Fisher County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
13 proposed energy projects from ERCOT's September 2026 report, plus who to call in Fisher County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.
Check land in Fisher CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Fisher County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Fisher County?
ERCOT's September 2026 interconnection report lists 13 proposed energy projects in Fisher County (4 solar, 4 wind, 4 battery storage and 1 gas), about 6,384 MW in all. 6 of the 13 have a signed interconnection agreement, and 1 has been approved for energization or synchronization. 2 are new since August.
What stands out in Fisher County
By capacity, gas leads in Fisher County with 3,000 MW across 1 project, followed by solar (4 projects, 1,706 MW) and wind (4 projects, 1,438 MW). The largest single project is Brazos Energy Security, a 3,000 MW gas combined cycle project listed under Golden Spread Electric, still in study, and its target online date is Sep 2030. Of the 13, 7 are still in ERCOT's study process, 5 have posted security or started construction and 1 is approved for energization or synchronization. Every listed connection point is on the 345 kV system (why the voltage matters). The single most-used connection point is tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2, shared by 5 projects. Innovative Solar 245, LLC is listed on the most projects here (5 of 13); 8 different companies appear in all. Target online dates for the projects not yet running span Jul 2027 to Sep 2030. All of them fall in ERCOT's West load zone. 2 are new since August.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Whitehorse Wind68001 Clayton 345kV | MESQUITE STAR SPECIAL LLC | Wind | 418.9 | Dec 2026 | Approved for synchronization |
| Indigo Solartap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2 · shared with 4 other requests | Innovative Solar 245, LLC | Solar | 150.0 | Sep 2027 | Signed; security posted |
| Indigo Storagetap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2 · shared with 4 other requests | Innovative Solar 245, LLC | Battery storage (paired with solar) | 60.0 | Sep 2027 | Signed; security posted |
| Indigo Storage 2tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2 · shared with 4 other requests | Innovative Solar 245, LLC | Battery storage (paired with solar) | 60.0 | Sep 2027 | Signed; security posted |
| Indigo Storage 3tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2 · shared with 4 other requests | Innovative Solar 245, LLC | Battery storage (paired with solar) | 60.0 | Sep 2027 | Signed; security posted |
| Indigo Storage 4tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2 · shared with 4 other requests | Innovative Solar 245, LLC | Battery storage (paired with solar) | 60.0 | Sep 2027 | Signed; security posted |
| Indigo solar 2Tap 345KV 68001 Clayton 345KV -68000 WShack Ckt 2 | Indigo Solar 2 | Solar | 180.0 | Jul 2027 | In study |
| Indigo Solar 3Tap Line Segment Tankawa (Bus #1048) to Graham (Bus #1430) | Indigo solar 3 | Solar | 800.0 | Nov 2028 | In study |
| Alkali Creek WindTap 345 kV BUS #1048 Tonkawa - | Alkali Creek Wind, LLC | Wind | 474.4 | Dec 2028 | In study |
| Alkali Creek Wind 2Tap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road | Alkali Creek Wind, LLC | Wind | 250.3 | Dec 2028 | In study |
| Jenna Eco-Electric SolarTap 345 kV 1048 Tonkawa Switch - 1430 Graham SES | Clean Energy Holdings, LLC | Solar | 576.3 | Apr 2029 | In study |
| Rugged Prairie Wind NewTap 345kV BUS #11305 Dermott- BUS #60706 Kirchhef | Rugged Prairie Wind, LLC | Wind | 294.1 | Dec 2029 | In study |
| Brazos Energy Security NewTap 345 kV (Bus #1048) Tonkawa Switch – (Bus #11050) Dusty Road | Golden Spread Electric | Gas combined cycle | 3,000.0 | Sep 2030 | In study |
Crowded connection points in Fisher County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Claytonville (68001) 345 kV 11 requests · 1,840 MW · 7 in Fisher County, 4 in Jones5 signed; security posted, 3 approved for synchronization, 3 in study
- Whitehorse Wind 19INR0080 · Wind · 419 MW · Approved for synchronization
- Crowded Star Solar 20INR0241 · Solar · 219 MW · Approved for synchronization · Jones
- Crowded Star Solar II 22INR0274 · Solar · 190 MW · Approved for synchronization · Jones
- Indigo Solar 21INR0031 · Solar · 150 MW · Signed; security posted
