Public companies in ERCOT: what their filings say
86 sourced statements from 22 companies · Checked October 18, 2026
Developers deal with these companies as counterparties, competitors for points of interconnection, buyers of projects, and suppliers. Their 10-Ks, 8-K earnings exhibits, and investor releases state things no trade article does: fleet MW by segment, Texas projects under construction, large-load request totals, queue counts, capital plans, and the tariff and credit-deadline language in the risk factors. This page quotes those documents and links each one.
Jump to: Owners and developers of generation and storage · Integrated retail and generation · Transmission and distribution utilities · Large loads: data-center and high-performance computing campuses · Equipment and the supply chain
What this page is not. It carries no share prices, ratings, targets, or opinions on any company, and names none as better than another; it is not investment advice and is not a complete list. Each statement is as of the date the document gives, and filings are superseded quarterly. Entries marked MISO or SPP are Texas utilities outside ERCOT, kept because developers in those parts of the state deal with them. Where a figure is company-wide rather than Texas-specific, the statement says so.
Owners and developers of generation and storage
Companies that own or build generation and storage in ERCOT and say so in their filings: fleet size by segment, Texas projects under construction, and what the risk factors name.
Vistra Corp. NYSE: VST
Irving, Texas · SEC filings (EDGAR)
- As of December 31, 2025, Vistra's Texas segment (ERCOT) accounted for 19,858 MW, or 46%, of a fleet the company describes as approximately 44,000 MW.
“Our generation fleet totals approximately 44,000 megawatts of generation capacity”
Vistra 10-K for 2025, Item 1 (Business), segment capacity table: 'Texas | 19,858 | 46% | ERCOT' · 2026-02-27 - As of December 31, 2025, Vistra owned 270 MW of battery storage and 538 MW of solar in Texas.
“As of December 31, 2025, we owned battery ESS totaling 350 MW in California, 270 MW in Texas and 4 MW in Illinois.”
Vistra 10-K for 2025, Item 1, Battery Energy Storage Projects (solar sentence: 'we owned solar generations facilities totaling 538 MW in Texas and 112 MW in Illinois') · 2026-02-27 - Vistra's 2025 10-K flags Texas Senate Bill 6 (2025) as a new requirement on co-located large loads in ERCOT, and cites 2025 ERCOT peak demand of about 83,707 MW.
“In 2025, the Texas legislature passed Senate Bill 6 (SB 6) that requires certain co-located large loads”
Vistra 10-K for 2025, Item 1, Market Discussion – ERCOT · 2026-02-27 - On September 29, 2025, Vistra confirmed it will build two gas units totaling 860 MW at its Permian Basin Power Plant, more than tripling the site's capacity from 325 MW to 1,185 MW (the release quotes the Mayor of Monahans but does not itself name Monahans as the site).
“confirms it will build two new advanced natural gas power units, together totaling 860 megawatts”
Vistra press release, 'Vistra Announces Plans to Build New Gas-Fueled Dispatchable Power Units in the Permian Basin', Sept. 29, 2025 · 2025-09-29 - As of August 3, 2026, Vistra had hedged about 100% of expected 2026 generation, 94% of 2027 and 72% of 2028; 2026 capex guidance (incl. nuclear fuel and LTSA prepayments) was $1,536 million.
“Vistra had hedged approximately 100% of its expected generation volumes for 2026”
Vistra Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 7, 2026, Guidance section and Adjusted FCFbG reconciliation · 2026-08-07 - Vistra's pending Cogentrix acquisition (10 gas plants, ~5,500 MW) includes one cogeneration facility in ERCOT; FERC approved it in August 2026 and closing is expected in late 2026.
“10 modern natural gas generation facilities totaling approximately 5,500 MW of capacity”
Vistra 10-Q for quarter ended June 30, 2026, Note 2 – Cogentrix Transaction ('one cogeneration facility in ERCOT'; 'expected to close in late 2026') · 2026-08-07
Constellation Energy Corporation Nasdaq: CEG
Baltimore, Maryland · SEC filings (EDGAR)
- As of December 31, 2025 (before the Calpine close), Constellation's ERCOT segment held 4,742 MW, or 15% of its owned generation.
