BESS 26INR0461 · Battery storage · 201 MW · In study
- Harryoung Solar 25INR0270 · Solar · 190 MW · In study
- HarryoungBESS 25INR0552 · Battery storage · 190 MW · In study
- Los Vientos IB Repower 26INR0507 · Wind · 185 MW · In study · Willacy
Chalybe (88337) 345 kV 3 requests · 602 MW3 in study
- Ouroboros Grid BESS 1 28INR0397 · Battery storage · 201 MW · In study
- Ouroboros Grid BESS 2 28INR0398 · Battery storage · 201 MW · In study
- Ouroboros Grid BESS 3 28INR0403 · Battery storage · 201 MW · In study
Rio Hondo (8318) 345 kV 3 requests · 483 MW · 2 in Cameron County, 1 in Willacy2 signed; security posted, 1 approved for synchronization
- Arroyo Storage 24INR0306 · Battery storage · 184 MW · Approved for synchronization
- Monte Alto 2 Wind 19INR0023 · Wind · 199 MW · Signed; security posted · Willacy
- Arroyo Solar 20INR0086 · Solar · 100 MW · Signed; security posted
La Palma (8317) 345 kV 2 requests · 284 MW1 signed; security posted, 1 approved for synchronization
- Arroyo Storage 24INR0306 · Battery storage · 184 MW · Approved for synchronization
- Arroyo Solar 20INR0086 · Solar · 100 MW · Signed; security posted
Cavazos (80229) 138 kV 2 requests · 334 MW1 signed; security posted, 1 in study
- Eval Storage 22INR0401 · Battery storage · 252 MW · Signed; security posted
- Harper Energy Storage 22INR0469 · Battery storage · 82 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Cameron County
- Cameron County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 15, Harlingen: 1804 W Jefferson Ave, Harlingen TX 78550-5247, 956-425-6010; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Cameron County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Cameron County.
Permits and reviews for Cameron County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Cameron County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Cameron County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.
How a project in Cameron County connects to the grid
Cameron County is on the ERCOT grid. The projects listed above are in ERCOT's Coastal load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Cameron County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Cameron County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 15
Brooks · Hidalgo · Jim Hogg · Kenedy · Starr · Willacy