Hidalgo County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
25 proposed energy projects from ERCOT's September 2026 report, plus who to call in Hidalgo County and in TCEQ Region 15 before signing a solar, wind, or battery storage lease.
Check land in Hidalgo CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Hidalgo County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Hidalgo County?
ERCOT's September 2026 interconnection report lists 25 proposed energy projects in Hidalgo County (3 solar, 1 wind, 20 battery storage and 1 gas), about 3,488 MW in all. 5 of the 25 have a signed interconnection agreement, and 2 have been approved for energization or synchronization.
What stands out in Hidalgo County
By capacity, battery storage leads in Hidalgo County with 2,572 MW across 20 projects, followed by solar (3 projects, 432 MW) and gas (1 project, 250 MW). The largest single project is Anawa La Gas, a 250 MW gas combined cycle project listed under Anawa La Solar LLC, still in study, and its target online date is Dec 2028. Of the 25, 20 are still in ERCOT's study process, 2 have a signed interconnection agreement but no security posted yet, 1 has posted security or started construction and 2 are approved for energization or synchronization. Connection points are mostly at 138 kV (19 projects) and 345 kV (5 projects) (why the voltage matters). Anawa La Solar LLC is listed on the most projects here (3 of 25); 18 different companies appear in all. Target online dates for the projects not yet running span May 2027 to Sep 2029. All of them fall in ERCOT's South load zone. 1 that was listed in August has since dropped off.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| North Edinburg BESS 1North Edinburg | Edinburg ESS Assets LLC | Battery storage (stand-alone) | 10.0 | Aug 2026 | Approved for synchronization |
| Gunnar BESS8029 CLOSNER4A 138kV | Gunnar Reliability Project LLC | Battery storage (stand-alone) | 154.8 | Nov 2026 | Approved for synchronization |
| Monte Cristo II Wind8574 Pomelo 345kV | Monte Cristo Windpower II, LLC | Wind | 233.9 | Dec 2028 | Signed; security posted |
| Val Vista Grid BESS 1Tap 345kV 8383 North Edinburg - 80137 Stewart Road · shared with 1 other request | Val Vista Grid, LLC | Battery storage (stand-alone) | 209.3 | Mar 2029 | Signed Dec 2025 |
| Val Vista Grid BESS 2Tap 345kV 8383 North Edinburg - 80137 Stewart Road · shared with 1 other request | Val Vista Grid, LLC | Battery storage (stand-alone) | 210.6 | Mar 2029 | Signed Dec 2025 |
| Palmvalley StorageFrontera (#8980) | Palm Valley BESS LLC | Battery storage (stand-alone) | 100.0 | May 2027 | In study |
| Anawa La BESSTap 138KV 8394 Liston- 8392 Bates | Anawa La Solar LLC | Battery storage (paired with solar) | 103.7 | Aug 2027 | In study |
| Anawa La SolarTAP 138 KV 8394 LISTON - 8392 BATES · shared with 2 other requests | Anawa La Solar LLC | Solar | 93.3 | Aug 2027 | In study |
| Bronze Quinta StorageS_MCALLN 8371 (S. McAllen 138kV Substation) | KCE TX 28, LLC | Battery storage (stand-alone) | 103.5 | Jan 2028 | In study |
| Big Five StorageTap 138kV (5784) Redgtss - (8380) Nedina | TX BESS 3 LLC | Battery storage (stand-alone) | 102.2 | Jan 2028 | In study |
| Hawkins BESS85005 ELGATO4A 138 kV | BRP BLUE TOPAZ 7, LLC | Battery storage (stand-alone) | 150.4 | Jan 2028 | In study |
| Camellia StorageTap 138 kV 8358 | Camellia Storage Project LLC | Battery storage (stand-alone) | 90.8 | Jun 2028 | In study |
| PSE Chihuahua TX StorageTap 138kV 8392 Bates – 8394 Liston | PureSky Development Inc | Battery storage (stand-alone) | 200.0 | Jun 2028 | In study |
| PSE Minnesota TX StorageTap 138kV 8372 North Pharr – 8906 North Alamo | PureSky Development Inc | Battery storage (stand-alone) | 94.0 | Jun 2028 | In study |
| PSE Richardson TX StorageTAP 138KV 8374 SOUTH EAST EDINBURG - 8029 CLOSNER | PureSky Development Inc. | Battery storage (stand-alone) | 100.0 | Jun 2028 | In study |
| Palladium StorageTap 138 kV 8656 Luna - 8033 Pantera | Palladium Energy Storage LLC | Battery storage (stand-alone) | 156.3 | Jun 2028 | In study |
| Eligius BESStap 138kV Liston (#8394) – JL Bates (#8392) line, AEP | Eligius Storage LLC | Battery storage (stand-alone) | 174.7 | Nov 2028 | In study |
| Borderland ESCtap 138kV 8380 NEDIN4A – 8632 NMCALLEN4C | FRESH AIR ENERGY II, LLC | Battery storage (stand-alone) | 200.0 | Nov 2028 | In study |
| McMEXICO STORAGE8644 Trade Zone 138kV | FRESH AIR ENERGY II, LLC | Battery storage (stand-alone) | 201.9 | Nov 2028 | In study |
| Anawa La GasListon 138 KV to Bates 138 KV | Anawa La Solar LLC | Gas combined cycle | 250.0 | Dec 2028 | In study |
| Donna BESSTap 345 kV 80137 Stewart Road - 8383 North Edinburg | Donna Solar LLC | Battery storage (paired with solar) | 53.9 | Feb 2029 | In study |
| Donna SolarTap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01 | Donna Solar LLC | Solar | 168.1 | Feb 2029 | In study |
| Sullivan BESSTap 138kV 8798 La Grulla - 8355 Goodwin · shared with 1 other request | Sullivan Solar LLC | Battery storage (paired with solar) | 72.2 | Feb 2029 | In study |
| Sullivan SolarTap 138kV 8798 La Grulla - 8355 Goodwin · shared with 1 other request | Sullivan Solar LLC | Solar | 170.7 | Feb 2029 | In study |
| Billie StorageTap 138kV 8357 North Weslaco – 8358 North Mercedes | Weslaco Storage LLC | Battery storage (stand-alone) | 83.8 | Sep 2029 | In study |
No longer listed since August
These projects were in ERCOT's August interconnection report but are not in its September 2026 report. ERCOT's reports do not say why a project leaves the list.
