Dimmit County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
12 proposed energy projects from ERCOT's September 2026 report, plus who to call in Dimmit County and in TCEQ Region 16 before signing a solar, wind, or battery storage lease.
Check land in Dimmit CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Dimmit County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Dimmit County?
ERCOT's September 2026 interconnection report lists 12 proposed energy projects in Dimmit County (3 solar and 9 battery storage), about 1,294 MW in all. 2 of the 12 have a signed interconnection agreement.
What stands out in Dimmit County
By capacity, battery storage leads in Dimmit County with 987 MW across 9 projects, followed by solar (3 projects, 307 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Desert Palm BESS, a 201 MW stand-alone battery storage project listed under Desert Palm BESS, LLC, with an interconnection agreement signed in Jul 2026, and its target online date is Sep 2028. Of the 12, 10 are still in ERCOT's study process and 2 have a signed interconnection agreement but no security posted yet. Connection points are mostly at 138 kV (10 projects) and 69 kV (2 projects) (why the voltage matters). 7L Solar, LLC, Velado Solar, LLC and Wild Horse Desert Solar, LLC are each listed on 2 projects; 9 different companies appear in all. Target online dates for the projects not yet running span Dec 2026 to Nov 2029. All of them fall in ERCOT's South load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Rose Quartz BESSTap 138kV 8283 Asherton - 8613 Bigwells | Rose Quartz BESS, LLC | Battery storage (stand-alone) | 101.4 | Dec 2026 | Signed Jul 2026 |
| Desert Palm BESS78280 Bevo Substation 138 kV | Desert Palm BESS, LLC | Battery storage (stand-alone) | 201.3 | Sep 2028 | Signed Jul 2026 |
| Saluga Ranch StorageAsherton 8283 - Big wells 8613 -138 kV | Saluga Ranch Energy, LLC | Battery storage (stand-alone) | 125.4 | Aug 2027 | In study |
| Steppe Reserve Storage8283 Asherton 138 kV | KCE TX 25, LLC | Battery storage (stand-alone) | 51.9 | Jan 2028 | In study |
| Sugarloaf BESS(#80481) PILONCIL4 138KV | Sugarloaf Clean Energy LLC | Battery storage (stand-alone) | 100.6 | Jan 2028 | In study |
| Wintergarden BESS8970 Catarina 138 kV | Wintergarden BESS LLC | Battery storage (stand-alone) | 201.2 | Jun 2028 | In study |
| Wild Horse Desert SolarTap 138kV 8613 Big Well - 8212 Dilley Switch · shared with 1 other request | Wild Horse Desert Solar, LLC | Solar | 120.0 | Jul 2028 | In study |
| Wild Horse Desert StorageTap 138kV 8613 Big Well - 8212 Dilley Switch · shared with 1 other request | Wild Horse Desert Solar, LLC | Battery storage (paired with solar) | 90.3 | Jul 2028 | In study |
| Velado Solar SLFTap 138kV 78281 Dimmit - 8274 Conoco Chittam | Velado Solar, LLC | Solar | 115.2 | Sep 2028 | In study |
| Velado Storage SLFTap 138kv 78281 Dimmit - 8274 Conoco Chittam. | Velado Solar, LLC | Battery storage (paired with solar) | 115.2 | Sep 2028 | In study |
| 7L Solar SLFTap 69kV 5870 Brundage - 5868 Big Wells · shared with 1 other request | 7L Solar, LLC | Solar | 71.6 | Nov 2029 | In study |
| 7L Storage SLFTap 69kV 5870 Brundage - 5868 Big Wells · shared with 1 other request | 7L Solar, LLC | Battery storage (paired with solar) | Self-limiting | Nov 2029 | In study |
Crowded connection points in Dimmit County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Big Wells (8613) 138 kV 5 requests · 638 MW · 4 in Dimmit County, 1 in Frio4 in study, 1 signed
- Rose Quartz BESS 25INR0133 · Battery storage · 101 MW · Signed Jul 2026
- Dilley Solar 28INR0461 · Solar · 201 MW · In study · Frio
- Saluga Ranch Storage 26INR0356 · Battery storage · 125 MW · In study
- Wild Horse Desert Solar 27INR0330 · Solar · 120 MW · In study
- Wild Horse Desert Storage 27INR0331 · Battery storage · 90 MW · In study
Asherton (8283) 138 kV 3 requests · 279 MW2 in study, 1 signed
- Rose Quartz BESS 25INR0133 · Battery storage · 101 MW · Signed Jul 2026
- Saluga Ranch Storage 26INR0356 · Battery storage · 125 MW · In study
- Steppe Reserve Storage 23INR0164 · Battery storage · 52 MW · In study
Dilley (8212) 138 kV 3 requests · 411 MW · 2 in Dimmit County, 1 in Frio3 in study
- Dilley Solar 28INR0461 · Solar · 201 MW · In study · Frio
- Wild Horse Desert Solar 27INR0330 · Solar · 120 MW · In study
- Wild Horse Desert Storage 27INR0331 · Battery storage · 90 MW · In study
Dimmit (78281) 138 kV 2 requests · 230 MW2 in study
- Velado Solar SLF 27INR0373 · Solar · 115 MW · In study
- Velado Storage SLF 27INR0374 · Battery storage · 115 MW · In study
Conoco Chittam (8274) 138 kV 2 requests · 230 MW2 in study
- Velado Solar SLF 27INR0373 · Solar · 115 MW · In study
- Velado Storage SLF 27INR0374 · Battery storage · 115 MW · In study
Brundage (5870) 69 kV 2 requests · 72 MW2 in study
- 7L Solar SLF 29INR0107 · Solar · 72 MW · In study
- 7L Storage SLF 29INR0108 · Battery storage · 0 MW · In study
Big Wells (5868) 69 kV 2 requests · 72 MW2 in study
- 7L Solar SLF 29INR0107 · Solar · 72 MW · In study
- 7L Storage SLF 29INR0108 · Battery storage · 0 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Dimmit County
- Dimmit County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 16, Laredo: 707 E Calton Rd, Ste 304, Laredo TX 78041-3887, 956-791-6611; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Dimmit County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Dimmit County.
Permits and reviews for Dimmit County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Dimmit County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Dimmit County connects to the grid
Dimmit County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Dimmit County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Dimmit County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 16
Duval · Kinney · La Salle · Maverick · McMullen · Val Verde · Webb · Zapata · Zavala