Midland County, Texas: solar, wind, and storage projects and permits
Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month
6 proposed energy projects from ERCOT's September 2026 report, plus who to call in Midland County and in TCEQ Region 7 before signing a solar, wind, or battery storage lease.
Check land in Midland CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
Power reliability here: minutes without power per year, outages per year, and outage length for Midland County, 2013–2024, from the serving utilities' EIA filings.
What energy projects are proposed in Midland County?
ERCOT's September 2026 interconnection report lists 6 proposed energy projects in Midland County (2 solar, 3 battery storage and 1 gas), about 854 MW in all. 2 of the 6 have a signed interconnection agreement, and 1 has been approved for energization or synchronization. The table also lists 1 change to existing plants (repowers or capacity changes), not counted above.
What stands out in Midland County
By capacity, battery storage leads in Midland County with 610 MW across 3 projects, followed by solar (2 projects, 134 MW) and gas (1 project, 110 MW). The largest single project is Energy City BESS, a 205 MW stand-alone battery storage project listed under Energy City BESS LLC, still in study, and its target online date is May 2029. Of the 6, 4 are still in ERCOT's study process, 1 has posted security or started construction and 1 is approved for energization or synchronization. Connection points are mostly at 138 kV (4 projects) and 345 kV (2 projects) (why the voltage matters). Each of the 6 projects is listed under a different company. Target online dates for the projects not yet running span Jul 2028 to May 2029. All of them fall in ERCOT's West load zone.
A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.
Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.
Scroll the table sideways to see every column.
| Project and connection point | Developer as listed by ERCOT | Type | MW | Target online date iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date. | Stage |
|---|---|---|---|---|---|
| Holzer Solar11165 Sloan Switch 138kV | Greater Bryant G Solar, LLC | Solar | 17.7 | Nov 2026 | Approved for synchronization |
| Jasper BESSTap 138kV 71230 Pleasant Farms - 1236 Pegasus South | Jasper BESS, LLC | Battery storage (stand-alone) | 201.1 | Oct 2028 | Signed; security posted |
| Pioneer Hutt Solar (Alternative POI)TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C) | NextEra Energy Interconnection Holdings LLC | Solar | 116.0 | Jul 2028 | In study |
| Electric E - West Texas Generation 2#18664 SHAWPD 138kV | Electric E Power Marketing | Gas turbine | 0 no capacity change | Sep 2028 | In study |
| Drill Baby Drill BESS23859 SALTFLAT 138KV | SBESS TX8 LLC | Battery storage (stand-alone) | 204.3 | Oct 2028 | In study |
| Flurry Gas 1Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) – Midla... | NET Power Canaveral LLC | Gas combined cycle | 109.8 | Apr 2029 | In study |
| Energy City BESSTap 138kV AQUEDUCT SUB(#1172) - Mockingbird North Tap(#11299) | Energy City BESS LLC | Battery storage (stand-alone) | 204.9 | May 2029 | In study |
What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.
Who to contact in Midland County
- Midland County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
- TCEQ Region 7, Midland: 10 Desta Dr, Ste 350E, Midland TX 79705-4530, 432-570-1359; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
- Midland County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
- Flood maps: FEMA map search for Midland County.
Permits and reviews for Midland County
Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Midland County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.
How a project in Midland County connects to the grid
Midland County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.
How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.
Solar for homes and businesses in Midland County
Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.
Get the land report for a spot in Midland County
Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.
Other counties served by TCEQ Region 7
Andrews · Borden · Crane · Dawson · Ector · Gaines · Glasscock · Howard · Loving · Martin · Pecos · Reeves · Terrell · Upton · Ward · Winkler