Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Texas › Tom Green County

Tom Green County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects13
Total capacity3,010MW
Signed agreements1of 13
New since August0requests

13 proposed energy projects from ERCOT's September 2026 report, plus who to call in Tom Green County and in TCEQ Region 8 before signing a solar, wind, or battery storage lease.

Check land in Tom Green CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Tom Green County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Tom Green County?

ERCOT's September 2026 interconnection report lists 13 proposed energy projects in Tom Green County (5 solar, 2 wind and 6 battery storage), about 3,010 MW in all. 1 of the 13 has a signed interconnection agreement.

What stands out in Tom Green County

By capacity, solar leads in Tom Green County with 1,291 MW across 5 projects, followed by battery storage (6 projects, 1,160 MW) and wind (2 projects, 559 MW). The largest single project is Moon Chapel Solar, a 402 MW solar project listed under Orsted Onshore Development North America, LLC, still in study, and its target online date is Dec 2029. Of the 13, 12 are still in ERCOT's study process and 1 has posted security or started construction. Connection points are mostly at 345 kV (8 projects) and 138 kV (4 projects) (why the voltage matters). Lightsource Renewable Energy Development LLC is listed on the most projects here (4 of 13); 8 different companies appear in all. Target online dates for the projects not yet running span Dec 2027 to Dec 2029. All of them fall in ERCOT's West load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Water Valley Wind Energy345 kV 76009 Twin Buttes to 76090 Divide Double CircuitWater Valley Wind Energy, LLCWind180.0Dec 2027Signed; security posted
Zeppelin Energy Storage6464 San Angelo NorthZEPPELIN ENERGY STORAGE LLCBattery storage (stand-alone)163.9May 2028In study
Dove Creek SolarTap at Big Hill - Twin Buttes 345 kV line (76003 / 76009) · shared with 1 other requestDove Creek Solar, LLCSolar163.6Jul 2028In study
Dove Creek StorageTap at Big Hill - Twin Buttes 345 kV line (76003 / 76009) · shared with 1 other requestDove Creek Solar, LLCBattery storage (paired with solar)162.5Jul 2028In study
Hofbrau BESS6442 Redcreek 138kVMomentum Hofbrau LLCBattery storage (stand-alone)180.7Jul 2028In study
Moon Chapel WindTap 345kV 76090 Divide - 76009 Twin Buttes Ckt 1Orsted Onshore Development North America, LLCWind379.2Oct 2028In study
Morning Glory Solartap 345kV 7077 Amos Creek - 76009 Twin ButtesArmadillo Solar, LLCSolar122.4Nov 2028In study
Fort Concho Energy storageTap 138 kV #76320 Schkade - #76011 Twin Buttes Line; LCRARocky Mountain Energy Development, LLCBattery storage (stand-alone)251.2Dec 2028In study
Silver Sky BESS6444 Red Creek 345kV · shared with 1 other requestLightsource Renewable Energy Development LLCBattery storage (paired with solar)201.1Dec 2029In study
Silver Sky Solar6444 Red Creek 345kV · shared with 1 other requestLightsource Renewable Energy Development LLCSolar401.9Dec 2029In study
Tango Lily SolarTap 138kV 60008 TRIBUTE4A - 6442 REDCREEK4A · shared with 1 other requestLightsource Renewable Energy Development LLCSolar200.9Dec 2029In study
Tango Lily BESSTap 138kV 60008 TRIBUTE4A - 6442 REDCREEK4A · shared with 1 other requestLightsource Renewable Energy Development LLCBattery storage (paired with solar)200.9Dec 2029In study
Moon Chapel SolarTap 345kV 76090 Divide – 76009 Twin Buttes Ckt 1Orsted Onshore Development North America, LLCSolar402.0Dec 2029In study

