Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Lampasas County

Lampasas County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects10
Total capacity1,742MW
Signed agreements2of 10
New since August0requests

10 proposed energy projects from ERCOT's September 2026 report, plus who to call in Lampasas County and in TCEQ Region 9 before signing a solar, wind, or battery storage lease.

Check land in Lampasas CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Lampasas County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Lampasas County?

ERCOT's September 2026 interconnection report lists 10 proposed energy projects in Lampasas County (5 solar and 5 battery storage), about 1,742 MW in all. 2 of the 10 have a signed interconnection agreement.

What stands out in Lampasas County

By capacity, battery storage leads in Lampasas County with 906 MW across 5 projects, followed by solar (5 projects, 836 MW). The largest single project is Barkley Creek Solar, a 312 MW solar project listed under 174 Power Global Properties, LLC, still in study, and its target online date is Oct 2029. Of the 10, 8 are still in ERCOT's study process and 2 have posted security or started construction. Connection points are mostly at 138 kV (7 projects) and 345 kV (3 projects) (why the voltage matters). Lampasas Hybrid Energy LLC is listed on the most projects here (2 of 10); 9 different companies appear in all. Target online dates for the projects not yet running span Jan 2028 to Oct 2029. All of them fall in ERCOT's North load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Seven Springs SolarTap 7061 COPPERAS COVE 7260 Kempner 138kVHancock Springs, LLCSolar145.0May 2028Signed; security posted
Thomas Cameron BESSTap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCHThomas Cameron BESS LLCBattery storage (stand-alone)205.5Apr 2029Signed; security posted
GIBSON BRANCH BESS7064 Lampasas Substation 138kVGibson Branch BESS LLCBattery storage (stand-alone)142.9Jan 2028In study
Hana Springs BESS7064 LAMPASAS 138KVBlack Mountain Energy Storage II LLCBattery storage (stand-alone)100.8May 2028In study
Triple B Solar Alt#2Tap 138kV 7066 Adamsville - 7064 LampasasTriple B Solar LLCSolar150.0Jul 2028In study
Aurora Energy StorageTap 345kV --- KILL_SS_5 (3422) --- BUCK_H_5 (3424)Aurora Energy Storage, LLCBattery storage (stand-alone)306.2Sep 2028In study
Senterfitt SolarTap 138 kV 7080 Lometa - 7064 LampasasAETS Development Holdings LLCSolar68.4Jul 2029In study
Solgen Solar7066 Adamsville 138kV · shared with 1 other requestLampasas Hybrid Energy LLCSolar160.2Aug 2029In study
Solgen Storage7066 Adamsville 138kV · shared with 1 other requestLampasas Hybrid Energy LLCBattery storage (paired with solar)150.3Aug 2029In study
Barkley Creek SolarTap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch...174 Power Global Properties, LLCSolar312.4Oct 2029In study

Crowded connection points in Lampasas County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Lampasas (7064) 138 kV 4 requests · 462 MW4 in study
  • Triple B Solar Alt#2 24INR0069 · Solar · 150 MW · In study
  • GIBSON BRANCH BESS 25INR0666 · Battery storage · 143 MW · In study
  • Hana Springs BESS 24INR0494 · Battery storage · 101 MW · In study
  • Senterfitt Solar 28INR0462 · Solar · 68 MW · In study
Adamsville (7066) 138 kV 3 requests · 460 MW3 in study
  • Solgen Solar 30INR0037 · Solar · 160 MW · In study
  • Solgen Storage 30INR0038 · Battery storage · 150 MW · In study
  • Triple B Solar Alt#2 24INR0069 · Solar · 150 MW · In study
Killeen (3422) 345 kV 4 requests · 1,126 MW · 3 in Lampasas County, 1 in Mills2 in study, 1 approved for synchronization, 1 signed; security posted
  • Priddy Wind 16INR0085 · Wind · 302 MW · Approved for synchronization · Mills
  • Thomas Cameron BESS 24INR0543 · Battery storage · 206 MW · Signed; security posted
  • Barkley Creek Solar 28INR0324 · Solar · 312 MW · In study
  • Aurora Energy Storage 28INR0277 · Battery storage · 306 MW · In study
Buckhorn (3424) 345 kV 6 requests · 1,219 MW · 2 in Lampasas County, 4 in Brown, Mills3 signed; security posted, 3 in study
  • Thomas Cameron BESS 24INR0543 · Battery storage · 206 MW · Signed; security posted
  • Chisme Storage 24INR0331 · Battery storage · 151 MW · Signed; security posted · Brown
  • Chisme Solar 24INR0333 · Solar · 147 MW · Signed; security posted · Brown
  • Aurora Energy Storage 28INR0277 · Battery storage · 306 MW · In study
  • Clapton Storage 26INR0430 · Battery storage · 209 MW · In study · Mills
  • Clapton Solar 26INR0238 · Solar · 201 MW · In study · Mills

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Lampasas County

  • Lampasas County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 9, Waco: 6801 Sanger Ave, Ste 2500, Waco TX 76710-7826, 254-751-0335; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Lampasas County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Lampasas County.

Permits and reviews for Lampasas County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Lampasas County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Lampasas County connects to the grid

Lampasas County is on the ERCOT grid. The projects listed above are in ERCOT's North load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Lampasas County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Lampasas County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 9

Bell · Bosque · Brazos · Burleson · Coryell · Falls · Freestone · Grimes · Hamilton · Hill · Leon · Limestone · Madison · McLennan · Milam · Mills · Robertson · San Saba · Washington

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.