“| ERCOT | 4,742 | 15% | Electric Reliability Council of Texas |”
Constellation 10-K for 2025, Item 1, Our Operations segment table · 2026-02-27 - The Calpine merger, closed January 7, 2026, added approximately 23 GW across 72 generation and storage assets, including 21 GW of gas-fired generation with a footprint in Texas; no ERCOT-specific MW breakout is given.
“our merger with Calpine added approximately 23 GWs across 72 generation and battery storage assets”
Constellation 10-K for 2025, Item 1, Our Business · 2026-02-27 - In fall 2025 the Texas Energy Fund selected a $278 million loan for Calpine's 460 MW Pin Oak Creek peaking facility; the TEF was approved in November 2023 to support up to 10 GW of new dispatchable generation.
“a $278 million loan for Calpine's 460 MW Pin Oak Creek peaking facility”
Constellation 10-K for 2025, Item 1, Outlook – Policy Support for New, Reliable Generation · 2026-02-27 - On August 6, 2026, Constellation reported an agreement to sell the 606 MW Brazos Valley Energy Center in ERCOT to LS Power for $860 million before closing adjustments, with closing expected by year-end 2026 subject to DOJ approval.
“a 606 MW natural gas-fired plant in ERCOT for $860 million before closing adjustments”
Constellation Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026 · 2026-08-06 - In Q2 2026 Constellation's ERCOT nuclear output was 2,036 GWh (vs 2,515 GWh in Q2 2025) and ERCOT gas/oil/renewables output was 3,742 GWh (vs 3,206 GWh).
“| ERCOT | 2,036 | 2,515 | 4,388 | 5,044 |”
Constellation Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Statistics table (Nuclear Generation and Natural Gas, Oil and Renewables rows) · 2026-08-06
NextEra Energy, Inc. NYSE: NEE
Juno Beach, Florida · SEC filings (EDGAR)
- As of December 31, 2025, NextEra Energy Transmission's operational ERCOT assets were 374 miles and 12 substations at 138–345 kV (in service 2013), with another 41 miles and 5 substations at 345 kV under construction for 2026–2028.
“ERCOT | 374 | 12 | 138 – 345 | Texas | PUCT | 100% | 2013”
NextEra Energy 10-K for 2025, Item 1, Rate-Regulated Electric Transmission tables (under construction row: 'ERCOT | 41 | 5 | 345 | Texas | PUCT | 100% | 2026 – 2028') · 2026-02-20 - As of December 31, 2025, NEER held net ownership interests in about 5,177 MW of battery storage across 18 states and one Canadian province, and its contracted wind fleet is located primarily in Texas and the West and Midwest; no Texas MW breakout is disclosed.
“essentially all MW are contracted wind assets located primarily throughout Texas and the West and Midwest regions”
NextEra Energy 10-K for 2025, Item 1, NEER Generation Assets – Fuel/Technology Mix · 2026-02-20 - NextEra's 2025 10-K states that wind and solar facilities beginning construction before July 5, 2026 remain eligible for 100% PTC or 30% ITC, and that facilities beginning construction after December 31, 2025 must satisfy OBBBA prohibited-foreign-entity material-assistance rules.
“must satisfy the prohibited foreign entity material assistance requirements under the OBBBA”
NextEra Energy 10-K for 2025, Item 1, Policy Incentives for Clean Energy Projects · 2026-02-20 - As of July 24, 2026, NEER's backlog totaled approximately 35.1 GW, with battery storage making up 2 GW of Q2 2026 additions; the release does not break out Texas/ERCOT.
“Battery storage represented 2 GW of additions this quarter.”
NextEra Energy Q2 2026 earnings release (8-K Exhibit 99), July 24, 2026 · 2026-07-24
The AES Corporation NYSE: AES
Arlington, Virginia · SEC filings (EDGAR)
- As of December 31, 2025, AES had three Texas projects under construction: Armadillo solar (200 MW gross, 75% owned, 1H 2026), Buffalo Gap wind repowering (527 MW, 100%, 1H 2027) and Four Horizons wind (945 MW, 75%, 2H 2027–1H 2028).
