Gray County, Texas: solar, wind, and storage projects and permits

Queue data as of ERCOT's September 2026 GIS report · Contacts checked 2026-09-26 · Next update early next month

Proposed projects3
Total capacity2,121MW
Signed agreements2of 3
New since August0requests

3 proposed energy projects from ERCOT's September 2026 report, plus who to call in Gray County and in TCEQ Region 1 before signing a solar, wind, or battery storage lease.

Check land in Gray CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

Power reliability here: minutes without power per year, outages per year, and outage length for Gray County, 2013–2024, from the serving utilities' EIA filings.

What energy projects are proposed in Gray County?

ERCOT's September 2026 interconnection report lists 3 proposed energy projects in Gray County (1 solar and 2 wind), about 2,121 MW in all. 2 of the 3 have a signed interconnection agreement.

What stands out in Gray County

By capacity, wind leads in Gray County with 1,418 MW across 2 projects, followed by solar (1 project, 703 MW). The largest single project is Meitner 2 Wind, a 709 MW wind project listed under IP Meitner, LLC, still in study, and its target online date is Jun 2028. Of the 3, 1 is still in ERCOT's study process and 2 have a signed interconnection agreement but no security posted yet. Every listed connection point is on the 345 kV system (why the voltage matters). IP Meitner, LLC is listed on the most projects here (3 of 3); 1 different companies appear in all. Target online dates for the projects not yet running span May 2028 to Jun 2028. All of them fall in ERCOT's Panhandle load zone.

A listing is a request to study a grid connection, not a built project; the stage column says how far each one has gone.

Stage, most advanced first: Approved for synchronization (first power) · Approved for energization (backfeed) · Under construction · Signed; security posted (interconnection agreement signed and financial security posted) · Signed (agreement signed, security not yet posted) · In study (screening or full interconnection study, no agreement). A target date that has already passed is marked; ERCOT keeps the developer's last reported date until the developer changes it.

Scroll the table sideways to see every column.

Project and connection pointDeveloper as listed by ERCOTTypeMWTarget online date
iThe commercial operation date the developer reported to ERCOT (ERCOT calls it the projected COD). Developers set and change it, many projects slip, and some are never built. It is not a promise or a construction date.
Stage
Meitner Wind79000 Gray Substation 345kV · shared with 1 other requestIP Meitner, LLCWind709.0May 2028Signed Apr 2024
Meitner Solar345 kV Gray (Bus# 79000)IP Meitner, LLCSolar702.6Jun 2028Signed Jan 2024
Meitner 2 Wind79000 Gray Substation 345kV · shared with 1 other requestIP Meitner, LLCWind709.1Jun 2028In study

Crowded connection points in Gray County

Substations and switching stations named by two or more of the county's requests, matched on ERCOT's PSS/E bus number rather than the exact wording, so "60404 SOLSTICE", "AEP Solstice Substation #60404" and a tap off the Solstice line count together. Every request statewide that names the bus is listed; a request on a tap line counts toward both ends. Sharing a bus is not the same as sharing a study group, and ERCOT decides the latter.

Gray (79000) 345 kV 3 requests · 2,121 MW2 signed, 1 in study
  • Meitner Wind 26INR0113 · Wind · 709 MW · Signed Apr 2024
  • Meitner Solar 25INR0080 · Solar · 703 MW · Signed Jan 2024
  • Meitner 2 Wind 29INR0103 · Wind · 709 MW · In study

What the stages and dates mean: how to read ERCOT's report. ERCOT's report lists self-limiting facilities (batteries that limit injection below nameplate) at 0 MW; repowers of existing plants show 0 with no capacity change. "Approved for energization" and "approved for synchronization" are ERCOT's own milestones (backfeed, then first power). "Shared with N other requests" counts active requests anywhere in ERCOT naming the same point of interconnection, matched on ERCOT's exact wording, so a bus written two ways counts as two points. Source: ERCOT Generator Interconnection Status (GIS) Report, September 2026, planning data entered by developers and transmission providers that ERCOT says may contain errors. Parcel & Grid is not affiliated with ERCOT.

Who to contact in Gray County

  • Gray County appraisal district and tax office: parcel records and agricultural valuation, which a lease can end (directory, Texas Comptroller · rollback taxes).
  • TCEQ Region 1, Amarillo: 5809 S. Western St., Ste 260, Amarillo TX 79110-3631, 806-353-9251; spills, 24 hours: 800-832-8224. Handles the construction stormwater permit for sites of 1 acre or more (TCEQ).
  • Gray County judge and commissioners court: road use agreements, tax agreements, and floodplain development permits where the county takes part in the flood insurance program.
  • Flood maps: FEMA map search for Gray County.

Permits and reviews for Gray County

Texas has no state siting permit for solar or wind, and Texas counties generally have no zoning authority, so a project in Gray County is shaped by site control, the county road use agreement, tax agreements, and the grid connection (what still applies · the twelve approvals, stage by stage). Wetland, endangered species, historic, and FAA reviews depend on the site: statewide and federal contacts · decommissioning law.

How a project in Gray County connects to the grid

Gray County is on the ERCOT grid. The projects listed above are in ERCOT's Panhandle load zone. The serving utility handles the connection request. Interconnection by market and utility · what ERCOT is.

How long it takes. ERCOT staff put the connection process at 18 to 30 months for generation of 10 MW or more, before construction or supply delays (ERCOT, Oct. 2024). Across the U.S., the median project built in 2025 took 61 months from interconnection request to commercial operation (Berkeley Lab, Queued Up 2026), so a lease signed today usually means construction years out: timelines by market.

Solar for homes and businesses in Gray County

Texas rules for rooftop and on-site systems are the same in every county; your electric utility sets the application steps: Texas home and business solar rules · your utility's application links.

Get the land report for a spot in Gray County

Get a free land report for any point: flood zone, wetlands, nearest power line, soils, and parcel acreage.

Check this land

Other counties served by TCEQ Region 1

Armstrong · Briscoe · Carson · Castro · Childress · Collingsworth · Dallam · Deaf Smith · Donley · Hall · Hansford · Hartley · Hemphill · Hutchinson · Lipscomb · Moore · Ochiltree · Oldham · Parmer · Potter · Randall · Roberts · Sherman · Swisher · Wheeler

Check before you file. Contacts come from official directories and can change. Confirm fees, forms, and deadlines with the agency. General information, not a substitute for the advice of an attorney. Found an error? Let us know.