The quick find: which office handles each approval a utility-scale project touches in Wisconsin, with the agency's own page. Counties and cities add their own land-use approvals; the state table is the part that is the same across the state.

State and grid

ApprovalWhere to go
State siting or certificateWhether the state itself approves where a generating facility goes, or leaves it to counties and cities.How Construction Projects Are Reviewed (CPCN for generation 100 MW+; Certificate of Authority)Public Service Commission of WisconsinConfirmed live; page renamed 'How Construction Projects Are Reviewed' and describes CA and CPCN thresholds (100 MW generation, 100 kV lines).
Grid interconnectionThe queue the project enters to connect: the regional grid operator, or the utility and public utility commission outside an RTO.MISO generator interconnectionMidcontinent ISO
Construction stormwater permitNPDES coverage for land disturbance of one acre or more, before earthwork starts.Construction site storm water permit overview (WPDES)Wisconsin Department of Natural ResourcesConfirmed; NOI for coverage under the Construction Site Storm Water Runoff General Permit. Parent: https://dnr.wisconsin.gov/topic/Stormwater/construction
Historic preservation reviewSection 106 consultation through the State Historic Preservation Office when a federal permit, federal funding or federal land is involved; many states add their own review on state land.Compliance review (Section 106 and Wis. Stat. 44.40) not script-checkableWisconsin Historical Society, State Historic Preservation Office · the agency's site blocks automated checks, so the link is as researched, not machine-confirmed
Wildlife and habitat reviewThe state wildlife agency's project screening or natural-heritage data request; federal species go through USFWS IPaC.Endangered resources reviewWisconsin DNR Endangered Resources Review
State road access and utility permitsA driveway onto a state highway, and a gen-tie or cable in state right of way.Access and utility permitsWisconsin Department of Transportation
Floodplain (state NFIP coordinator)Local floodplain development permits are county or city; the state coordinator lists who administers them.State NFIP coordinatorWisconsin DNR Floodplain Management
Water rights and wellsConstruction water, dust control and O&M wells: the state engineer, water board or environmental agency.Water use permits and high-capacity wellsWisconsin DNR Water Use Program
Property-tax incentive programState abatement or exemption programs for renewable generation, where one exists.Renewable Energy Systems: Biogas, Solar & Wind - Property Tax ExemptionWisconsin Department of RevenueAgency FAQ (PDF/print of DOR page, last updated 2014) replacing the slf-solar.aspx FAQ; states solar and wind energy systems are exempt from general property tax. Statute cite 70.111(18) not shown on page.

Federal portals (the same in every state)

ApprovalWhere to go
Clean Water Act Section 404 / Rivers and Harbors Act Section 10U.S. Army Corps of EngineersRegulatory Request System: applications, pre-application meetings and jurisdictional determinations; the district office is by watershed.
Endangered species and critical habitatU.S. Fish and Wildlife ServiceIPaC: official species list and the Section 7 consultation path for the project footprint.
Tall structures (wind turbines, met towers)Federal Aviation AdministrationForm 7460-1 notice through OE/AAA before construction above the 14 CFR 77.9 heights.
Construction stormwater where EPA is the permitting authorityU.S. EPAEPA's Construction General Permit (NeT eNOI) in New Mexico, Massachusetts, New Hampshire, D.C., Indian country and the territories.
Projects on federal landBureau of Land ManagementRight-of-way applications and NEPA documents for BLM-managed land.
Transmission and wholesale market rulesFederal Energy Regulatory CommissionOrder No. 2023 cluster-study reforms, followed by every FERC-jurisdictional transmission provider, RTO or utility; ERCOT has its own process.

County and city pages for Wisconsin

From the nationwide permit finder; counties and cities issue most land-use approvals, so start with the jurisdiction that covers the parcel.

Other states

How this list is made. Each link was found on the agency's own site and is re-checked by a script that loads it and records the date; a link that stops answering is shown without a link rather than dropped. Programs change with each legislative session: confirm fees, forms and thresholds on the agency page before filing. General information, not legal advice. How we check our data · Report an error.