“Four Horizons | US-TX | Wind | 945 MW gross | 75% | 2H 2027 - 1H 2028”
AES 10-K for 2025, Item 1, Renewables SBU – projects under construction table · 2026-03-02 - As of December 31, 2025, AES Clean Energy owned/operated 10,961 MW in the U.S. with another 3,031 MW under construction and a 7.6 GW backlog expected online mostly through 2029.
“AES Clean Energy has a 7.6 GW backlog of projects, the majority of which are expected to come online through 2029.”
AES 10-K for 2025, Item 1, Renewables SBU – AES Clean Energy · 2026-03-02 - In 2025 AES Clean Energy signed or was awarded 2,776 MW of PPAs.
“In 2025, AES Clean Energy signed or was awarded 2,776 MW of PPAs.”
AES 10-K for 2025, Item 1, Renewables SBU – AES Clean Energy · 2026-03-02
Clearway Energy, Inc. NYSE: CWEN
Princeton, New Jersey · SEC filings (EDGAR)
- As of its 2025 10-K, Clearway's committed investments include the 360 MW Goat Mountain wind repowering in Texas with estimated funding in 2H 2027.
“Goat Mountain Repower | Wind | 360 | TX | 2H27”
Clearway Energy, Inc. 10-K for 2025, Item 1, committed investments table · 2026-02-24 - As of December 31, 2025, Clearway's portfolio was approximately 12.9 GW gross in 27 states, including about 10.1 GW of wind, solar and storage and 2.8 GW of dispatchable combustion assets.
“approximately 12.9 GW of gross capacity in 27 states, including approximately 10.1 GW of wind, solar and BESS”
Clearway Energy, Inc. 10-K for 2025, Item 1, Business overview · 2026-02-24 - Clearway's 2025 10-K notes its ERCOT-footprint operations are outside FERC rate regulation, and that the federal tax legislation enacted July 4, 2025 provides that the percentage of facility components manufactured by foreign entities of concern cannot exceed a specified percentage (for wind and solar facilities beginning construction after July 4, 2026).
“The Company’s operations within the ERCOT footprint are not subject to rate regulation by FERC”
Clearway Energy, Inc. 10-K for 2025, Item 1, Regulatory Matters (FEOC sentence under Policy Incentives) · 2026-02-24
Integrated retail and generation
Companies that both sell electricity to Texas customers and own plants, and what they disclose about Texas capacity and new build.
NRG Energy, Inc. NYSE: NRG
Houston, Texas · SEC filings (EDGAR)
- As of December 31, 2025, NRG's Texas generation portfolio totaled 9,271 MW (5,069 MW gas, 4,202 MW coal) out of 12,276 MW company-wide.
“The following table summarizes NRG's generation portfolio as of December 31, 2025:”
NRG 10-K for 2025, Item 1, Plant Operations table (row 'Total generation capacity | 9,271 | 2,073 | 932 | 12,276') · 2026-02-25 - NRG's Texas Energy Fund projects are a 415 MW peaker at T.H. Wharton (expected June 2026), a 689 MW combined cycle at Cedar Bayou 5 and a 443 MW peaker at Greens Bayou 6 (both mid-2028), funded by PUCT loans of $216 million (July 31, 2025), $562 million (Sept. 26, 2025) and $370 million (Nov. 20, 2025).
“a 689 MW combined cycle generating facility at Cedar Bayou 5”
NRG 10-K for 2025, Item 1, Texas Development Projects and Regional Regulatory Developments – Texas Energy Fund · 2026-02-25 - NRG's 2025 10-K records that SB 6 was signed June 20, 2025, that PUCT rulemaking on SB 6 was still in progress, and that the PUCT adopted a final firming-requirement rule in December 2025.
“On June 20, 2025, the Governor of Texas signed SB 6 into law”
NRG 10-K for 2025, Item 1, Regional Regulatory Developments – ERCOT/PUCT · 2026-02-25 - On May 26, 2026, NRG's 415 MW T.H. Wharton facility reached commercial operation; NRG says its TEF program will bring 1.5 GW online by mid-2028.
