Wharton County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
38 proposed energy projects from ERCOT's September 2026 report, plus who to call in Wharton County and in TCEQ Region 12 before signing a solar, wind, or battery storage lease.
Check land in Wharton CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Wharton County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Wharton County?
ERCOT's September 2026 interconnection report lists 38 proposed energy projects in Wharton County (17 solar, 1 wind, 18 battery storage and 2 gas), about 8,294 MW in all. 21 of the 38 have a signed interconnection agreement, and 6 have been approved for energization or synchronization. The table also lists 4 changes to existing plants (repowers or capacity changes), not counted above. 1 is new since August.
What stands out in Wharton County
By capacity, solar leads in Wharton County with 3,865 MW across 17 projects, followed by battery storage (18 projects, 2,794 MW) and gas (2 projects, 1,436 MW). The largest single project is EmberGreen, a 1,036 MW gas turbine project listed under EmberGreen Energy Center, with an interconnection agreement signed in Aug 2026, and its target online date is Jan 2028. Of the 38, 17 are still in ERCOT's study process, 7 have a signed interconnection agreement but no security posted yet, 8 have posted security or started construction and 6 are approved for energization or synchronization. Connection points are mostly at 345 kV (19 projects) and 138 kV (17 projects) (why the voltage matters). The single most-used connection point is 44200 Hillje 345kV, shared by 4 projects. GulfStar Power, LLC is listed on the most projects here (3 of 38); 35 different companies appear in all. Target online dates for the projects not yet running span Nov 2026 to Apr 2032. All of them fall in ERCOT's South load zone. 1 is new since August.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| TEXAS GULF SULPHUR REPOWER43340 Gulftie 138 kV | Wharton County Generation, LLC | Gas turbine | 16.1 | Mar 2025 | Approved for synchronization |
| PHOTON SOLAR 1 2 SLF44880 Waterh_POI_5 345kV · shared with 4 other requests | GulfStar Power, LLC | Solar | 235.7 | May 2026 | Approved for synchronization |
| PHOTON SOLAR 3 SLF44880 Waterh_POI_5 345kV · shared with 4 other requests | GulfStar Power, LLC | Solar | 110.0 | May 2026 | Approved for synchronization |
| PHOTON SOLAR 4 SLF44880 Waterh_POI_5 345kV · shared with 4 other requests | GulfStar Power, LLC | Solar | 106.0 | May 2026 | Approved for synchronization |
| Danish Fields Solar44200 Hillje 345kV · shared with 3 other requests | Danish Fields Solar, LLC | Solar | 602.8 | Aug 2026 | Approved for synchronization |
| Sbranch SolarTap 138kV 44190 East Bernard - 44130 Caney | Bernard Creek Solar, LLC | Solar | 233.5 | Oct 2026 | Approved for synchronization |
| Lane City Wind44040 Bailey 345kV | RWE Clean Energy, LLC | Wind | 199.5 | Dec 2026 | Approved for synchronization |
| Hollywood Solar Repower44060 BLU 345kV | RED TAILED HAWK SOLAR LLC | Solar | 9.9 | Sep 2026 date passed; status per ERCOT | Signed; security posted |
| East Bernard BESSStation Name: East Bernard | Regis East Bernard LLC | Battery storage (stand-alone) | 9.5 | Nov 2026 | Signed; security posted |
