Jack County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
17 proposed energy projects from ERCOT's September 2026 report, plus who to call in Jack County and in TCEQ Region 3 before signing a solar, wind, or battery storage lease.
Check land in Jack CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Jack County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Jack County?
ERCOT's September 2026 interconnection report lists 17 proposed energy projects in Jack County (4 solar, 2 wind, 9 battery storage and 2 gas), about 7,978 MW in all. 4 of the 17 have a signed interconnection agreement.
What stands out in Jack County
By capacity, battery storage leads in Jack County with 2,638 MW across 9 projects, followed by gas (2 projects, 2,546 MW) and solar (4 projects, 2,261 MW). The largest single project is Thunder Bird 2 Gas, a 1,273 MW gas combined cycle project listed under BKV Power Ventures Jack, LLC 3, still in study, and its target online date is Jun 2031. Of the 17, 13 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet and 3 have posted security or started construction. Connection points are mostly at 345 kV (14 projects) and 138 kV (1 project) (why the voltage matters). BKV Power Ventures Jack, LLC 3 and PK Solar, LLC are each listed on 2 projects; 15 different companies appear in all. Target online dates for the projects not yet running span Jul 2026 to Jun 2031. All of them fall in ERCOT's North load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Possum Kingdom SolarTap 345kV 1421 Willow Creek Switch – 11523 Thomas Price | PK Solar, LLC | Solar | 262.2 | Jun 2028 | Under construction |
| Possum Kingdom BESSTap 345kV 1421 Willow Creek – 11523 Thomas Price | PK Solar, LLC | Battery storage (paired with solar) | 200.9 | Oct 2028 | Under construction |
| O'Bannion Energy Storage1506 Long Hollow Switch 345 kV | O'Bannion Energy Storage, LLC | Battery storage (stand-alone) | 306.4 | Apr 2028 | Signed; security posted |
| Fortuna WindTap 345kV 1429 Jacksboro - 1730 WKrum | RWE Renewables Development, LLC | Wind | 295.3 | Jul 2026 date passed; status per ERCOT | Signed Aug 2024 |
| Liberty Senate Energy Storage 11445 Burwick 345kV | Senate Solar LLC | Battery storage (stand-alone) | 207.4 | Oct 2027 | In study |
| Beitel Energy Storage579 Jack County 138kV | Brazos Energy Storage, LLC | Battery storage (stand-alone) | 200.6 | Dec 2027 | In study |
| Lightning Ridge Energy StorageTap #1429 Jacksboro Substation 345kV | Lightning Ridge Storage LLC | Battery storage (stand-alone) | 204.7 | Mar 2028 | In study |
| Dovetail Solar 1Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2 | Hecate Energy Dovetail Solar 1 LLC | Solar | 666.1 | Apr 2028 | In study |
| Dovetail StorageTap 345 KV 1421 Willow Creek-60515 Clear Crossing CKT#2 | Hecate Energy Dovetail Storage LLC | Battery storage (paired with solar) | 508.7 | Apr 2028 | In study |
| JackGard BESS1429 Jacksboro 345kV | Jackgard BESS | Battery storage (stand-alone) | 200.6 | Apr 2028 | In study |
| Campsey Windtap 345kV 1458 Cobb - 1429 Jacksboro | RWE Clean Energy Development, LLC | Wind | 238.3 | Jun 2028 | In study |
| Wooderson Energy StorageTap 345 kV 11418 TECUMSEH- 1421 Willow Creek | Wooderson Energy Storage, LLC | Battery storage (stand-alone) | 306.4 | Sep 2028 | In study |
| Dovetail Solar 2Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing | Hecate Energy Dovetail Solar 2 LLC | Solar | 666.1 | Apr 2029 | In study |
| Dovetail Solar 3Tap 345kV 1421 Willow Creek – 11523 THOMPRIC | Hecate Energy Dovetail Solar Holdings LLC | Solar | 666.1 | Apr 2029 | In study |
| Pinnington Storagetap both 345kV 1430 Graham - 1436 Parker 345kV lines | Hecate Energy Longhorn Storage LLC | Battery storage (stand-alone) | 502.7 | Apr 2029 | In study |
| Thunder Bird 1 GasTap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (14... · shared with 1 other request | BKV Power Ventures Jack, LLC 3 | Gas combined cycle | 1,272.8 | Jun 2030 | In study |
| Thunder Bird 2 GasTap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (14... · shared with 1 other request | BKV Power Ventures Jack, LLC 3 | Gas combined cycle | 1,272.8 | Jun 2031 | In study |