“On May 26, 2026, NRG achieved commercial operations at its first project, the 415 MW T.H. Wharton facility.”
NRG Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 4, 2026, Texas Energy Fund section · 2026-08-04 - As of August 4, 2026, NRG had agreed principal terms with an unnamed hyperscaler for a 1.2 GW combined-cycle gas plant in Texas under its 'Bring Your Own Power' strategy, subject to final documentation and approvals.
“a 1.2 GW combined cycle natural gas generation facility in Texas and remains subject to final documentation and approvals.”
NRG Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 4, 2026, Advanced BYOP Data Center Strategy · 2026-08-04 - NRG's 2026 guidance (reaffirmed Aug. 4, 2026) is Adjusted EBITDA of $5,325–$5,825 million with maintenance capex of $450–$480 million, including 11 months of ownership of the portfolio acquired from LS Power (described in NRG's 2025 10-K as 18 natural gas-fired and dual fuel facilities totaling approximately 13 GW).
“Includes 11 months of ownership of the portfolio acquired from LS Power.”
NRG Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 4, 2026, Table 2 and Table A-9; LSP quote from NRG 10-K for 2025, Item 1 · 2026-08-04
Transmission and distribution utilities
The wires companies. Their releases are where large-load request totals, capital plans, and point-of-interconnection queue counts are stated; two companies below (Entergy Texas in MISO; Southwestern Public Service, which is outside ERCOT) are marked.
Oncor Electric Delivery Company LLC n/a (no listed equity; 80.25% owned by Sempra, NYSE: SRE)
Dallas, Texas · SEC filings (EDGAR)
- On February 26, 2026, Oncor announced a $47.5 billion base capital plan for 2026–2030, including $6 billion for remaining Permian Basin Reliability Plan projects; non-PBRP 765 kV STEP work, currently estimated by Oncor at $3 billion for 2026–2030, is excluded from the base plan and counted among roughly $10 billion of potential incremental opportunities.
“Today, Oncor is announcing a new five-year base capital plan of approximately $47.5 billion for the 2026 to 2030 period”
Oncor Q4 2025 earnings release, Feb. 26, 2026, Five-Year Capital Plan · 2026-02-26 - As of December 31, 2025, Oncor had 562 active generation POI requests in queue and large-load requests that included about 255 GW from data centers; transmission POI requests were up 24% year over year.
“As of December 31, 2025, Oncor had 562 active generation POI requests in queue”
Oncor Q4 2025 earnings release, Feb. 26, 2026, Strategic Growth and Operational Highlights · 2026-02-26 - At June 30, 2026, Oncor's active transmission LC&I interconnection queue had 737 requests, including about 282 GW from data centers, and 552 active generation POI requests.
“Those requests included approximately 282 gigawatts from data centers”
Oncor Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Operational Highlights · 2026-08-06 - Under ERCOT's Batch Zero process, about 44 GW of large-load requests in Oncor's territory are expected to be eligible as base or studied load (≈27 GW base, ≈17 GW studied) as of the Q2 2026 release.
“approximately 44 gigawatts of large-load requests are expected to be eligible as base or studied load”
Oncor Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Operational Highlights · 2026-08-06 - As of August 1, 2026, Oncor held about $5.9 billion in customer collateral for active generation and large commercial/industrial interconnection requests.
“As of August 1, 2026, Oncor held approximately $5.9 billion in customer collateral for active generation and Large Commercial and Industrial”
Oncor Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Operational Highlights · 2026-08-06 - Oncor placed in service its portion of the 165-mile double-circuit 345 kV Delaware Basin Stage 2 line, described as the first in a series of upgrades needed to resolve import constraints into far west Texas; separately, ERCOT-endorsed projects serving the southern Dallas–Fort Worth area and the I-35 corridor are expected to require over $7 billion of investment.