| Raven StorageTap 138kV 44740 Wallis - 44190 East Bernard CKT#65 | Raven Storage, LLC | Battery storage (stand-alone) | 103.5 | Feb 2027 | Signed; security posted |
| Space City Solar44200 Hillje 345kV · shared with 3 other requests | Apollo Solar Ranch, LLC | Solar | 366.0 | Jun 2027 | Signed; security posted |
| OCI SunRopertap138kV #43190 South Lane City to #42985 Dyann CKT#60 | OCI SunRoper LLC | Solar | 265.1 | Oct 2027 | Signed; security posted |
| Diran BESS43190 South Lane City 138kV | BRP Diran BESS LLC | Battery storage (stand-alone) | 103.0 | Jan 2028 | Signed; security posted |
| Northington SolarThe 138 kV El Campo (#8102) - Pulsar (#8192) Line; AEP. | Northington Solar, LLC | Solar | 125.9 | Mar 2028 | Signed; security posted |
| Ramsey Storage44200 Hillje 345kV · shared with 3 other requests | Hecate Energy Ramsey Storage LLC | Battery storage (stand-alone) | 500.0 | Jun 2028 | Signed; security posted |
| Maleza Solartap Blue – Hillje 345 kv Ckt.#27 · shared with 2 other requests | Brush Solar LLC | Solar | 254.9 | Dec 2028 | Signed; security posted |
| PHOTON SOLAR REPOWERING44880 Waterh_POI_5 345kV · shared with 4 other requests | GulfStar Power, LLC | Solar | 0 no capacity change | Aug 2027 | Signed Feb 2021 |
| Sorghum BESS#44060 Blue Substation 345kV | Blue Creek BESS, LLC | Battery storage (stand-alone) | 208.9 | Dec 2027 | Signed Jan 2025 |
| EmberGreenTap 138kV 48050 Caney - 44150 Hungerford | EmberGreen Energy Center | Gas turbine | 1,036.0 | Jan 2028 | Signed Aug 2026 |
| Cernan BESSHillje 345kV (#44200) | Cernan BESS LLC | Battery storage (stand-alone) | 10.0 | Oct 2028 | Signed Dec 2025 |
| TOCE BESS 1138 kV Danevang Switching Station (Bus# 5546) | TOCE BESS 1, LLC | Battery storage (stand-alone) | 205.2 | Dec 2028 | Signed Dec 2024 |
| Erin Solar44040 Bailey 345 kV · shared with 1 other request | Erin Solar LLC | Solar | 208.3 | Dec 2029 | Signed Mar 2023 |
| Malachite BESSTap 345 kV 44200 Hillje – 9073 Holman | Malachite Storage LLC | Battery storage (paired with solar) | 191.1 | Apr 2032 | Signed Dec 2025 |
| Malachite SolarThe 345 kV Hillje (#44200) – Holman (#9073) Line; AEN. | Malachite Solar LLC | Solar | 184.6 | Apr 2032 | Signed Dec 2025 |
| Cottonseed Energy StorageSouth Lane City and PSEE # is 43190 | Cottonseed Energy Storage LLC | Battery storage (stand-alone) | 207.6 | Apr 2027 | In study |
| PHOTON BESS REPOWERING44880 Waterh_POI_5 345kV · shared with 4 other requests | GulfStar Power, LLC | Battery storage (paired with solar) | 305.5 | Aug 2027 | In study |
| Hynes Bay Energy StorageTap 138kV 5546 DANEVANG SW - 8121 BLESSING | Hynes Bay Energy Storage, LLC | Battery storage (stand-alone) | 101.2 | Dec 2027 | In study |
| Voyager Storage44200 Hillje 345kV · shared with 3 other requests | EDF Renewables Development, Inc. | Battery storage (stand-alone) | 50.1 | Apr 2028 | In study |
| Alpujarra Solar5521 GALOW 138 KV | Greening USA Corp. | Solar | 112.5 | May 2028 | In study |
| Brela BESS LLC44040 Bailey SW 345 kV | Brela BESS LLC | Battery storage (stand-alone) | 251.3 | May 2028 | In study |
| Wittig Solar138 kV Gulftie (#43340) – San Bernard (#43110) | Greenalia Solar Power Wittig LLC | Solar | 106.9 | Oct 2028 | In study |
| Boling Generation (TEF-Due Diligience)43340 Gulftie 138kV | Boling Generation | Gas turbine | 400.0 | Dec 2028 | In study |
