Navarro County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
26 proposed energy projects from ERCOT's September 2026 report, plus who to call in Navarro County and in TCEQ Region 4 before signing a solar, wind, or battery storage lease.
Check land in Navarro CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Navarro County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Navarro County?
ERCOT's September 2026 interconnection report lists 26 proposed energy projects in Navarro County (16 solar, 3 wind and 7 battery storage), about 4,255 MW in all. 11 of the 26 have a signed interconnection agreement, and 2 have been approved for energization or synchronization.
What stands out in Navarro County
By capacity, solar leads in Navarro County with 2,733 MW across 16 projects, followed by battery storage (7 projects, 780 MW) and wind (3 projects, 741 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Tehuacana Creek Solar, a 505 MW solar project listed under Tehuacana Creek Solar LLC, with its agreement signed and security posted, and its target online date is May 2027. Of the 26, 15 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet, 8 have posted security or started construction and 2 are approved for energization or synchronization. Connection points are mostly at 138 kV (12 projects), 345 kV (11 projects) and 69 kV (1 project) (why the voltage matters). Glasgow Solar LLC, Hector Solar, LLC and Kennedy Bypass Solar LLC are each listed on 2 projects; 22 different companies appear in all. Target online dates for the projects not yet running span Mar 2027 to Apr 2030. All of them fall in ERCOT's North load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Board Creek Wind345kV 3386 Outlaw Switch | Limestone Wind Project, LLC | Wind | 299.2 | Oct 2026 | Approved for synchronization |
| Armadillo Solar3387 Revolution 138kV | Armadillo Solar Center, LLC | Solar | 150.5 | Dec 2026 | Approved for energization |
| Yellow Cat WindTap 345kV 1906 Venus - 68091 Navarro · shared with 2 other requests | Yellow Cat Wind LLC | Wind | 262.0 | Mar 2027 | Signed; security posted |
| TORMES SOLARtap 345kV 1906 Venus - 68091 Navarro · shared with 2 other requests | BDPU SOLAR TORMES LLC | Solar | 356.6 | Mar 2027 | Signed; security posted |
| Tehuacana Creek SolarTap 345kV 3381 Big Brown – 68091 Navarro circuit | Tehuacana Creek Solar LLC | Solar | 505.4 | May 2027 | Signed; security posted |
| Elm Flats Solar SLFTap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8 · shared with 1 other request | Orca Falls Solar, LLC | Solar | 125.8 | Nov 2027 | Signed; security posted |
| Elm Flats Storage SLFTap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8 · shared with 1 other request | Orca Falls Solar, LLC | Battery storage (paired with solar) | Self-limiting | Nov 2027 | Signed; security posted |
| Glasgow SolarTap 345kV #2466 Big Onion - #68091 Navarro · shared with 1 other request | Glasgow Solar LLC | Solar | 203.5 | Mar 2028 | Signed; security posted |
| Glasgow StorageTap 345kV #2466 Big Onion - #68091 Navarro · shared with 1 other request | Glasgow Solar LLC | Battery storage (paired with solar) | 101.0 | Mar 2028 | Signed; security posted |
| Bluebonnet Prairie WindTap 138kV 200 CHATFIELD - 3454 MONTFTSS__8 | Bluebonnet Prairie Wind, LLC | Wind | 180.0 | Jul 2028 | Signed; security posted |
| Cape Rich BESS3387 Revolution Switch 138kV | Cape Rich BESS | Battery storage (stand-alone) | 150.5 | Apr 2030 | Signed Feb 2025 |
| Goodalta Solartap 138kV 3127 Trinidad - 212 Winkler | GoodAlta Power Center LLC | Solar | 221.4 | Sep 2027 | In study |
| Eytcheson Ranches SolarTap 69kV 186 Navarro Mills – 107 Prairie Hill | Gransolar Texas Fourteen, LLC | Solar | 76.4 | Jan 2028 | In study |
| Whistle SolarTap 138kV 213 Haney – 3478 Navarro | Gransolar Texas Nineteen, LLC | Solar | 56.3 | May 2028 | In study |
| Santa Monica SolarTap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2 | Karol Solar IV | Solar | 105.8 | Sep 2028 | In study |
| Wildflower StorageDrane switch #3295 | Wildflower Storage LLC | Battery storage (stand-alone) | 359.1 | Sep 2028 | In study |
| Hector SolarHaney (213) - Hubbard_8 (3515) 138kV Line · shared with 1 other request | Hector Solar, LLC | Solar | 81.6 | Oct 2028 | In study |
| Hector StorageHaney (213) - Hubbard_8 (3515) 138kV Line · shared with 1 other request | Hector Solar, LLC | Battery storage (paired with solar) | 42.7 | Oct 2028 | In study |