“these projects are expected to require investment of over $7 billion”
Oncor Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Operational Highlights · 2026-08-06
Sempra NYSE: SRE
San Diego, California · SEC filings (EDGAR)
- As of August 6, 2026, Sempra's 2026–2030 capital plan is approximately $65 billion, with 59% allocated to Sempra Texas Utilities (Oncor) and 95% to its Texas and California utilities combined.
“record five-year 2026-2030 capital plan of approximately $65 billion”
Sempra Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Advancing Value Creation Initiatives and Table D ('Percentage of Capital Plan | 36% | 59% | 5% | 100%') · 2026-08-06 - Sempra reported about 44 GW of large-load requests in Oncor's service territory expected to be eligible as base or studied load (including 8 GW of existing load ramping up), which if fully realized would represent over 140% growth relative to Oncor's current 31 GW system peak load, as of the Q2 2026 release.
“over 140% growth relative to Oncor's current system peak load of 31 GW”
Sempra Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Sempra Texas section · 2026-08-06 - Sempra cites more than $7 billion of incremental ERCOT-endorsed transmission investment at Oncor supporting roughly 16 GW of new electric demand.
“more than $7 billion of incremental investment, supporting approximately 16 GW of new electric demand”
Sempra Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Sempra Texas section · 2026-08-06 - Sempra Texas Utilities segment earnings were $346 million in Q2 2026 versus $208 million in Q2 2025.
“Sempra Texas Utilities | 346 | 208 | 517 | 354”
Sempra Q2 2026 earnings release (8-K Exhibit 99.1), Aug. 6, 2026, Table D segment earnings · 2026-08-06
CenterPoint Energy, Inc. NYSE: CNP
Houston, Texas · SEC filings (EDGAR)
- On April 23, 2026, CenterPoint reported 12.2 GW of firmly committed industrial load at Houston Electric, with 3.5 GW already under construction and 8 GW of data center load expected to be energized by 2029.
“Announces 12.2 gigawatts of firmly committed industrial load at Houston Electric”
CenterPoint Energy Q1 2026 earnings release (8-K Exhibit 99.1), Apr. 23, 2026 · 2026-04-23 - CenterPoint submitted over 17 GW of large-load projects through ERCOT's Batch Zero process, of which about 14 GW is expected to qualify as base or studied load by 2031 (as of July 28, 2026).
“submitted over 17 gigawatts of large load projects through ERCOT's Batch Zero process”
CenterPoint Energy Q2 2026 earnings release (8-K Exhibit 99.1), July 28, 2026 · 2026-07-28 - The ~14 GW of eligible Batch Zero load would be a more than 65% increase over Houston Electric's current peak system demand of 21 GW.
“would represent more than a 65% increase from our current Houston Electric peak system demand of 21 gigawatts”
CenterPoint Energy Q2 2026 earnings release (8-K Exhibit 99.1), July 28, 2026, CEO statement · 2026-07-28 - On July 28, 2026, CenterPoint increased its 10-year capital investment plan by $1.2 billion to $66.7 billion and reiterated 2026 non-GAAP EPS guidance of $1.89–$1.91 (at least the midpoint).
“increased its 10-year capital investment plan by $1.2 billion to $66.7 billion”
CenterPoint Energy Q2 2026 earnings release (8-K Exhibit 99.1), July 28, 2026, summary bullets · 2026-07-28
American Electric Power Company, Inc. Nasdaq: AEP
Columbus, Ohio · SEC filings (EDGAR)
- In Q2 2026 AEP added 6 GW of signed load agreements, primarily in Texas, bringing contracted load growth through 2030 to 69 GW (as of July 30, 2026).
“added an incremental six GW of signed load agreements during the second quarter, primarily in Texas”
AEP Q2 2026 earnings release (8-K Exhibit 99.1), July 30, 2026 · 2026-07-30 - AEP Texas secured a DOE loan of up to $3.3 billion to support nearly 100 transmission projects (reported July 30, 2026).
“AEP Texas secured a DOE loan for up to $3.3 billion to support nearly 100 transmission projects”
AEP Q2 2026 earnings release (8-K Exhibit 99.1), July 30, 2026 · 2026-07-30 - AEP plans to invest $78 billion from 2026 through 2030 and cites line of sight to more than $10 billion of incremental capital; the load agreements include hyperscalers, data centers and industrials.