| Blue Creek Energy StorageTap 138kV 42985 DYANN_POI8 - 43190 S_LANE_B138 Ckt 60 | Blue Creek Energy Storage, LLC | Battery storage (stand-alone) | 101.2 | Dec 2028 | In study |
| Hadrian Energy StorageLine Tap 138kV #43012 NEWGLF60T3_8 - #43190 S_LANE_B138 | Hadrian Energy Storage, LLC | Battery storage (stand-alone) | 101.2 | Dec 2028 | In study |
| Maleza Solar IItap Blue – Hillje 345 kv Ckt.#27 · shared with 2 other requests | Brush Solar, LLC | Solar | 254.9 | Dec 2028 | In study |
| Maleza Storagetap Blue – Hillje 345 kv Ckt.#27 · shared with 2 other requests | Brush Storage, LLC | Battery storage (paired with solar) | 150.8 | Dec 2028 | In study |
| Maleza Storage II44220 Julia 345kV | Brush Storage, LLC | Battery storage (stand-alone) | 256.1 | Dec 2028 | In study |
| Neal Batterytap of 138kV 8750 Chalmers - 8127 Lane City · shared with 1 other request | CH Neal Battery LLC | Battery storage (paired with solar) | 120.5 | Apr 2029 | In study |
| Neal Solartap of 138kV 8750 Chalmers - 8127 Lane City · shared with 1 other request | CH Neal Solar LLC | Solar | 146.6 | Apr 2029 | In study |
| Peach Creek Solar44040 Bailey 345 kV · shared with 1 other request | AEUG Peach Creek Solar LLC | Solar | 300.0 | Sep 2029 | In study |
| Zora Solar46650 Athena 138 kV | Zora Solar, LLC | Solar | 250.8 | Oct 2029 | In study |
| Starfield Energy Storage NewTap 138kV 44150 Hungerford - 44190 East Bernard | Starfield Energy Storage, LLC | Battery storage | 122.2 | Dec 2030 | In study |
Crowded connection points in Wharton County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Hillje (44200) 345 kV 9 requests · 2,307 MW · 7 in Wharton County, 2 in Matagorda4 signed; security posted, 3 signed, 1 approved for synchronization, 1 in study
- Danish Fields Solar 20INR0069 · Solar · 603 MW · Approved for synchronization
- Ramsey Storage 21INR0505 · Battery storage · 500 MW · Signed; security posted
- Space City Solar 21INR0341 · Solar · 366 MW · Signed; security posted
- Eldora BESS 24INR0338 · Battery storage · 201 MW · Signed; security posted · Matagorda
- Eldora Solar 24INR0337 · Solar · 201 MW · Signed; security posted · Matagorda
- Malachite BESS 27INR0112 · Battery storage · 191 MW · Signed Dec 2025
- Malachite Solar 27INR0111 · Solar · 185 MW · Signed Dec 2025
- Cernan BESS 27INR0392 · Battery storage · 10 MW · Signed Dec 2025
- Voyager Storage 20INR0238 · Battery storage · 50 MW · In study
South Lane (43190) 138 kV 5 requests · 778 MW3 in study, 2 signed; security posted
- OCI SunRoper 24INR0167 · Solar · 265 MW · Signed; security posted
- Diran BESS 23INR0137 · Battery storage · 103 MW · Signed; security posted
- Cottonseed Energy Storage 27INR0102 · Battery storage · 208 MW · In study
- Hadrian Energy Storage 24INR0569 · Battery storage · 101 MW · In study
- Blue Creek Energy Storage 25INR0545 · Battery storage · 101 MW · In study
Bailey (44040) 345 kV 4 requests · 959 MW2 in study, 1 approved for synchronization, 1 signed
- Lane City Wind 22INR0517 · Wind · 200 MW · Approved for synchronization
- Erin Solar 23INR0058 · Solar · 208 MW · Signed Mar 2023
- Peach Creek Solar 29INR0082 · Solar · 300 MW · In study
- Brela BESS LLC 28INR0030 · Battery storage · 251 MW · In study
East Bernard (44190) 138 kV 3 requests · 459 MW1 approved for synchronization, 1 signed; security posted, 1 in study
- Sbranch Solar 22INR0205 · Solar · 234 MW · Approved for synchronization