- Grapefruit Solar, solar, 291 MW (Grapefruit Solar LLC)
Crowded connection points in Hidalgo County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
North Edinburg (8383) 345 kV 6 requests · 1,032 MW · 4 in Hidalgo County, 2 in Willacy, Cameron3 in study, 2 signed, 1 signed; security posted
- Monte Alto 2 Wind 19INR0023 · Wind · 199 MW · Signed; security posted · Willacy
- Val Vista Grid BESS 2 24INR0102 · Battery storage · 211 MW · Signed Dec 2025
- Val Vista Grid BESS 1 22INR0387 · Battery storage · 209 MW · Signed Dec 2025
- Accalia Point Solar 23INR0066 · Solar · 190 MW · In study · Cameron
- Donna Solar 27INR0205 · Solar · 168 MW · In study
- Donna BESS 26INR0442 · Battery storage · 54 MW · In study
Stewart Road (80137) 345 kV 5 requests · 942 MW · 4 in Hidalgo County, 1 in Cameron3 in study, 2 signed
- Val Vista Grid BESS 2 24INR0102 · Battery storage · 211 MW · Signed Dec 2025
- Val Vista Grid BESS 1 22INR0387 · Battery storage · 209 MW · Signed Dec 2025
- Pachanga Wind 22INR0480 · Wind · 300 MW · In study · Cameron
- Donna Solar 27INR0205 · Solar · 168 MW · In study
- Donna BESS 26INR0442 · Battery storage · 54 MW · In study
Bates (8392) 138 kV 6 requests · 749 MW · 4 in Hidalgo County, 2 in Starr6 in study
- PSE Chihuahua TX Storage 24INR0447 · Battery storage · 200 MW · In study
- Eligius BESS 28INR0247 · Battery storage · 175 MW · In study
- Sword Solar 26INR0445 · Solar · 137 MW · In study · Starr
- Anawa La BESS 27INR0233 · Battery storage · 104 MW · In study
- Anawa La Solar 27INR0232 · Solar · 93 MW · In study
- Sword BESS 26INR0446 · Battery storage · 40 MW · In study · Starr
Liston (8394) 138 kV 6 requests · 749 MW · 4 in Hidalgo County, 2 in Starr6 in study
- PSE Chihuahua TX Storage 24INR0447 · Battery storage · 200 MW · In study
- Eligius BESS 28INR0247 · Battery storage · 175 MW · In study
- Sword Solar 26INR0445 · Solar · 137 MW · In study · Starr
- Anawa La BESS 27INR0233 · Battery storage · 104 MW · In study
- Anawa La Solar 27INR0232 · Solar · 93 MW · In study
- Sword BESS 26INR0446 · Battery storage · 40 MW · In study · Starr
North Mercedes (8358) 138 kV 2 requests · 175 MW2 in study
- Camellia Storage 23INR0480 · Battery storage · 91 MW · In study
- Billie Storage 27INR0338 · Battery storage · 84 MW · In study
Closner (8029) 138 kV 2 requests · 255 MW1 in study, 1 approved for synchronization
- Gunnar BESS 24INR0491 · Battery storage · 155 MW · Approved for synchronization
- PSE Richardson TX Storage 24INR0449 · Battery storage · 100 MW · In study
NEDIN4A (8380) 138 kV 2 requests · 302 MW2 in study
- Borderland ESC 25INR0039 · Battery storage · 200 MW · In study
- Big Five Storage 25INR0239 · Battery storage · 102 MW · In study
La Grulla (8798) 138 kV 3 requests · 443 MW · 2 in Hidalgo County, 1 in Starr3 in study
- PSE Flores TX Storage 24INR0445 · Battery storage · 200 MW · In study · Starr
- Sullivan Solar 26INR0443 · Solar · 171 MW · In study
- Sullivan BESS 26INR0444 · Battery storage · 72 MW · In study
Goodwin (8355) 138 kV 2 requests · 243 MW2 in study
- Sullivan Solar 26INR0443 · Solar · 171 MW · In study
- Sullivan BESS 26INR0444 · Battery storage · 72 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Hidalgo County
- Hidalgo County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 15, Harlingen: 1804 W Jefferson Ave, Harlingen TX 78550-5247, 956-425-6010; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Hidalgo County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Hidalgo County.
Permits and reviews for Hidalgo County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Hidalgo County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Recent local action: On July 22, 2025, the Hidalgo County Commissioners Court adopted an order approving a Chapter 312 tax abatement agreement with Monte Alto Windpower, LLC for the Monte Alto II project, an approximately 200-megawatt wind power project in Hidalgo County. The agreement set the abatement at 60% of ad valorem taxes on the newly created value. (Hidalgo County Commissioners Court order (Monte Alto II); checked October 17, 2026).
How a project in Hidalgo County connects to the grid
Hidalgo County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Hidalgo County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Hidalgo County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 15
Brooks · Cameron · Jim Hogg · Kenedy · Starr · Willacy