Crowded connection points in Jack County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Willow Creek (1421) 345 kV 10 requests · 5,843 MW · 9 in Jack County, 1 in Wise7 in study, 2 under construction, 1 signed; security posted
- Possum Kingdom Solar 24INR0118 · Solar · 262 MW · Under construction
- Possum Kingdom BESS 24INR0375 · Battery storage · 201 MW · Under construction
- Wise County Power Repower (CT1, CT2) 20INR0286 · Gas combined cycle · 21 MW · Signed; security posted · Wise
- Thunder Bird 2 Gas 28INR0509 · Gas combined cycle · 1,273 MW · In study
- Thunder Bird 1 Gas 30INR0110 · Gas combined cycle · 1,273 MW · In study
- Dovetail Solar 1 24INR0094 · Solar · 666 MW · In study
- Dovetail Solar 2 24INR0095 · Solar · 666 MW · In study
- Dovetail Solar 3 24INR0097 · Solar · 666 MW · In study
- Dovetail Storage 24INR0098 · Battery storage · 509 MW · In study
- Wooderson Energy Storage 25INR0660 · Battery storage · 306 MW · In study
Jacksboro (1429) 345 kV 9 requests · 4,324 MW · 6 in Jack County, 3 in Wise8 in study, 1 signed
- Fortuna Wind 22INR0301 · Wind · 295 MW · Signed Aug 2024
- Thunder Bird 2 Gas 28INR0509 · Gas combined cycle · 1,273 MW · In study
- Thunder Bird 1 Gas 30INR0110 · Gas combined cycle · 1,273 MW · In study
- Spur Energy Storage 28INR0278 · Battery storage · 613 MW · In study · Wise
- Campsey Wind 23INR0174 · Wind · 238 MW · In study
- Lightning Ridge Energy Storage 26INR0460 · Battery storage · 205 MW · In study
- JackGard BESS 26INR0215 · Battery storage · 201 MW · In study
- Sandford Solar 26INR0318 · Solar · 126 MW · In study · Wise
- Sandford Storage 26INR0319 · Battery storage · 101 MW · In study · Wise
Clear Crossing (60515) 345 kV 11 requests · 5,068 MW · 3 in Jack County, 8 in Haskell, Jones, Stonewall7 in study, 4 signed; security posted
- Moccasin Solar 26INR0269 · Solar · 604 MW · Signed; security posted · Stonewall
- Briggs Storage 24INR0058 · Battery storage · 336 MW · Signed; security posted · Haskell
- Briggs Solar 23INR0059 · Solar · 324 MW · Signed; security posted · Haskell
- Inertia Solar 22INR0374 · Solar · 202 MW · Signed; security posted · Haskell
- Dovetail Solar 1 24INR0094 · Solar · 666 MW · In study
- Dovetail Solar 2 24INR0095 · Solar · 666 MW · In study
- Hackberry Draw Solar 30INR0146 · Solar · 653 MW · In study · Jones
- Moccasin Storage 27INR0452 · Battery storage · 603 MW · In study · Jones
- Dovetail Storage 24INR0098 · Battery storage · 509 MW · In study
- Blue Spring Solar 28INR0433 · Solar · 301 MW · In study · Haskell
- Chimney Creek Solar 28INR0151 · Solar · 204 MW · In study · Shackelford
Thomas Price (11523) 345 kV 3 requests · 1,129 MW2 under construction, 1 in study
- Possum Kingdom Solar 24INR0118 · Solar · 262 MW · Under construction
- Possum Kingdom BESS 24INR0375 · Battery storage · 201 MW · Under construction
- Dovetail Solar 3 24INR0097 · Solar · 666 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Jack County
- Jack County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 3, Abilene: 1977 Industrial Blvd, Abilene TX 79602-7833, 325-698-9674; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Jack County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Jack County.
Permits and reviews for Jack County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Jack County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Recent local action: The Jacksboro Herald-Gazette reported that PK Solar applied to Jack County in February 2025 for a 50% property tax abatement, and that in June 2025 the commissioners court approved an order establishing a reinvestment zone of about 1,368 acres in southern Jack County. The paper also reported proposed abatement hearings for PK Solar and for Jack County Energy Storage, a proposed 201-megawatt lithium-ion battery facility. (Jacksboro Herald-Gazette; checked October 17, 2026).
How a project in Jack County connects to the grid
Jack County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Jack County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Jack County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 3
Archer · Baylor · Brown · Callahan · Clay · Coleman · Comanche · Cottle · Eastland · Fisher · Foard · Hardeman · Haskell · Jones · Kent · Knox · Mitchell · Montague · Nolan · Runnels · Scurry · Shackelford · Stephens · Stonewall · Taylor · Throckmorton · Wichita · Wilbarger · Young