Home › Texas › Eastland County

Eastland County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects10
Total capacity1,357MW
Signed agreements2of 10
New since August0requests

10 proposed energy projects from ERCOT's September 2026 report, plus who to call in Eastland County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.

Check land in Eastland CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Eastland County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Eastland County?

ERCOT's September 2026 interconnection report lists 10 proposed energy projects in Eastland County (4 solar, 1 wind and 5 battery storage), about 1,357 MW in all. 2 of the 10 have a signed interconnection agreement, and 2 have been approved for energization or synchronization. The table also lists 2 changes to existing plants (repowers or capacity changes), not counted above.

What stands out in Eastland County

By capacity, solar leads in Eastland County with 891 MW across 4 projects, followed by battery storage (5 projects, 450 MW) and wind (1 project, 16 MW); 2 self-limiting projects (reported at 0 MW because the resource limits its own output) are listed without a capacity. The largest single project is Damia Solar, a 306 MW solar project listed under Damia Solar, LLC, still in study, and its target online date is Jul 2028. Of the 10, 8 are still in ERCOT's study process and 2 are approved for energization or synchronization. Connection points are mostly at 138 kV (8 projects), 345 kV (1 project) and 354 kV (1 project) (why the voltage matters). Basketflower Solar, LLC, Damia Solar, LLC and Rising Star Energy Center, LLC are each listed on 2 projects; 6 different companies appear in all. Target online dates for the projects not yet running span Dec 2027 to Nov 2029. All of them fall in ERCOT's North load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Anchor Wind III345 kV Aspire Station (68011)RANCHLAND WIND PROJECT LLCWind16.0Dec 2025Approved for synchronization
Roadrunner Crossing BESS SLF68051 Reata 354kVRoadrunner Crossing BESSBattery storage (paired with wind)Self-limitingAug 2026Approved for synchronization
Silver Star repower1642 Flat Creek 138kVSilver Star I Power Partners, LLCWind−7.2 capacity change to an existing plantDec 2026Approved for synchronization
Roadrunner Crossing Wind (Uprate)68051 Reata 345kV · shared with 1 other requestRoadrunner Wind, LLCWind7.3Jun 2027Signed; security posted
Basketflower SolarTap 138kV Risingstar (285) - Nimrod (289) · shared with 1 other requestBasketflower Solar, LLCSolar183.0Dec 2027In study
Basketflower StorageTap 138kV Risingstar (285) - Nimrod (289) · shared with 1 other requestBasketflower Solar, LLCBattery storage (paired with solar)92.0Dec 2027In study
Damia SolarTap 138kV 6317 Cisco - 3545 MTNBRANCH_8 · shared with 1 other requestDamia Solar, LLCSolar306.0Jul 2028In study
Damia StorageTap 138kV 6317 Cisco - 3545 MTNBRANCH_8 · shared with 1 other requestDamia Solar, LLCBattery storage (paired with solar)153.0Jul 2028In study
Star Grass Renewable Energy Solar SLFTap 138kV 6310 Putnam - 3378 Carbon_8 · shared with 1 other requestStar Grass Renewable Energy LLCSolar150.0Sep 2029In study
Star Grass Renewable Energy Storage SLFTap 138kV 6310 Putnam - 3378 Carbon_8 · shared with 1 other requestStar Grass Renewable Energy LLCBattery storage (paired with solar)Self-limitingSep 2029In study
Richardson McClung Ranch BESS33285 Rising Star 138 kV · shared with 1 other requestRising Star Energy Center, LLCBattery storage (paired with solar)205.5Nov 2029In study
Richardson McClung Ranch Solar33285 Rising Star 138 kV · shared with 1 other requestRising Star Energy Center, LLCSolar251.9Nov 2029In study

Crowded connection points in Eastland County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Bus 285 (285) 138 kV 2 requests · 275 MW2 in study
  • Basketflower Solar 26INR0468 · Solar · 183 MW · In study
  • Basketflower Storage 26INR0467 · Battery storage · 92 MW · In study
Bus 289 (289) 138 kV 2 requests · 275 MW2 in study
  • Basketflower Solar 26INR0468 · Solar · 183 MW · In study
  • Basketflower Storage 26INR0467 · Battery storage · 92 MW · In study
Cisco (6317) 138 kV 2 requests · 459 MW2 in study
  • Damia Solar 26INR0603 · Solar · 306 MW · In study
  • Damia Storage 26INR0602 · Battery storage · 153 MW · In study
MTNBRANCH_8 (3545) 138 kV 2 requests · 459 MW2 in study
  • Damia Solar 26INR0603 · Solar · 306 MW · In study
  • Damia Storage 26INR0602 · Battery storage · 153 MW · In study
Putnam (6310) 138 kV 2 requests · 150 MW2 in study
  • Star Grass Renewable Energy Solar SLF 28INR0195 · Solar · 150 MW · In study
  • Star Grass Renewable Energy Storage SLF 28INR0197 · Battery storage · 0 MW · In study
CARBON_8 (3378) 138 kV 3 requests · 300 MW · 2 in Eastland County, 1 in Comal3 in study
  • Short River BESS 30INR0112 · Battery storage · 150 MW · In study · Comal
  • Star Grass Renewable Energy Solar SLF 28INR0195 · Solar · 150 MW · In study
  • Star Grass Renewable Energy Storage SLF 28INR0197 · Battery storage · 0 MW · In study
Rising Star (33285) 138 kV 2 requests · 457 MW2 in study
  • Richardson McClung Ranch Solar 29INR0274 · Solar · 252 MW · In study
  • Richardson McClung Ranch BESS 29INR0275 · Battery storage · 205 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Eastland County

  • Eastland County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Eastland County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Eastland County.

Permits and reviews for Eastland County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Eastland County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Eastland County connects to the grid

Eastland County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Eastland County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Eastland County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 3

Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Fisher · Foard · Hardeman · Haskell · Jack · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.