Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Cooke County

Cooke County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects5
Total capacity948MW
Signed agreements2of 5
New since August0requests

5 proposed energy projects from ERCOT's September 2026 report, plus who to call in Cooke County and in TCEQ Region 4 before signing a solar, wind, or battery storage lease.

Check land in Cooke CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Cooke County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Cooke County?

ERCOT's September 2026 interconnection report lists 5 proposed energy projects in Cooke County (1 wind and 4 battery storage), about 948 MW in all. 2 of the 5 have a signed interconnection agreement, and 1 has been approved for energization or synchronization.

What stands out in Cooke County

By capacity, battery storage leads in Cooke County with 768 MW across 4 projects, followed by wind (1 project, 180 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Two Forks BESS, a 310 MW stand-alone battery storage project listed under Two Forks LLC, with its agreement signed and security posted, and its target online date is Aug 2028. Of the 5, 3 are still in ERCOT's study process, 1 has posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 138 kV (3 projects) and 345 kV (2 projects) (why the voltage matters). Each of the 5 projects is listed under a different company. Target online dates for the projects not yet running span Feb 2028 to Jul 2029. All of them fall in ERCOT's North load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
WILDWINDtap 345kV 1730 KrumW - 2373 AnnaWildcat CreekWind180.1Apr 2026Approved for synchronization
Two Forks BESS684 SPRING 138kVTwo Forks LLCBattery storage (stand-alone)309.8Aug 2028Signed; security posted
18-ALPHA BESSTo the 138 kV Valley View Substation, ( Bus No.691)SCOUT ENERGY MANAGEMENT, LLCBattery storage (stand-alone)307.4Feb 2028In study
Mountain Springs BESS704 Mountain Springs 138 kVMountain Springs BESSBattery storage (stand-alone)150.5Apr 2029In study
Trojan BESS SLF11735 Cedar Elm Switch 345kVTrojan BESSBattery storage (paired with solar)Self-limitingJul 2029In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Cooke County

  • Cooke County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 4, Dallas/Fort Worth: 2309 Gravel Dr, Fort Worth TX 76118-6951, 817-588-5800; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Cooke County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Cooke County.

Permits and reviews for Cooke County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Cooke County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Cooke County connects to the grid

Cooke County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Cooke County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Cooke County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 4

Collin · Dallas · Denton · Ellis · Erath · Fannin · Grayson · Hood · Hunt · Johnson · Kaufman · Navarro · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.