Crowded connection points in Tom Green County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Twin Buttes (76009) 345 kV 11 requests · 2,620 MW · 6 in Tom Green County, 5 in Concho, Schleicher, Coke6 in study, 4 signed, 1 signed; security posted
  • Water Valley Wind Energy 20INR0247 · Wind · 180 MW · Signed; security posted
  • Cold Creek Solar 2 26INR0290 · Solar · 432 MW · Signed Apr 2025 · Schleicher
  • Concho Pearl Solar 25INR0174 · Solar · 172 MW · Signed Jul 2024 · Concho
  • Cold Creek Storage 2 26INR0291 · Battery storage · 172 MW · Signed Apr 2025 · Schleicher
  • Concho Pearl Storage 25INR0175 · Battery storage · 162 MW · Signed Jul 2024 · Concho
  • Moon Chapel Solar 29INR0328 · Solar · 402 MW · In study
  • Moon Chapel Wind 27INR0445 · Wind · 379 MW · In study
  • Roboman Solar 27INR0453 · Solar · 273 MW · In study · Coke
  • Dove Creek Solar 26INR0454 · Solar · 164 MW · In study
  • Dove Creek Storage 26INR0455 · Battery storage · 162 MW · In study
  • Morning Glory Solar 23INR0224 · Solar · 122 MW · In study
Divide (76090) 345 kV 7 requests · 1,866 MW · 3 in Tom Green County, 4 in Coke, Sterling6 in study, 1 signed; security posted
  • Water Valley Wind Energy 20INR0247 · Wind · 180 MW · Signed; security posted
  • Moon Chapel Solar 29INR0328 · Solar · 402 MW · In study
  • Moon Chapel Wind 27INR0445 · Wind · 379 MW · In study
  • Roboman Solar 27INR0453 · Solar · 273 MW · In study · Coke
  • Coke BESS 28INR0155 · Battery storage · 220 MW · In study · Coke
  • Roan Solar Phase 1 29INR0185 · Solar · 206 MW · In study · Sterling
  • Roan Solar Phase 2 29INR0187 · Solar · 206 MW · In study · Sterling
REDCREEK4A (6442) 138 kV 3 requests · 583 MW3 in study
  • Tango Lily BESS 25INR0853 · Battery storage · 201 MW · In study
  • Tango Lily Solar 29INR0231 · Solar · 201 MW · In study
  • Hofbrau BESS 23INR0312 · Battery storage · 181 MW · In study
TRIBUTE4A (60008) 138 kV 2 requests · 402 MW2 in study
  • Tango Lily BESS 25INR0853 · Battery storage · 201 MW · In study
  • Tango Lily Solar 29INR0231 · Solar · 201 MW · In study
Big Hill (76003) 345 kV 8 requests · 1,880 MW · 2 in Tom Green County, 6 in Schleicher5 in study, 2 signed, 1 signed; security posted
  • Rockefeller Storage 22INR0239 · Battery storage · 207 MW · Signed; security posted · Schleicher
  • Cold Creek Solar 2 26INR0290 · Solar · 432 MW · Signed Apr 2025 · Schleicher
  • Cold Creek Storage 2 26INR0291 · Battery storage · 172 MW · Signed Apr 2025 · Schleicher
  • Live Oak Wind II 28INR0280 · Wind · 303 MW · In study · Schleicher
  • Easy Wind Energy Center 27INR0246 · Wind · 241 MW · In study · Schleicher
  • Easy Battery Energy Storage Center 27INR0231 · Battery storage · 200 MW · In study · Schleicher
  • Dove Creek Solar 26INR0454 · Solar · 164 MW · In study
  • Dove Creek Storage 26INR0455 · Battery storage · 162 MW · In study
Red Creek (6444) 345 kV 5 requests · 1,390 MW · 2 in Tom Green County, 3 in Concho4 in study, 1 signed; security posted
  • Lucy Solar 25INR0225 · Solar · 352 MW · Signed; security posted · Concho
  • Silver Sky Solar 29INR0365 · Solar · 402 MW · In study
  • Trail Ranch Solar 1 29INR0139 · Solar · 302 MW · In study · Concho
  • Silver Sky BESS 29INR0376 · Battery storage · 201 MW · In study
  • Trail Ranch Solar 2 29INR0272 · Solar · 133 MW · In study · Concho

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Tom Green County

  • Tom Green County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 8, San Angelo: 622 S Oakes, Ste K, San Angelo TX 76903-7035, 325-655-9479; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Tom Green County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Tom Green County.

Permits and reviews for Tom Green County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Tom Green County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Tom Green County connects to the grid

Tom Green County is on the ERCOT grid. The projects listed above are in ERCOT's West load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Tom Green County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Tom Green County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 8

Coke · Concho · Crockett · Irion · Kimble · Mason · McCulloch · Menard · Reagan · Schleicher · Sterling · Sutton

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.

Browse resources