How to register with the PUCT (PGC) and ERCOT (Resource Entity)

Updated

General information, not a substitute for the advice of an attorney.

Who grants it: Public Utility Commission of Texas (PGC registration) and ERCOT (Resource Entity registration).

When it applies: Any owner of a generating facility of 1 MW or more that sells power at wholesale registers as a PGC under 16 TAC 25.109 (self-generators register too); the entity responsible for the resource registers with ERCOT as a Resource Entity before the resource is modeled and energized.

What the application asks for, and where to find it

The application asks forWhere you find itHow
Legal entity, officers, address, FEINYou (the applicant)Your organizing documents; the PGC form is verified by oath and signed by an owner, partner or officer.
Facility location and descriptionThis site: the land reportThe land report: county and coordinates; nameplate and technology from your engineer.
FERC filings and orders (non-interrogatory)You (the applicant)Copies of any FERC filings for the facility, as the rule requires for PGCs.
Resource Asset Registration Forms (RARF) dataYour engineerUnit data, metering, telemetry, from the electrical design and the RARF templates.
Interconnection agreementThe agency's websiteThe executed SGIA from the ERCOT request (see the GINR guide).
Qualified Scheduling Entity (QSE) designationYou (the applicant)Who will schedule the resource in the market; many developers contract a QSE.
What the "where you find it" column means
This site: the land report
Run the spot on the land report; the value is on the page named, with its agency source.
Appraisal district (tax assessor)
The county appraisal district record: property ID, legal description, acreage, owner of record, agricultural valuation. The report's Lease page links it; the Permits page lists the district's phone.
The landowner
Only the owner can supply it: signed authorization, deed reference, existing leases, access, their contact details.
Your engineer
From your civil or electrical engineer: site plan, disturbed acreage, drainage, the electrical one-line, nameplate and inverter data, structure heights.
Surveyor or title company
Boundary survey, legal description for recording, easements of record, title commitment.
The agency's website
The agency publishes it: forms, fee schedules, community numbers, district offices, portal accounts.
You (the applicant)
Your entity details: legal name, address, signatory, contacts, FEIN, insurance.

How to file it

  1. Download the PGC registration form from the PUCT PGC page, complete and verify it, and file it with PUCT Central Records (PUCT staff review for completeness within 15 business days under the rule; 10 business days to cure).
  2. Register with ERCOT as a Resource Entity and submit the RARF; ERCOT models the unit once Planning Guide 6.9 is met.
  3. Report changes: PGCs within 45 days; generating capacity reports under 16 TAC 25.91.

The pages you will use

Open: PUCT power generation company registration →
PUCT power generation company registration (screenshot captured monthly from the agency page)
Open: 16 TAC 25.109 (PDF) →
16 TAC 25.109 (PDF) (screenshot captured monthly from the agency page)
Open: ERCOT Resource Entity registration →
ERCOT Resource Entity registration (screenshot captured monthly from the agency page)

Official pages cited

How-to guidance from the agency pages linked above, not legal advice; forms, fees and offices change, so confirm with the office before filing. The land report fills in the site facts; the rest comes from the sources named in each row.

General information from the sources linked above, not legal, tax, or financial advice.

Sources and helpful links

More official contacts and resources: Helpful links.

Browse resources