Haskell County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
17 proposed energy projects from ERCOT's September 2026 report, plus who to call in Haskell County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.
Check land in Haskell CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Haskell County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Haskell County?
ERCOT's September 2026 interconnection report lists 17 proposed energy projects in Haskell County (10 solar, 2 wind and 5 battery storage), about 3,976 MW in all. 9 of the 17 have a signed interconnection agreement, and 5 have been approved for energization or synchronization.
What stands out in Haskell County
By capacity, solar leads in Haskell County with 2,301 MW across 10 projects, followed by battery storage (5 projects, 1,100 MW) and wind (2 projects, 575 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Grasshopper Solar, a 408 MW solar project listed under Grasshopper Solar LLC, still in study, and its target online date is Oct 2028. Of the 17, 8 are still in ERCOT's study process, 4 have posted security or started construction and 5 are approved for energization or synchronization. Connection points are mostly at 345 kV (13 projects) and 138 kV (4 projects) (why the voltage matters). Double Mountain Fork LLC and IP Quantum III, LLC are each listed on 2 projects; 15 different companies appear in all. Target online dates for the projects not yet running span Jul 2027 to Dec 2029. All of them fall in ERCOT's West load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Quantum Solar60089 Kilby Station 345kV | IP QUANTUM II, LLC | Solar | 321.7 | Sep 2026 | Approved for synchronization |
| Quantum Storage60089 Kilby Switching Station 345kV | IP Quantum II BESS, LLC | Battery storage | 321.8 | Sep 2026 | Approved for synchronization |
| Solace Solartap 345kV 1430 Graham - 1048 Tonkawas · shared with 1 other request | IP QUANTUM, LLC. | Solar | 321.6 | Sep 2026 | Approved for synchronization |
| Solace Storagetap 345kV 1430 Graham - 1048 Tonkawas · shared with 1 other request | IP Quantum BESS, LLC | Battery storage | 321.8 | Sep 2026 | Approved for synchronization |
| Millers Branch Solar IIITap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR) | Miller's Branch Solar LLC | Solar | 133.0 | Oct 2026 | Approved for synchronization |
| Rubicon Alpha Wind60507 pendulo7A 345kV | Throckmorton Wind, LLC | Wind | 222.6 | Jul 2027 | Signed; security posted |
| Briggs Solartap 345kV 60515 Clear Crossing - 60507 Pendulo · shared with 1 other request | IP Quantum III, LLC | Solar | 323.7 | Apr 2028 | Signed; security posted |
| Briggs Storagetap 345kV 60515 Clear Crossing - 60507 Pendulo · shared with 1 other request | IP Quantum III, LLC | Battery storage (paired with solar) | 336.0 | Apr 2028 | Signed; security posted |
| Inertia Solartap 345kV 60515 Clear Crossing - 6104 Smoky Hill | Inertia Solar Project, LLC | Solar | 202.4 | Mar 2029 | Signed; security posted |
| Journey SolarTap 138kV Paint Creek 6161 - Aspermont 6158 | Journey Solar, LLC | Solar | 124.7 | Sep 2027 | In study |
| Rolling Plains BESS6104 SMOKY HILL 345kV | Haskell County BESS LLC | Battery storage (stand-alone) | 120.0 | Jun 2028 | In study |
| Grasshopper SolarSmoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414;... | Grasshopper Solar LLC | Solar | 407.7 | Oct 2028 | In study |
| Blue Spring Solar#60515 Clear Crossing 345 kV | Flat Creek Solar, LLC | Solar | 301.0 | Oct 2028 | In study |
| DMF Sagerton Solar SLFTap 138kV 6158 Aspermont – 6161 Paint Creek · shared with 1 other request | Double Mountain Fork LLC | Solar | 125.5 | Dec 2028 | In study |
| DMF Sagerton Storage SLFTap 138kV 6158 Aspermont – 6161 Paint Creek · shared with 1 other request | Double Mountain Fork LLC | Battery storage (paired with solar) | Self-limiting | Dec 2028 | In study |
| Max 4 WindTap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmissi... | Lake Creek Wind, LLC | Wind | 352.6 | Aug 2029 | In study |
| Lueders SolarTap 138kV 6161 Paint Creek - 6200 Ft Phantom | Innovative Solar 75 | Solar | 40.0 | Dec 2029 | In study |
Crowded connection points in Haskell County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Paint Creek (6161) 138 kV 4 requests · 290 MW4 in study
- DMF Sagerton Solar SLF 26INR0146 · Solar · 126 MW · In study
- Journey Solar 27INR0217 · Solar · 125 MW · In study
- Lueders Solar 20INR0012 · Solar · 40 MW · In study
- DMF Sagerton Storage SLF 26INR0148 · Battery storage · 0 MW · In study
Clear Crossing (60515) 345 kV 11 requests · 5,068 MW · 4 in Haskell County, 7 in Jack, Jones, Stonewall7 in study, 4 signed; security posted
- Moccasin Solar 26INR0269 · Solar · 604 MW · Signed; security posted · Stonewall
- Briggs Storage 24INR0058 · Battery storage · 336 MW · Signed; security posted
- Briggs Solar 23INR0059 · Solar · 324 MW · Signed; security posted
