Home › Texas › Glasscock County
Glasscock County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
15 proposed energy projects from ERCOT's September 2026 report, plus who to call in Glasscock County and in TCEQ Region 7 before signing a solar, wind, or battery storage lease.
Check land in Glasscock CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Glasscock County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Glasscock County?
ERCOT's September 2026 interconnection report lists 15 proposed energy projects in Glasscock County (3 solar, 4 wind, 7 battery storage and 1 gas), about 3,265 MW in all. 8 of the 15 have a signed interconnection agreement, and 2 have been approved for energization or synchronization. The table also lists 3 changes to existing plants (repowers or capacity changes), not counted above.
What stands out in Glasscock County
By capacity, solar leads in Glasscock County with 1,059 MW across 3 projects, followed by battery storage (7 projects, 1,007 MW) and wind (4 projects, 829 MW); 1 self-limiting project (reported at 0 MW because the resource limits its own output) is listed without a capacity. The largest single project is Proteus London-Leigh Solar SLF, a 600 MW solar project listed under London Leigh Solar, LLC, still in study, and its target online date is Sep 2028. Of the 15, 7 are still in ERCOT's study process, 6 have posted security or started construction and 2 are approved for energization or synchronization. Connection points are mostly at 345 kV (10 projects) and 138 kV (3 projects) (why the voltage matters). RWE Clean Energy Development, LLC is listed on the most projects here (3 of 15); 11 different companies appear in all. Target online dates for the projects not yet running span Jul 2027 to Sep 2029. All of them fall in ERCOT's West load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Harald (BearKat Wind B)59903 Bearkat 345kV | McCrae Wind Energy II, LLC | Wind | 162.1 | Dec 2026 | Approved for synchronization |
| Honey Mesquite Wind Farm59902 Sand Bluff 345kV · shared with 2 other requests | Honey Mesquite Wind Farm , LLC | Wind | 173.9 | Dec 2026 | Approved for synchronization |
| Forest Creek Wind RepowerMcdonald 138 kV (Bus #: 1333) | Forest Creek Wind Farm, LLC | Wind | 125.1 | Dec 2026 | Approved for synchronization |
| Panther Creek 1 Repower1058 Longshore 345kV · shared with 2 other requests | Panther Creek Wind Farm I&II, LLC | Wind | 11.0 | Dec 2026 | Approved for synchronization |
| Panther Creek 2 RepowerLongshore 345kV [Bus# 1058] | Panther Creek Wind Farm I&II, LLC | Wind | 8.0 | Dec 2026 | Approved for synchronization |
| Champaign BESSTap 138kV Shaw POD (18664) – Desert Wind Sub (11283) | Champaign BESS, LLC | Battery storage (stand-alone) | 201.1 | Mar 2028 | Signed; security posted |
| Cannibal Draw SolarSand_Bluff 345 kV (59902) · shared with 1 other request | Cannibal Draw Solar, LLC | Solar | 149.5 | Apr 2028 | Signed; security posted |
| Cannibal Draw StorageSand_Bluff 345 kV (59902) · shared with 1 other request | Cannibal Draw Solar, LLC | Battery storage (paired with solar) | 98.6 | Apr 2028 | Signed; security posted |
| Gardner Draw Solar59902 Sand Bluff 345kV · shared with 2 other requests | RWE Clean Energy Development, LLC | Solar | 309.5 | Jun 2028 | Signed; security posted |
| Gusty WindpowerTap 345kV 59903 Bearkat - 1058 Longshore_5; Anemone 345 kV Station | Gusty Windpower, LLC | Wind | 248.9 | Dec 2028 | Signed; security posted |
| Windjammer Windpowertap 345kV 59902 Sand Bluff Wind Farm - 59907 Bernoulli | Windjammer Windpower, LLC | Wind | 244.1 | Dec 2028 | Signed; security posted |
| Feather Dalea BESS59902 Sand_Bluff 345kV · shared with 1 other request | RWE Clean Energy Development, LLC | Battery storage (stand-alone) | 200.0 | Jul 2027 | In study |
| Sagewood BESStap McDonald Road Switch (1333) – Pastores Switch (10121) ckt 1 | Sagewood BESS, LLC | Battery storage (stand-alone) | 100.6 | Mar 2028 | In study |
| Cummins BESS1333 MCDONALD 138kV | RWE Solar Development, LLC | Battery storage (stand-alone) | 200.9 | Jun 2028 | In study |
| Proteus London-Leigh Solar SLF345kV Bernoulli (bus # 59907) | London Leigh Solar, LLC | Solar | 600.0 | Sep 2028 | In study |
| Proteus London-Leigh Storage SLFBernoulli (bus # 59907) | London Leigh Solar, LLC | Battery storage (paired with solar) | Self-limiting | Sep 2028 | In study |
| Indigo Quill Gas59902 SAND_BLUFF 345KV · shared with 1 other request | RWE Clean Energy Development, LLC | Gas turbine | 370.1 | Dec 2028 | In study |
| Pleiades StorageTap 138kV Einstein 23852 - 10043 St. Lawrence | Pleiades Storage, LLC | Battery storage (stand-alone) | 205.5 | Sep 2029 | In study |
Crowded connection points in Glasscock County
Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.
