Missouri: every permit portal for solar, wind, and storage

Links checked October 24, 2026 · Official sites only · Pick another state

The quick find: which office handles each approval a utility-scale project touches in Missouri, with the agency's own page. Counties and cities add their own land-use approvals; the state table is the part that is the same across the state.

State and grid

ApprovalWhere to go
State siting or certificateWhether the state itself approves where a generating facility goes, or leaves it to counties and cities.No state siting permit for merchant solar; county governsMissouri Public Service CommissionSB 745 (2022) addressed solar property tax; counties use CUPs.
Grid interconnectionThe queue the project enters to connect: the regional grid operator, or the utility and public utility commission outside an RTO.MISO Generator InterconnectionMidcontinent Independent System Operator (MISO)MISO serves the Ameren Missouri footprint covering most of the state's load; western Missouri (Evergy) is in SPP.
Construction stormwater permitNPDES coverage for land disturbance of one acre or more, before earthwork starts.Construction or Land Disturbance Master General Stormwater Permit MORA00000 not script-checkableMissouri Department of Natural Resources · the agency's site blocks automated checks, so the link is as researched, not machine-confirmedPermit page confirmed (covers land disturbance >= 1 acre, fees, timelines). Related area-wide permit MOR100000 at https://dnr.mo.gov/water/area-wide-land-disturbance-master-general-stormwater-permit-mor100000.
Historic preservation reviewSection 106 consultation through the State Historic Preservation Office when a federal permit, federal funding or federal land is involved; many states add their own review on state land.Section 106 ReviewMissouri State Historic Preservation OfficePage confirmed: 'Section 106 Review | Missouri State Parks', with Missouri submission instructions (MOSection106@dnr.mo.gov).
Wildlife and habitat reviewThe state wildlife agency's project screening or natural-heritage data request; federal species go through USFWS IPaC.Missouri Natural Heritage Program / Natural Heritage ReviewMissouri Department of Conservation, Natural Heritage Review ProgramProgram page confirmed; links the review request portal https://naturalheritagereview.mdc.mo.gov/ (also confirmed live).
State road access and utility permitsA driveway onto a state highway, and a gen-tie or cable in state right of way.EPG 941 Permits and Access Requests (entrance/driveway and utility permits)Missouri Department of TransportationConfirmed live; MoDOT Engineering Policy Guide section on permits and access requests (driveways, utility permits on right of way). modot.org/access-management is gone; this is the closest agency page found.
Floodplain (state NFIP coordinator)Local floodplain development permits are county or city; the state coordinator lists who administers them.Missouri Floodplain Management / NFIP (State NFIP Coordinator)Missouri State Emergency Management Agency, Floodplain ManagementPage confirmed: 'Missouri Floodplain Management/Floodplain Insurance Programs | SEMA'; lists State NFIP Coordinator contact.
Water rights and wellsConstruction water, dust control and O&M wells: the state engineer, water board or environmental agency.Major water user registration / Water Use Reporting (PUB2221)Missouri DNR Water Resources Center
Property-tax incentive programState abatement or exemption programs for renewable generation, where one exists.Solar property assessment (Section 137.123 RSMo, 2022)Missouri State Tax Commission

Federal portals (the same in every state)

ApprovalWhere to go
Clean Water Act Section 404 / Rivers and Harbors Act Section 10U.S. Army Corps of EngineersRegulatory Request System: applications, pre-application meetings and jurisdictional determinations; the district office is by watershed.
Endangered species and critical habitatU.S. Fish and Wildlife ServiceIPaC: official species list and the Section 7 consultation path for the project footprint.
Tall structures (wind turbines, met towers)Federal Aviation AdministrationForm 7460-1 notice through OE/AAA before construction above the 14 CFR 77.9 heights.
Construction stormwater where EPA is the permitting authorityU.S. EPAEPA's Construction General Permit (NeT eNOI) in New Mexico, Massachusetts, New Hampshire, D.C., Indian country and the territories.
Projects on federal landBureau of Land ManagementRight-of-way applications and NEPA documents for BLM-managed land.
Transmission and wholesale market rulesFederal Energy Regulatory CommissionOrder No. 2023 cluster-study reforms, followed by every FERC-jurisdictional transmission provider, RTO or utility; ERCOT has its own process.

County and city pages for Missouri

From the nationwide permit finder; counties and cities issue most land-use approvals, so start with the jurisdiction that covers the parcel.

Other states

How this list is made. Each link was found on the agency's own site and is re-checked by a script that loads it and records the date; a link that stops answering is shown without a link rather than dropped. Programs change with each legislative session: confirm fees, forms and thresholds on the agency page before filing. General information, not legal advice. How we check our data · Report an error.