- Inertia Solar 22INR0374 · Solar · 202 MW · Signed; security posted
- Dovetail Solar 1 24INR0094 · Solar · 666 MW · In study · Jack
- Dovetail Solar 2 24INR0095 · Solar · 666 MW · In study · Jack
- Hackberry Draw Solar 30INR0146 · Solar · 653 MW · In study · Jones
- Moccasin Storage 27INR0452 · Battery storage · 603 MW · In study · Jones
- Dovetail Storage 24INR0098 · Battery storage · 509 MW · In study · Jack
- Blue Spring Solar 28INR0433 · Solar · 301 MW · In study
- Chimney Creek Solar 28INR0151 · Solar · 204 MW · In study · Shackelford
Smoky Hill (6104) 345 kV 3 requests · 730 MW2 in study, 1 signed; security posted
- Inertia Solar 22INR0374 · Solar · 202 MW · Signed; security posted
- Grasshopper Solar 24INR0125 · Solar · 408 MW · In study
- Rolling Plains BESS 26INR0501 · Battery storage · 120 MW · In study
Pendulo (60507) 345 kV 3 requests · 882 MW3 signed; security posted
- Briggs Storage 24INR0058 · Battery storage · 336 MW · Signed; security posted
- Briggs Solar 23INR0059 · Solar · 324 MW · Signed; security posted
- Rubicon Alpha Wind 24INR0291 · Wind · 223 MW · Signed; security posted
Aspermont (6158) 138 kV 4 requests · 385 MW · 3 in Haskell County, 1 in Stonewall4 in study
- Stonewall BESS 28INR0253 · Battery storage · 135 MW · In study · Stonewall
- DMF Sagerton Solar SLF 26INR0146 · Solar · 126 MW · In study
- Journey Solar 27INR0217 · Solar · 125 MW · In study
- DMF Sagerton Storage SLF 26INR0148 · Battery storage · 0 MW · In study
Kilby (60089) 345 kV 2 requests · 643 MW2 approved for synchronization
- Quantum Storage 26INR0310 · Battery storage · 322 MW · Approved for synchronization
- Quantum Solar 21INR0207 · Solar · 322 MW · Approved for synchronization
Graham (1430) 345 kV 12 requests · 4,716 MW · 2 in Haskell County, 10 in Young, Throckmorton, Fisher10 in study, 2 approved for synchronization
- Solace Storage 26INR0309 · Battery storage · 322 MW · Approved for synchronization
- Solace Solar 23INR0031 · Solar · 322 MW · Approved for synchronization
- Indigo Solar 3 28INR0067 · Solar · 800 MW · In study · Fisher
- Jenna Eco-Electric Solar 25INR0632 · Solar · 576 MW · In study · Fisher
- Miller Bend Energy BESS 29INR0204 · Battery storage · 548 MW · In study · Young
- Miller Bend Energy Solar 29INR0203 · Solar · 532 MW · In study · Young
- Pinnington Storage 24INR0011 · Battery storage · 503 MW · In study · Jack
- Sweetheart BESS 29INR0172 · Battery storage · 310 MW · In study · Young
- Sweetheart Solar 29INR0171 · Solar · 301 MW · In study · Young
- Sideoats Solar 1 30INR0123 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 2 30INR0124 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 3 30INR0125 · Solar · 168 MW · In study · Throckmorton
Tonkawa (1048) 345 kV 8 requests · 5,745 MW · 2 in Haskell County, 6 in Fisher, Nolan5 in study, 3 approved for synchronization
- Solace Storage 26INR0309 · Battery storage · 322 MW · Approved for synchronization
- Solace Solar 23INR0031 · Solar · 322 MW · Approved for synchronization
- Champion Wind Repower 24INR0627 · Wind · 0 MW · Approved for synchronization · Nolan
- Brazos Energy Security 28INR0456 · Gas combined cycle · 3,000 MW · In study · Fisher
- Indigo Solar 3 28INR0067 · Solar · 800 MW · In study · Fisher
- Jenna Eco-Electric Solar 25INR0632 · Solar · 576 MW · In study · Fisher
- Alkali Creek Wind 28INR0415 · Wind · 474 MW · In study · Fisher
- Alkali Creek Wind 2 28INR0478 · Wind · 250 MW · In study · Fisher
Gauss (60703) 345 kV 3 requests · 838 MW · 2 in Haskell County, 1 in Knox1 approved for synchronization, 1 signed; security posted, 1 in study
- Millers Branch Solar III 26INR0521 · Solar · 133 MW · Approved for synchronization
- West Munday Wind 26INR0531 · Wind · 352 MW · Signed; security posted · Knox
- Max 4 Wind 28INR0408 · Wind · 353 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Haskell County
- Haskell County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Haskell County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Haskell County.
Permits and reviews for Haskell County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Haskell County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Recent local action: Haskell County's tax abatement page lists tax abatement agreements dated November 12, 2024 for Quantum I BESS and Quantum II BESS, each with an Order Approving Abatement, and a Throckmorton Wind, LLC agreement with the same date. The page also lists Tax Abatement Guidelines & Criteria adopted May 27, 2025. (Haskell County tax abatement page; checked October 17, 2026).
How a project in Haskell County connects to the grid
Haskell County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Haskell County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Haskell County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 3
Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young