- Raven Storage 24INR0210 · Battery storage · 104 MW · Signed; security posted
- Starfield Energy Storage 30INR0133 · Battery storage · 122 MW · In study
WATERH_POI_5 (44880) 345 kV 5 requests · 757 MW3 approved for synchronization, 1 signed, 1 in study
- PHOTON SOLAR 1 2 SLF 25INR0493 · Solar · 236 MW · Approved for synchronization
- PHOTON SOLAR 3 SLF 23INR0111 · Solar · 110 MW · Approved for synchronization
- PHOTON SOLAR 4 SLF 25INR0673 · Solar · 106 MW · Approved for synchronization
- PHOTON SOLAR REPOWERING 26INR0718 · Solar · 0 MW · Signed Feb 2021
- PHOTON BESS REPOWERING 26INR0725 · Battery storage · 305 MW · In study
Dyann (42985) 138 kV 2 requests · 366 MW1 signed; security posted, 1 in study
- OCI SunRoper 24INR0167 · Solar · 265 MW · Signed; security posted
- Blue Creek Energy Storage 25INR0545 · Battery storage · 101 MW · In study
Gulftie (43340) 138 kV 4 requests · 623 MW · 2 in Wharton County, 1 in Matagorda3 in study, 1 approved for synchronization
- TEXAS GULF SULPHUR REPOWER 24INR0605 · Gas turbine · 16 MW · Approved for synchronization
- Boling Generation (TEF-Due Diligience) 24INR0576 · Gas turbine · 400 MW · In study
- Wittig Solar 26INR0144 · Solar · 107 MW · In study
- Pledgor BESS 25INR0405 · Battery storage · 100 MW · In study · Matagorda
Danevang (5546) 138 kV 2 requests · 306 MW1 signed, 1 in study
- TOCE BESS 1 25INR0293 · Battery storage · 205 MW · Signed Dec 2024
- Hynes Bay Energy Storage 25INR0542 · Battery storage · 101 MW · In study
Holman (9073) 345 kV 3 requests · 785 MW · 2 in Wharton County, 1 in Fayette2 signed, 1 in study
- Malachite BESS 27INR0112 · Battery storage · 191 MW · Signed Dec 2025
- Malachite Solar 27INR0111 · Solar · 185 MW · Signed Dec 2025
- Lightcycle Energy Storage 29INR0249 · Battery storage · 410 MW · In study · Fayette
Hungerford (44150) 138 kV 2 requests · 1,158 MW1 signed, 1 in study
- EmberGreen 28INR0090 · Gas turbine · 1,036 MW · Signed Aug 2026
- Starfield Energy Storage 30INR0133 · Battery storage · 122 MW · In study
Chalmers (8750) 138 kV 2 requests · 267 MW2 in study
- Neal Solar 28INR0160 · Solar · 147 MW · In study
- Neal Battery 28INR0452 · Battery storage · 121 MW · In study
Lane City (8127) 138 kV 2 requests · 267 MW2 in study
- Neal Solar 28INR0160 · Solar · 147 MW · In study
- Neal Battery 28INR0452 · Battery storage · 121 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Wharton County
- Wharton County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 12, Houston: 5425 Polk St, Ste H, Houston TX 77023-1452, 713-767-3500; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Wharton County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Wharton County.
Permits and reviews for Wharton County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Wharton County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Wharton County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.
How a project in Wharton County connects to the grid
Wharton County is on the ERCOT grid. The projects listed above are in ERCOT's South load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Wharton County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Wharton County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 12
Austin · Brazoria · Chambers · Colorado · Fort Bend · Galveston · Harris · Liberty · Matagorda · Montgomery · Walker · Waller