Frio County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects5
Total capacity924MW
Signed agreements0of 5
New since August0requests

5 proposed energy projects from ERCOT's September 2026 report, plus who to call in Frio County and in TCEQ Region 13 before signing a solar, wind, or battery storage lease.

Check land in Frio CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Frio County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Frio County?

ERCOT's September 2026 interconnection report lists 5 proposed energy projects in Frio County (2 solar and 3 battery storage), about 924 MW in all. None has a signed interconnection agreement yet.

What stands out in Frio County

By capacity, battery storage leads in Frio County with 522 MW across 3 projects, followed by solar (2 projects, 402 MW). The largest single project is Morrow Lake Storage, a 201 MW battery storage paired with solar project listed under Morrow Lake Storage, LLC, still in study, and its target online date is Sep 2028. Of the 5, 5 are still in ERCOT's study process. Every listed connection point is on the 138 kV system (why the voltage matters). Hamlet Solar, LLC is listed on the most projects here (2 of 5); 4 different companies appear in all. Target online dates for the projects not yet running span Jun 2028 to Sep 2029. All of them fall in ERCOT's South load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Dilley SolarTap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLSAETS Development Holdings LLCSolar200.7Jun 2028In study
Morrow Lake StorageMorrow Lake Switch 138kV (5896)Morrow Lake Storage, LLCBattery storage (paired with solar)201.1Sep 2028In study
Black Creek BESSNew tap between line Bigfoot4A (8221) - MooreSw8 (5827)Francitas Renewables LLCBattery storage (stand-alone)120.0Mar 2029In study
Hamlet Solar SLFTap 138kV #5895 PEARSALL - #5827 MOOREHamlet Solar, LLCSolar201.0Sep 2029In study
Hamlet Storage SLFTap 138kV #5895 PEARSALL -#5827 MOOREHamlet Solar, LLCBattery storage (paired with solar)201.0Sep 2029In study

Crowded connection points in Frio County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Moore (5827) 138 kV 3 requests · 522 MW3 in study
  • Hamlet Solar SLF 27INR0362 · Solar · 201 MW · In study
  • Hamlet Storage SLF 27INR0363 · Battery storage · 201 MW · In study
  • Black Creek BESS 28INR0411 · Battery storage · 120 MW · In study
Pearsall (5895) 138 kV 2 requests · 402 MW2 in study
  • Hamlet Solar SLF 27INR0362 · Solar · 201 MW · In study
  • Hamlet Storage SLF 27INR0363 · Battery storage · 201 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Frio County

  • Frio County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 13, San Antonio: 14250 Judson Rd, San Antonio TX 78233-4480, 210-490-3096; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Frio County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Frio County.

Permits and reviews for Frio County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Frio County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Frio County connects to the grid

Frio County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Frio County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Frio County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 13

Atascosa · Bandera · Bexar · Comal · Edwards · Gillespie · Guadalupe · Karnes · Kendall · Kerr · Medina · Real · Uvalde · Wilson

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.