Kaufman County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
15 proposed energy projects from ERCOT's September 2026 report, plus who to call in Kaufman County and in TCEQ Region 4 before signing a solar, wind, or battery storage lease.
Check land in Kaufman CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Kaufman County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Kaufman County?
ERCOT's September 2026 interconnection report lists 15 proposed energy projects in Kaufman County (6 solar and 9 battery storage), about 2,075 MW in all. 4 of the 15 have a signed interconnection agreement, and 1 has been approved for energization or synchronization. The table also lists 1 change to existing plants (repowers or capacity changes), not counted above.
What stands out in Kaufman County
By capacity, solar leads in Kaufman County with 1,102 MW across 6 projects, followed by battery storage (9 projects, 974 MW); 2 self-limiting projects (reported at 0 MW because the resource limits its own output) are listed without a capacity. The largest single project is Solarville Solar SLF, a 403 MW solar project listed under Ville Solar, LLC, still in study, and its target online date is Jul 2029. Of the 15, 11 are still in ERCOT's study process, 2 have a signed interconnection agreement but no security posted yet, 1 has posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 138 kV (9 projects) and 345 kV (6 projects) (why the voltage matters). Erika Solar, LLC, Lightsource Renewable Energy Development LLC and Mystic Spring Renewable Energy LLC are each listed on 2 projects; 10 different companies appear in all. Target online dates for the projects not yet running span Dec 2026 to Sep 2029. All of them fall in ERCOT's North load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Erika SolarTap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432) · shared with 1 other request | Erika Solar, LLC | Solar | 200.5 | Nov 2026 | Approved for synchronization |
| Sowers Storage6894 Rose Hill_RC Sub 138 kV | Sowers Energy Storage LLC | Battery storage (stand-alone) | 208.9 | Jul 2027 | Signed; security posted |
| Mystic Springs Renewable Energy Solar SLFTap 345 kV Royse Switch (2478) – Poetry Switch (2485) · shared with 1 other request | Mystic Spring Renewable Energy LLC | Solar | 258.8 | Mar 2028 | Signed Oct 2025 |
| LUBIO SOLARtap 138kV 2727 Crandall - 2724 Kaufman Northwest | BDPU Solar Lubio LLC | Solar | 54.7 | Apr 2028 | Signed Nov 2024 |
| Sunbelt Solartap 138kV 6902 Talty - 6801 Patton | Rose Hill Solar LLC | Solar | 81.5 | Dec 2026 | In study |
| Sunbelt StorageTap 138kV 6902 Talty - 6894 Rose Hill | Rose Hill Solar LLC | Battery storage (paired with solar) | 52.0 | Dec 2026 | In study |
| Fudge Ranch BESS<6902><TALTY_RC><138kV> | Crandall BESS LLC | Battery storage (stand-alone) | 104.0 | Jun 2027 | In study |
| Mystic Springs Renewable Energy Storage SLFTap 345 kV Royse Switch (2478) – Poetry Switch (2485) · shared with 1 other request | Mystic Spring Renewable Energy LLC | Battery storage (paired with solar) | Self-limiting | Mar 2028 | In study |
| Solarville BESS SLFTap 345 kV (#2432)Tri Corner - (#3105) Elkton · shared with 1 other request | Ville Solar, LLC | Battery storage (paired with solar) | Self-limiting | Sep 2028 | In study |
| Solarville Wind SLFTap 345 kV (#2432)Tri Corner - (#3105) Elkton · shared with 1 other request | Ville Solar, LLC | Wind | 0 no capacity change | Sep 2028 | In study |
| Yellow Leaf BESSTap 138kV Crandall (#2727) – Kaufman Northwest (#2724) · shared with 1 other request | Lightsource Renewable Energy Development LLC | Battery storage (paired with solar) | 103.1 | Sep 2028 | In study |
| Yellow Leaf II BESSTap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8 | Yellow Leaf Energy Storage LLC | Battery storage (paired with solar) | 205.7 | Sep 2028 | In study |
| Yellow Leaf SolarTap 138kV Crandall (#2727) – Kaufman Northwest (#2724) · shared with 1 other request | Lightsource Renewable Energy Development LLC | Solar | 103.2 | Sep 2028 | In study |
| Erika BESSTap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432) · shared with 1 other request | Erika Solar, LLC | Battery storage (paired with solar) | 100.0 | Jul 2029 | In study |
| Solarville Solar SLFTap 345kV #3123 Trinidad Switch – #2432 Tri Corner. | Ville Solar, LLC | Solar | 402.9 | Jul 2029 | In study |
| Slash Pine Storage1698 Sulphur Springs Switch and 3174 Canton Switch 138 kV | EG Slash Pine LLC | Battery storage (stand-alone) | 200.0 | Sep 2029 | In study |