| Kennedy SolarTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro · shared with 1 other request | Kennedy Bypass Solar LLC | Solar | 101.5 | Dec 2028 | In study |
| Kennedy StorageTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro · shared with 1 other request | Kennedy Bypass Solar LLC | Battery storage (paired with solar) | 25.3 | Dec 2028 | In study |
| Pisgah Ridge Solar 2Tap 345kV 68091 Navarro - 46020 Limestone · shared with 1 other request | Pisgah Ridge Solar 2, LLC | Solar | 101.9 | Mar 2029 | In study |
| Pisgah Ridge Storage 3Tap 345kV 68091 Navarro - 46020 Limestone · shared with 1 other request | Pisgah Ridge 3, LLC | Battery storage (paired with solar) | 101.4 | Mar 2029 | In study |
| Ponferrada SolarTap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8 | Karol Solar VI | Solar | 148.9 | Apr 2029 | In study |
| Wensowitch SolarTapping 138 kV line Telico (192) to Montfort Switch (3454) | Greenalia Solar Power Wensowitch LLC | Solar | 146.1 | Apr 2029 | In study |
| Main Horn Solar3387 Revolution 138 KV | Main Horn Solar LLC | Solar | 100.4 | Sep 2029 | In study |
| Oak Valley Solar68091 (Navarro) (345) | Oak Valley Solar LLC | Solar | 251.3 | Sep 2029 | In study |
Crowded connection points in Navarro County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Navarro (68091) 345 kV 22 requests · 5,873 MW · 11 in Navarro County, 11 in Ellis, Freestone, Hill13 in study, 6 signed; security posted, 2 approved for synchronization, 1 approved for energization
- Aquilla Lake 3 Wind 22INR0499 · Wind · 297 MW · Approved for synchronization · Hill
- Piedra Solar 25INR0168 · Solar · 282 MW · Approved for synchronization · Freestone
- Oystercatcher Solar 21INR0362 · Solar · 198 MW · Approved for energization · Ellis
- Tehuacana Creek Solar 24INR0188 · Solar · 505 MW · Signed; security posted
- TORMES SOLAR 22INR0437 · Solar · 357 MW · Signed; security posted
- Yellow Cat Wind 25INR0018 · Wind · 262 MW · Signed; security posted
- Glasgow Solar 24INR0206 · Solar · 204 MW · Signed; security posted
- Piedra BESS 25INR0169 · Battery storage · 104 MW · Signed; security posted · Freestone
- Glasgow Storage 24INR0207 · Battery storage · 101 MW · Signed; security posted
- Kickstart Energy Storage VI 29INR0218 · Battery storage · 1,026 MW · In study · Ellis
- BM Freestone Energy Center 29INR0298 · Gas combined cycle · 991 MW · In study · Freestone
- Two Step Solar 29INR0196 · Solar · 402 MW · In study · Ellis
- Silver Dollar Solar 27INR0186 · Solar · 302 MW · In study · Freestone
- Oak Valley Solar 28INR0335 · Solar · 251 MW · In study
- Silver Dollar Storage 27INR0187 · Battery storage · 153 MW · In study · Freestone
- Santa Monica Solar 26INR0228 · Solar · 106 MW · In study
- Pisgah Ridge Solar 2 24INR0086 · Solar · 102 MW · In study
- Kennedy Solar 24INR0256 · Solar · 102 MW · In study
- Pisgah Ridge Storage 3 24INR0087 · Battery storage · 101 MW · In study
- Kennedy Storage 24INR0391 · Battery storage · 25 MW · In study
- Kickstart Energy Storage III 27INR0471 · Battery storage · 1 MW · In study · Ellis
- Kickstart Energy Storage IV 27INR0472 · Battery storage · 1 MW · In study · Ellis
Revolution (3387) 138 kV 5 requests · 566 MW · 3 in Navarro County, 2 in Hill3 in study, 1 approved for energization, 1 signed
- Armadillo Solar 21INR0421 · Solar · 150 MW · Approved for energization
- Cape Rich BESS 26INR0180 · Battery storage · 151 MW · Signed Feb 2025
- HILLBORO BESS 26INR0402 · Battery storage · 131 MW · In study · Hill
- Main Horn Solar 28INR0467 · Solar · 100 MW · In study
- HILLBORO WIND 27INR0312 · Wind · 33 MW · In study · Hill
Venus (1906) 345 kV 8 requests · 2,408 MW · 2 in Navarro County, 6 in Ellis4 in study, 3 signed; security posted, 1 approved for energization
- Oystercatcher Solar 21INR0362 · Solar · 198 MW · Approved for energization · Ellis
- TORMES SOLAR 22INR0437 · Solar · 357 MW · Signed; security posted
- Yellow Cat Wind 25INR0018 · Wind · 262 MW · Signed; security posted
- Cumulus Grid BESS 24INR0178 · Battery storage · 211 MW · Signed; security posted · Ellis
- Kickstart Energy Storage V 29INR0217 · Battery storage · 999 MW · In study · Ellis
- Digital Ranch Gas 28INR0100 · Gas engines · 378 MW · In study · Ellis
- Kickstart Energy Storage III 27INR0471 · Battery storage · 1 MW · In study · Ellis