Sand Bluff (59902) 345 kV 10 requests · 2,197 MW · 7 in Glasscock County, 3 in Sterling5 signed; security posted, 4 in study, 1 approved for synchronization
- Honey Mesquite Wind Farm 26INR0447 · Wind · 174 MW · Approved for synchronization
- Gardner Draw Solar 27INR0355 · Solar · 310 MW · Signed; security posted
- Windjammer Windpower 27INR0383 · Wind · 244 MW · Signed; security posted
- Bob Creek Wind 27INR0076 · Wind · 239 MW · Signed; security posted · Sterling
- Cannibal Draw Solar 26INR0452 · Solar · 150 MW · Signed; security posted
- Cannibal Draw Storage 26INR0453 · Battery storage · 99 MW · Signed; security posted
- Indigo Quill Gas 30INR0080 · Gas turbine · 370 MW · In study
- Roan Solar Phase 1 29INR0185 · Solar · 206 MW · In study · Sterling
- Roan Solar Phase 2 29INR0187 · Solar · 206 MW · In study · Sterling
- Feather Dalea BESS 27INR0371 · Battery storage · 200 MW · In study
Bernoulli (59907) 345 kV 3 requests · 844 MW2 in study, 1 signed; security posted
- Windjammer Windpower 27INR0383 · Wind · 244 MW · Signed; security posted
- Proteus London-Leigh Solar SLF 25INR0608 · Solar · 600 MW · In study
- Proteus London-Leigh Storage SLF 25INR0609 · Battery storage · 0 MW · In study
Bearkat (59903) 345 kV 7 requests · 1,721 MW · 2 in Glasscock County, 5 in Upton, Reagan4 in study, 1 approved for synchronization, 1 signed; security posted, 1 signed
- Harald (BearKat Wind B) 15INR0064b · Wind · 162 MW · Approved for synchronization
- Gusty Windpower 29INR0040 · Wind · 249 MW · Signed; security posted
- Slager Lake Wind 29INR0042 · Wind · 310 MW · Signed Dec 2025 · Reagan
- Vista Bluff Wind I "Alternate POI" 28INR0446 · Wind · 290 MW · In study · Upton
- Vista Bluff Wind II "Alternate POI" 28INR0447 · Wind · 290 MW · In study · Upton
- Badger Solar 28INR0212 · Solar · 280 MW · In study · Upton
- Badger BESS 28INR0213 · Battery storage · 139 MW · In study · Upton
Mcdonald (1333) 138 kV 3 requests · 427 MW2 in study, 1 approved for synchronization
- Forest Creek Wind Repower 25INR0578 · Wind · 125 MW · Approved for synchronization
- Cummins BESS 26INR0573 · Battery storage · 201 MW · In study
- Sagewood BESS 25INR0142 · Battery storage · 101 MW · In study
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Glasscock County
- Glasscock County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 7, Midland: 10 Desta Dr, Ste 350E, Midland TX 79705-4530, 432-570-1359; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Glasscock County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Glasscock County.
Permits and reviews for Glasscock County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Glasscock County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
Local action: as of October 17, 2026, we found no 2024–2026 commissioners court action on solar, wind, or battery storage posted on Glasscock County's website or reported by local news. Counties act mostly through tax abatement and road use agreements, so ask the county judge's office whether any are pending.
How a project in Glasscock County connects to the grid
Glasscock County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Glasscock County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Glasscock County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.