“We plan to invest $78 billion from 2026 through 2030 to enhance service for customers”
AEP Q2 2026 earnings release (8-K Exhibit 99.1), July 30, 2026 · 2026-07-30
Entergy Corporation NYSE: ETR MISO (Entergy Texas), not ERCOT
New Orleans, Louisiana · SEC filings (EDGAR)
- Entergy Texas incurs MISO capacity costs; its 2025 10-K says Entergy Texas cannot recover those costs beyond the level included in base rates, that June 2025 Texas legislation established a capacity cost recovery rider mechanism, and that it planned to file for the rider in Q2 2026.
“Entergy Texas plans in second quarter 2026 to file for such a rider to recover future capacity procurement costs.”
Entergy 10-K for 2025, MD&A – Other Income Statement Items (Utility) · 2026-02-24 - Entergy Texas purchased power costs rose $34 million in 2025, and construction work in progress at Orange County Advanced Power Station, Legend Power Station and Lone Star Power Station increased AFUDC equity (2025 10-K).
“Purchased power includes an increase in 2025 of $34 million in costs, at Entergy Texas”
Entergy 10-K for 2025, MD&A – Other Income Statement Items and Other Income (Deductions) · 2026-02-24 - Entergy Texas was awarded an approximately $200 million Texas Energy Fund grant for electric reliability, and the PUCT approved its DCRF rate update (reported July 29, 2026).
“Entergy Texas was awarded an approximately $200 million Texas Energy Fund grant for electric reliability”
Entergy Q2 2026 earnings release (entergy.com), July 29, 2026, Business highlights · 2026-07-29
Xcel Energy Inc. Nasdaq: XEL Southwestern Public Service; outside ERCOT, not ERCOT
Minneapolis, Minnesota · SEC filings (EDGAR)
- Xcel's Southwestern Public Service (SPS) conducts business in Texas and New Mexico with 5,100 MW of owned generating capacity, 41,000 miles of transmission lines and 25,000 miles of distribution lines, as of December 31, 2025; the reachable 10-K text does not state SPS's RTO or mention the Panhandle.
“SPS conducts business in Texas and New Mexico and generates, purchases, transmits, distributes and sells electricity.”
Xcel Energy 10-K for 2025, Item 1, Utility Subsidiaries table · 2026-02-25 - As of December 31, 2025, SPS owned two wind farms totaling 986 MW and held 1,482 MW of contracted wind PPAs; its Tolk 1 (532 MW) and Tolk 2 (535 MW) coal units are approved for early retirement in 2028.
“Owned wind: 986 MW (two wind farms); purchased wind under PPA: 1,482 MW; Tolk 1, 532 MW, and Tolk 2, 535 MW, approved for early retirement in 2028 (10-K tables).”
Xcel Energy 10-K for 2025, Item 1, Owned and Purchased Energy Generation tables and early coal retirement table (quote from Item 1A credit-risk factor) · 2026-02-25 - Xcel's 2026–2030 plan system-wide includes approximately 9,500 MW of new and repowered wind, solar and battery storage and approximately 3,000 MW of new natural gas generation within a $60 billion five-year capital plan; the 10-K does not break these out for SPS/Texas.
“In our base 2026 - 2030 capital investment plan, we have ~9,500 MW of new and repowered wind, solar, and battery storage resources included and ~3,000 MW of new natural gas generation”
Xcel Energy 10-K for 2025, Item 1 (system-wide resource additions and capital plan; Texas quote from Wildfire Resiliency section) · 2026-02-25
Large loads: data-center and high-performance computing campuses
Public companies building load in ERCOT that state MW, interconnection and lease terms in filings.
Riot Platforms, Inc. Nasdaq: RIOT
Castle Rock, Colorado · SEC filings (EDGAR)
- Riot's Rockdale, Texas facility has 700 MW of developed capacity and a 700 MW grid interconnection; its Corsicana, Texas facility has 400 MW developed and is expected to reach about 1 GW (2025 10-K).