- Indigo Storage 24INR0496 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 2 25INR0528 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 3 25INR0529 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 4 25INR0530 · Battery storage · 60 MW · Signed; security posted
- Lone Tiger Solar 29INR0393 · Solar · 243 MW · In study · Jones
- Anson Solar Center, Phase III 21INR0247 · Solar · 200 MW · In study · Jones
- Indigo solar 2 25INR0547 · Solar · 180 MW · In study
Phantom Hill (68004) 345 kV 12 requests · 1,998 MW · 5 in Fisher County, 7 in Jones8 signed; security posted, 3 approved for synchronization, 1 in study
- Crowded Star Solar 20INR0241 · Solar · 219 MW · Approved for synchronization · Jones
- Anson Solar 2 20INR0242 · Solar · 201 MW · Approved for synchronization · Jones
- Crowded Star Solar II 22INR0274 · Solar · 190 MW · Approved for synchronization · Jones
- Funston Solar 29INR0015 · Solar · 351 MW · Signed; security posted · Jones
- Tiger Solar 23INR0244 · Solar · 251 MW · Signed; security posted · Jones
- Anson BAT 22INR0457 · Battery storage · 154 MW · Signed; security posted · Jones
- Indigo Solar 21INR0031 · Solar · 150 MW · Signed; security posted
- Indigo Storage 24INR0496 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 2 25INR0528 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 3 25INR0529 · Battery storage · 60 MW · Signed; security posted
- Indigo Storage 4 25INR0530 · Battery storage · 60 MW · Signed; security posted
- Lone Tiger Solar 29INR0393 · Solar · 243 MW · In study · Jones
Tonkawa (1048) 345 kV 8 requests · 5,745 MW · 5 in Fisher County, 3 in Haskell, Nolan5 in study, 3 approved for synchronization
- Solace Storage 26INR0309 · Battery storage · 322 MW · Approved for synchronization · Haskell
- Solace Solar 23INR0031 · Solar · 322 MW · Approved for synchronization · Haskell
- Champion Wind Repower 24INR0627 · Wind · 0 MW · Approved for synchronization · Nolan
- Brazos Energy Security 28INR0456 · Gas combined cycle · 3,000 MW · In study
- Indigo Solar 3 28INR0067 · Solar · 800 MW · In study
- Jenna Eco-Electric Solar 25INR0632 · Solar · 576 MW · In study
- Alkali Creek Wind 28INR0415 · Wind · 474 MW · In study
- Alkali Creek Wind 2 28INR0478 · Wind · 250 MW · In study
Graham (1430) 345 kV 12 requests · 4,716 MW · 2 in Fisher County, 10 in Young, Throckmorton, Haskell10 in study, 2 approved for synchronization
- Solace Storage 26INR0309 · Battery storage · 322 MW · Approved for synchronization · Haskell
- Solace Solar 23INR0031 · Solar · 322 MW · Approved for synchronization · Haskell
- Indigo Solar 3 28INR0067 · Solar · 800 MW · In study
- Jenna Eco-Electric Solar 25INR0632 · Solar · 576 MW · In study
- Miller Bend Energy BESS 29INR0204 · Battery storage · 548 MW · In study · Young
- Miller Bend Energy Solar 29INR0203 · Solar · 532 MW · In study · Young
- Pinnington Storage 24INR0011 · Battery storage · 503 MW · In study · Jack
- Sweetheart BESS 29INR0172 · Battery storage · 310 MW · In study · Young
- Sweetheart Solar 29INR0171 · Solar · 301 MW · In study · Young
- Sideoats Solar 1 30INR0123 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 2 30INR0124 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 3 30INR0125 · Solar · 168 MW · In study · Throckmorton
BUS2 (11050) 345 kV 7 requests · 4,833 MW · 2 in Fisher County, 5 in Throckmorton, Young7 in study
- Brazos Energy Security 28INR0456 · Gas combined cycle · 3,000 MW · In study
- Miller Bend Energy BESS 29INR0204 · Battery storage · 548 MW · In study · Young
- Miller Bend Energy Solar 29INR0203 · Solar · 532 MW · In study · Young
- Alkali Creek Wind 2 28INR0478 · Wind · 250 MW · In study
- Sideoats Solar 1 30INR0123 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 2 30INR0124 · Solar · 168 MW · In study · Throckmorton
- Sideoats Solar 3 30INR0125 · Solar · 168 MW · In study · Throckmorton
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Fisher County
- Fisher County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Fisher County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Fisher County.
Permits and reviews for Fisher County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Fisher County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Fisher County connects to the grid
Fisher County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Fisher County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Fisher County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 3
Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young