Crowded connection points in Kaufman County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Crandall (2727) 138 kV 4 requests · 467 MW3 in study, 1 signed
- LUBIO SOLAR 22INR0426 · Solar · 55 MW · Signed Nov 2024
- Yellow Leaf II BESS 28INR0412 · Battery storage · 206 MW · In study
- Yellow Leaf Solar 27INR0455 · Solar · 103 MW · In study
- Yellow Leaf BESS 27INR0456 · Battery storage · 103 MW · In study
Kaufman Northwest (2724) 138 kV 4 requests · 467 MW3 in study, 1 signed
- LUBIO SOLAR 22INR0426 · Solar · 55 MW · Signed Nov 2024
- Yellow Leaf II BESS 28INR0412 · Battery storage · 206 MW · In study
- Yellow Leaf Solar 27INR0455 · Solar · 103 MW · In study
- Yellow Leaf BESS 27INR0456 · Battery storage · 103 MW · In study
TRICRN1_5 (2432) 345 kV 13 requests · 1,520 MW · 4 in Kaufman County, 8 in Dallas12 in study, 1 approved for synchronization
- Erika Solar 24INR0303 · Solar · 200 MW · Approved for synchronization
- Solarville Solar SLF 26INR0086 · Solar · 403 MW · In study
- watermelon 1 energy storage 27INR0457 · Battery storage · 102 MW · In study · Dallas
- watermelon 2 energy storage 27INR0458 · Battery storage · 102 MW · In study · Dallas
- watermelon 3 energy storage 27INR0459 · Battery storage · 102 MW · In study · Dallas
- watermelon 4 energy storage 27INR0460 · Battery storage · 102 MW · In study · Dallas
- watermelon 5 energy storage 28INR0255 · Battery storage · 102 MW · In study · Dallas
- watermelon 6 energy storage 28INR0256 · Battery storage · 102 MW · In study · Dallas
- watermelon 7 energy storage 28INR0257 · Battery storage · 102 MW · In study · Dallas
- watermelon 8 energy storage 28INR0258 · Battery storage · 102 MW · In study · Dallas
- Erika BESS 27INR0531 · Battery storage · 100 MW · In study
- Solarville Wind SLF 28INR0431 · Wind · 0 MW · In study
- Solarville BESS SLF 28INR0432 · Battery storage · 0 MW · In study
Talty (6902) 138 kV 3 requests · 238 MW3 in study
- Fudge Ranch BESS 26INR0502 · Battery storage · 104 MW · In study
- Sunbelt Solar 23INR0222 · Solar · 82 MW · In study
- Sunbelt Storage 23INR0409 · Battery storage · 52 MW · In study
Elkton (3105) 345 kV 6 requests · 703 MW · 3 in Kaufman County, 2 in Rusk4 in study, 2 approved for synchronization
- Dry Creek Solar I 23INR0286 · Solar · 201 MW · Approved for synchronization · Rusk
- Erika Solar 24INR0303 · Solar · 200 MW · Approved for synchronization
- Dry Creek Solar II 27INR0488 · Solar · 201 MW · In study · Rusk
- Erika BESS 27INR0531 · Battery storage · 100 MW · In study
- Solarville Wind SLF 28INR0431 · Wind · 0 MW · In study
- Solarville BESS SLF 28INR0432 · Battery storage · 0 MW · In study
ROSE HILL_RC (6894) 138 kV 2 requests · 261 MW1 signed; security posted, 1 in study
- Sowers Storage 22INR0552 · Battery storage · 209 MW · Signed; security posted
- Sunbelt Storage 23INR0409 · Battery storage · 52 MW · In study
Royse (2478) 345 kV 3 requests · 384 MW · 2 in Kaufman County, 1 in Rockwall2 in study, 1 signed
- Mystic Springs Renewable Energy Solar SLF 24INR0339 · Solar · 259 MW · Signed Oct 2025
- TE Smith Storage 2 26INR0418 · Battery storage · 125 MW · In study · Rockwall
- Mystic Springs Renewable Energy Storage SLF 24INR0340 · Battery storage · 0 MW · In study
Poetry (2485) 345 kV 4 requests · 510 MW · 2 in Kaufman County, 2 in Van Zandt3 in study, 1 signed
- Mystic Springs Renewable Energy Solar SLF 24INR0339 · Solar · 259 MW · Signed Oct 2025
- Goldfinch Solar 26INR0253 · Solar · 151 MW · In study · Van Zandt
- Goldfinch Storage 26INR0254 · Battery storage · 100 MW · In study · Van Zandt
- Mystic Springs Renewable Energy Storage SLF 24INR0340 · Battery storage · 0 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Kaufman County
- Kaufman County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 4, Dallas/Fort Worth: 2309 Gravel Dr, Fort Worth TX 76118-6951, 817-588-5800; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Kaufman County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Kaufman County.
Permits and reviews for Kaufman County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Kaufman County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Kaufman County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.
How a project in Kaufman County connects to the grid
Kaufman County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Kaufman County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Kaufman County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 4
Collin · Cooke · Dallas · Denton · Ellis · Erath · Fannin · Grayson · Hood · Hunt · Johnson · Navarro · Palo Pinto · Parker · Rockwall · Somervell · Tarrant · Wise