“currently has 400 MW of developed capacity and, upon completion, is expected to have a total of approximately one gigawatt”
Riot Platforms 10-K for 2025, Item 1, General and Data Center Development · 2026-03-02 - In January 2026 Riot announced execution of a long-term data center lease with AMD to initially provide 25 MW of critical IT load at Rockdale, with expansion options for up to an additional 75 MW and a right of first refusal of up to an additional 100 MW; the 10-K notes SB 6 (2025) introduces new disclosure and reliability requirements for large industrial electricity users.
“to initially provide 25 MW of critical IT load capacity at the Rockdale Facility”
Riot Platforms 10-K for 2025, Item 1, AMD Lease and Regulation (SB 6) · 2026-03-02 - On August 10, 2026, Riot reported a 20-year, 191 MW critical-IT data center lease at Rockdale with an unnamed frontier AI lab, expected to generate $9.1 billion of initial contract revenue, with 96 MW delivered December 2027 and 95 MW June 2028 at expected capex of $2.1–$2.3 billion.
“Executed Data Center Lease with a leading frontier AI lab for 191 MW of critical IT capacity”
Riot Platforms Q2 2026 earnings presentation (8-K Exhibit 99.2), Aug. 10, 2026, Key Highlights, Deal Highlights and Financing Update · 2026-08-10 - Riot earned $10.1 million of power curtailment credits in Q2 2026 by participating in ERCOT demand response programs, and reports approximately 1,700 MW of available power capacity in Texas.
“Riot's power strategy generated significant power curtailment credits of $10.1 million in Q2 2026.”
Riot Platforms Q2 2026 earnings presentation (8-K Exhibit 99.2), Aug. 10, 2026, Operational Appendix and 'By the Numbers' · 2026-08-10
Cipher Digital Inc. (formerly Cipher Mining Inc.) Nasdaq: CIFR
New York, New York · SEC filings (EDGAR)
- Cipher's portfolio is 4.2 GW across 10 sites, including a pipeline of about 3.4 GW across seven Texas sites and one in Ohio; its wholly owned Texas facilities are 207 MW at Odessa and 300 MW at Black Pearl (Wink), as of the 2025 10-K.
“a pipeline of approximately 3.4 GW across seven sites in Texas and one additional site in Ohio.”
Cipher Digital 10-K for 2025, Item 1, Business overview · 2026-02-26 - Cipher signed a 15-year lease with Amazon Web Services for approximately 300 gross MW of turnkey data center capacity at Black Pearl, targeting rent commencement for the initial subphase by Q4 2026.
“to deliver approximately 300 gross MW of turnkey data center capacity at the site”
Cipher Digital 10-K for 2025, Item 1, Black Pearl / AWS lease · 2026-02-26 - At Barber Lake, Texas, Cipher has 300 MW of interconnection approvals, with 244 MW gross allocated to Fluidstack in Phase I (Google backstopping Fluidstack obligations), targeted for delivery by September 30, 2026.
“244 MW of gross capacity will be allocated to Fluidstack in Barber Lake Phase I”
Cipher Digital 10-K for 2025, Item 1, Barber Lake / Fluidstack · 2026-02-26 - Cipher's Milsing site targets up to 500 MW with energization estimated 2028–2029, and its Stingray site has conditional ERCOT interconnection approval of up to 100 MW.
“The Stingray Site has conditional ERCOT interconnection approval of up to 100 MW.”
Cipher Digital 10-K for 2025, Item 1, development sites · 2026-02-26 - Cipher's 10-K describes SB 6 as covering interconnection of loads of at least 75 MW to ERCOT and requiring security-type payments with the initial interconnection request, and notes ERCOT amended its large-load approval process.
“SB 6 also requires security type payments as part of the initial interconnection request”
Cipher Digital 10-K for 2025, Item 1/1A, Regulation – SB 6 and ERCOT large load interconnection · 2026-02-26 - Cipher's Odessa PPA with Luminant provides power at about 2.7 c/kWh (raised to 2.8 c/kWh in October 2025) until at least July 2027, with a take-or-pay of at least 66.7% of the 207 MW capacity each year.
