Nueces County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
13 proposed energy projects from ERCOT's September 2026 report, plus who to call in Nueces County and in TCEQ Region 14 before signing a solar, wind, or battery storage lease.
Check land in Nueces CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Nueces County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Nueces County?
ERCOT's September 2026 interconnection report lists 13 proposed energy projects in Nueces County (2 solar, 8 battery storage and 3 gas), about 2,277 MW in all. 7 of the 13 have a signed interconnection agreement, and 1 has been approved for energization or synchronization. 1 is new since August.
What stands out in Nueces County
By capacity, battery storage leads in Nueces County with 1,207 MW across 8 projects, followed by solar (2 projects, 668 MW) and gas (2 projects, 351 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Sunscape Renewable Energy Solar SLF, a 523 MW solar project listed under Sunscape Renewable Energy LLC, with its agreement signed and security posted, and its target online date is Oct 2028. Of the 13, 6 are still in ERCOT's study process, 1 has a signed interconnection agreement but no security posted yet, 5 have posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 138 kV (8 projects), 345 kV (4 projects) and 69 kV (1 project) (why the voltage matters). Corpus Battery Storage, LLC, HEP Power Generation, LLC and Noria Hondo Solar LLC are each listed on 2 projects; 9 different companies appear in all. Target online dates for the projects not yet running span Mar 2027 to Jul 2029. All of them fall in ERCOT's Coastal load zone. 1 is new since August.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Lynx Energy Storage138KV Tap 8921 Terra Verde - 8518 Kingsville | Corpus Battery Storage, LLC | Battery storage (stand-alone) | 125.3 | May 2026 | Approved for synchronization |
| Noria Solar DCC85000 Nelson Sharpe 345kV · shared with 1 other request | Noria Hondo Solar LLC | Solar | 145.0 | Apr 2028 | Signed; security posted |
| Noria Storage85000 Nelson Sharpe 345kV · shared with 1 other request | Noria Hondo Solar LLC | Battery storage (paired with solar) | 75.0 | Apr 2028 | Signed; security posted |
| Blanquilla BESSTap 138kV 8452 LON_HILL4A - 8441 NUECES_B4A | Blanquilla BESS LLC | Battery storage (stand-alone) | 200.8 | May 2028 | Signed; security posted |
| Sunscape Renewable Energy Solar SLFBus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line | Sunscape Renewable Energy LLC | Solar | 522.8 | Oct 2028 | Signed; security posted |
| Sunscape Renewable Energy Storage SLFTap 345kV 8455 Lon C Hill -- 80078 Reforzar | Sunscape Renewable Energy LLC | Battery storage (paired with solar) | Self-limiting | Oct 2028 | Signed; security posted |
| NavBoot BESS8858 MCKENZIE4A 138kV | Navboot BESS LLC | Battery storage (stand-alone) | 303.7 | Nov 2027 | Signed Oct 2025 |
| GOTHAM BESS5640 DRISCOLLSUB9 69kV | AEU BATTERY PROJECT IV LLC | Battery storage (stand-alone) | 151.2 | Mar 2027 | In study |
| Lynx Energy Storage_Full NewPRIMAVERA 138kV Substation | Corpus Battery Storage, LLC | MWH | 50.0 | Dec 2027 | In study |
| Barbara BESSLINE TAP OF WESTSIDE (8485) AND WEIL TRACT (8482) 138 KV TRANSMISSI... | Barbara BESS LLC | Battery storage (stand-alone) | 200.5 | May 2028 | In study |
| Jalisco Cogen8475 JAVELINA4A 138 KV | HEP Power Generation, LLC | Gas combined cycle | 167.8 | May 2029 | In study |
| Jalisco Peaker8475 JAVELINA4A 138kV | HEP Power Generation, LLC | Gas turbine | 183.6 | May 2029 | In study |
| Violet StorageMcKenzie Road (8858) 138 kV Substation | VIOLET STORAGE | Battery storage (stand-alone) | 151.0 | Jul 2029 | In study |
Crowded connection points in Nueces County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Nelson Sharpe (85000) 345 kV 2 requests · 220 MW2 signed; security posted
- Noria Solar DCC 23INR0061 · Solar · 145 MW · Signed; security posted
- Noria Storage 23INR0062 · Battery storage · 75 MW · Signed; security posted
MCKENZIE4A (8858) 138 kV 2 requests · 455 MW1 in study, 1 signed
- NavBoot BESS 25INR0375 · Battery storage · 304 MW · Signed Oct 2025
- Violet Storage 25INR0076 · Battery storage · 151 MW · In study
Lon Hill (8455) 345 kV 6 requests · 1,573 MW · 2 in Nueces County, 4 in San Patricio, Zapata, Brooks3 in study, 2 signed; security posted, 1 signed
- Sunscape Renewable Energy Solar SLF 27INR0047 · Solar · 523 MW · Signed; security posted
- Sunscape Renewable Energy Storage SLF 27INR0048 · Battery storage · 0 MW · Signed; security posted
- Palo Verde Wind 27INR0132 · Wind · 298 MW · Signed Dec 2025 · San Patricio
- Vaquero 1 Wind 17INR0043 · Wind · 400 MW · In study · Zapata
- Kinenos Solar 23INR0087 · Solar · 203 MW · In study · Brooks
- PALO VERDE BESS 27INR0227 · Battery storage · 150 MW · In study · San Patricio
Reforzar (80078) 345 kV 5 requests · 1,199 MW · 2 in Nueces County, 3 in Brooks3 in study, 2 signed; security posted
- Sunscape Renewable Energy Solar SLF 27INR0047 · Solar · 523 MW · Signed; security posted
- Sunscape Renewable Energy Storage SLF 27INR0048 · Battery storage · 0 MW · Signed; security posted
- Verily Solar (FKA Cuello De Cuero Solar) 28INR0059 · Solar · 261 MW · In study · Brooks
- Reforzar BESS 1 27INR0400 · Battery storage · 208 MW · In study · Brooks
- Reforzar Bess 2 27INR0401 · Battery storage · 208 MW · In study · Brooks
JAVELINA4A (8475) 138 kV 2 requests · 351 MW2 in study
- Jalisco Peaker 28INR0121 · Gas turbine · 184 MW · In study
- Jalisco Cogen 27INR0337 · Gas combined cycle · 168 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Nueces County
- Nueces County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 14, Corpus Christi: 500 North Shoreline Blvd, Ste 500, Corpus Christi TX 78401-0318, 361-881-6900; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Nueces County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Nueces County.
Permits and reviews for Nueces County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Nueces County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Nueces County connects to the grid
Nueces County is on the ERCOT grid. The projects listed above are in ERCOT's Coastal load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Nueces County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Nueces County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 14
Aransas · Bee · Calhoun · DeWitt · Goliad · Gonzales · Jackson · Jim Wells · Kleberg · Lavaca · Live Oak · Refugio · San Patricio · Victoria