- Kickstart Energy Storage IV 27INR0472 · Battery storage · 1 MW · In study · Ellis
Limestone (46020) 345 kV 12 requests · 5,105 MW · 2 in Navarro County, 10 in Freestone, Leon, Madison8 in study, 2 signed, 1 approved for synchronization, 1 signed; security posted
- Piedra Solar 25INR0168 · Solar · 282 MW · Approved for synchronization · Freestone
- Piedra BESS 25INR0169 · Battery storage · 104 MW · Signed; security posted · Freestone
- Jewett Energy Center 1 Gas 29INR0150 · Gas combined cycle · 1,274 MW · Signed Jul 2026 · Freestone
- Great Rock BESS 25INR0230 · Battery storage · 301 MW · Signed Aug 2024 · Leon
- BM Great Rock Energy Center 30INR0091 · Gas combined cycle · 1,981 MW · In study · Leon
- Simsboro Storage 29INR0119 · Battery storage · 302 MW · In study · Freestone
- Masava Storage 25INR0176 · Battery storage · 257 MW · In study · Madison
- Savannah Oaks Solar 25INR0286 · Solar · 201 MW · In study · Madison
- Kahla Storage 25INR0513 · Battery storage · 201 MW · In study · Leon
- Pisgah Ridge Solar 2 24INR0086 · Solar · 102 MW · In study
- Pisgah Ridge Storage 3 24INR0087 · Battery storage · 101 MW · In study
- Three Canes Gas P2 27INR0652 · Gas engines · 0 MW · In study · Freestone
BIGBRNW_5 (3381) 345 kV 5 requests · 1,285 MW · 2 in Navarro County, 3 in Freestone3 in study, 2 signed; security posted
- Tehuacana Creek Solar 24INR0188 · Solar · 505 MW · Signed; security posted
- Utley Solar 24INR0117 · Solar · 222 MW · Signed; security posted · Freestone
- Amerada Solar 26INR0082 · Solar · 302 MW · In study · Freestone
- Amerada Storage 26INR0084 · Battery storage · 151 MW · In study · Freestone
- Santa Monica Solar 26INR0228 · Solar · 106 MW · In study
MONTFTSS__8 (3454) 138 kV 2 requests · 326 MW1 in study, 1 signed; security posted
- Bluebonnet Prairie Wind 25INR0247 · Wind · 180 MW · Signed; security posted
- Wensowitch Solar 24INR0205 · Solar · 146 MW · In study
Big Onion (2466) 345 kV 6 requests · 1,545 MW · 2 in Navarro County, 4 in Ellis3 signed; security posted, 3 in study
- Glasgow Solar 24INR0206 · Solar · 204 MW · Signed; security posted
- Sol Marina SLF Energy Center 26INR0241 · Solar · 171 MW · Signed; security posted · Ellis
- Glasgow Storage 24INR0207 · Battery storage · 101 MW · Signed; security posted
- Victory Ellis – Gas 29INR0264 · Gas turbine · 466 MW · In study · Ellis
- Victory Ellis–BESS 28INR0529 · Battery storage · 453 MW · In study · Ellis
- Bluebonnet Trail Solar 27INR0417 · Solar · 151 MW · In study · Ellis
Kopperl (68040) 345 kV 4 requests · 632 MW · 2 in Navarro County, 2 in Hill, Bosque3 in study, 1 approved for synchronization
Hubbard (3515) 138 kV 3 requests · 209 MW · 2 in Navarro County, 1 in Hill2 in study, 1 signed
- Payne Battlecreek 24INR0106 · Solar · 85 MW · Signed Feb 2024 · Hill
- Hector Solar 25INR0220 · Solar · 82 MW · In study
- Hector Storage 25INR0221 · Battery storage · 43 MW · In study
BRIAR_CRK_8 (3472) 138 kV 2 requests · 126 MW2 signed; security posted
- Elm Flats Solar SLF 26INR0130 · Solar · 126 MW · Signed; security posted
- Elm Flats Storage SLF 26INR0131 · Battery storage · 0 MW · Signed; security posted
POWELL1_8 (3467) 138 kV 2 requests · 126 MW2 signed; security posted
- Elm Flats Solar SLF 26INR0130 · Solar · 126 MW · Signed; security posted
- Elm Flats Storage SLF 26INR0131 · Battery storage · 0 MW · Signed; security posted
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Navarro County
- Navarro County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 4, Dallas/Fort Worth: 2309 Gravel Dr, Fort Worth TX 76118-6951, 817-588-5800; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Navarro County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Navarro County.
Permits and reviews for Navarro County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Navarro County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Navarro County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.
How a project in Navarro County connects to the grid
Navarro County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Navarro County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Navarro County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 4
Collin · Cooke · Dallas · Denton · Ellis · Erath · Fannin · Grayson · Hood · Hunt · Johnson · Kaufman · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise