Utah: every permit portal for solar, wind, and storage

Links checked October 24, 2026 · Official sites only · Pick another state

The quick find: which office handles each approval a utility-scale project touches in Utah, with the agency's own page. Counties and cities add their own land-use approvals; the state table is the part that is the same across the state.

State and grid

ApprovalWhere to go
State siting or certificateWhether the state itself approves where a generating facility goes, or leaves it to counties and cities.No state siting permit; county conditional use permitsUtah county governments
Grid interconnectionThe queue the project enters to connect: the regional grid operator, or the utility and public utility commission outside an RTO.PacifiCorp (Rocky Mountain Power; non-RTO) exact page not confirmedLook for: Generator interconnection · the exact page did not answer our check, so this goes to the agency's site
Construction stormwater permitNPDES coverage for land disturbance of one acre or more, before earthwork starts.Construction Storm Water Permit (UPDES)Utah Division of Water QualityConfirmed program page; 'Utah requires an UPDES construction storm water permit for soil disturbances of an acre or more.'
Historic preservation reviewSection 106 consultation through the State Historic Preservation Office when a federal permit, federal funding or federal land is involved; many states add their own review on state land.SHPO ComplianceUtah State Historic Preservation OfficeSection 106 and state compliance review submissions to the Utah SHPO.
Wildlife and habitat reviewThe state wildlife agency's project screening or natural-heritage data request; federal species go through USFWS IPaC.Utah Division of Wildlife Resources exact page not confirmedLook for: Wildlife Habitat Analysis Tool (project-planning wildlife review for developers) · the exact page did not answer our check, so this goes to the agency's siteConfirmed live. DWR no longer has a standalone 'environmental review' page; the WHAT tool (launched 2024) is what DWR directs developers to for habitat reports and regional biologist contacts. Natural Heritage Program page: https://wildlife.utah.gov/naturalheritage
State road access and utility permitsA driveway onto a state highway, and a gen-tie or cable in state right of way.Access Management (Conditional Access Permit)Utah Department of TransportationUDOT access/driveway permits for connections to state highways.
Floodplain (state NFIP coordinator)Local floodplain development permits are county or city; the state coordinator lists who administers them.Utah Flood Hazards (NFIP)Utah Division of Emergency ManagementUtah DEM's NFIP state coordinating office site; search surfaced subpages of this dedicated program site.
Water rights and wellsConstruction water, dust control and O&M wells: the state engineer, water board or environmental agency.Division of Water RightsUtah Division of Water RightsState Engineer water right applications, temporary change/appropriation forms and well drilling permits; only forms/documents on this site surfaced in search.
Property-tax incentive programState abatement or exemption programs for renewable generation, where one exists.Centrally assessed property; alternative energy development incentivesUtah State Tax Commission

Federal portals (the same in every state)

ApprovalWhere to go
Clean Water Act Section 404 / Rivers and Harbors Act Section 10U.S. Army Corps of EngineersRegulatory Request System: applications, pre-application meetings and jurisdictional determinations; the district office is by watershed.
Endangered species and critical habitatU.S. Fish and Wildlife ServiceIPaC: official species list and the Section 7 consultation path for the project footprint.
Tall structures (wind turbines, met towers)Federal Aviation AdministrationForm 7460-1 notice through OE/AAA before construction above the 14 CFR 77.9 heights.
Construction stormwater where EPA is the permitting authorityU.S. EPAEPA's Construction General Permit (NeT eNOI) in New Mexico, Massachusetts, New Hampshire, D.C., Indian country and the territories.
Projects on federal landBureau of Land ManagementRight-of-way applications and NEPA documents for BLM-managed land.
Transmission and wholesale market rulesFederal Energy Regulatory CommissionOrder No. 2023 cluster-study reforms, followed by every FERC-jurisdictional transmission provider, RTO or utility; ERCOT has its own process.

County and city pages for Utah

From the nationwide permit finder; counties and cities issue most land-use approvals, so start with the jurisdiction that covers the parcel.

Other states

How this list is made. Each link was found on the agency's own site and is re-checked by a script that loads it and records the date; a link that stops answering is shown without a link rather than dropped. Programs change with each legislative session: confirm fees, forms and thresholds on the agency page before filing. General information, not legal advice. How we check our data · Report an error.