“we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh”
Cipher Digital 10-K for 2025, Item 1, Odessa power purchase agreement · 2026-02-26
Equipment and the supply chain
Module, tracker, inverter, battery and turbine makers. Most do not report Texas figures; what they do report is backlog and the tariff, prohibited-foreign-entity and credit-deadline language that decides what a project can buy.
Fluence Energy, Inc. Nasdaq: FLNC
Arlington, Virginia · SEC filings (EDGAR)
- As of September 30, 2025, Fluence had a 128.8 GW gross global pipeline (65.1 GW storage solutions and services), with U.S. customers the largest share at 16.1 GW (~25%); its Mosaic bidding software is available in ERCOT.
“Fluence Mosaic is currently available in the NEM (Australia), CAISO (California), ERCOT (Texas), and Japan.”
Fluence 10-K for fiscal 2025 (FYE Sept. 30, 2025), Item 1, Our Customers and Digital Application Offerings · 2025-11-25 - Fluence's fiscal 2025 10-K states the Section 301 tariff on lithium-ion non-EV batteries from China rises from 7.5% to 25% effective January 1, 2026, and that OBBBA prohibited-foreign-entity restrictions require Treasury regulations by December 31, 2026.
“The new PFE restrictions apply to virtually all key tax credits under the IRA and come in two forms”
Fluence 10-K for fiscal 2025, Item 1, Recent U.S. Tariffs and Trade Policies; IRA and OBBBA · 2025-11-25 - Fluence sources battery cells manufactured in Tennessee for its U.S. domestic-content offering, with modules from a contract manufacturer in Utah since September 2024.
“are incorporating battery cells manufactured in Tennessee for our domestic content offering in the U.S.”
Fluence 10-K for fiscal 2025, Item 1, Fluence-designed Battery Pack · 2025-11-25 - As of June 30, 2026, Fluence's backlog was approximately $6.4 billion (a company record) after quarterly order intake of more than $1.44 billion; fiscal 2026 revenue guidance was cut to $2.9–$3.1 billion from $3.2–$3.6 billion.
“Backlog2 as of June 30, 2026 of approximately $6.4 billion, the highest level in Company history.”
Fluence Q3 fiscal 2026 earnings release (8-K Exhibit 99.1), Aug. 5, 2026 · 2026-08-05
First Solar, Inc. Nasdaq: FSLR
Tempe, Arizona · SEC filings (EDGAR)
- First Solar's 2025 10-K states utility-scale solar projects generally must begin construction by early July 2026 to remain eligible for OBBBA-amended tax credits, which also carry foreign-entity-related eligibility restrictions.
“utility‑scale solar projects generally must begin construction by early July 2026 to remain eligible”
First Solar 10-K for 2025, Item 1, Incentive Programs – Investment and Production Tax Credits · 2026-02-26 - First Solar's 2025 10-K lists IEEPA tariffs of 20% (Vietnam), 25% (India; 50% overall after an additional 25% tariff in August 2025) and 19% (Malaysia), a 10% reciprocal tariff on China effective until November 10, 2026, and final AD/CVD rates on certain solar imports from de minimis to over 3,400%; it also reports that on February 20, 2026 the Supreme Court ruled the IEEPA tariffs unlawful and they were revoked and replaced with Section 122 tariffs of up to 15% for no more than 150 days.
“Final AD/CVD rates ranged from de minimis to over 3,400%, depending on the particular foreign producer.”
First Solar 10-K for 2025, Item 1A, Risk Factors – United States tariffs and AD/CVD · 2026-02-26 - As of June 30, 2026, First Solar's contracted sales backlog was 45.1 GW extending through 2030; 2026 guidance was unchanged at $4.9–$5.2 billion net sales and 17.0–18.2 GW volume sold.
“Contracted sales backlog of 45.1 GW as of June 30, 2026”
First Solar Q2 2026 earnings release (8-K Exhibit 99.1), July 30, 2026 · 2026-07-30
Array Technologies, Inc. Nasdaq: ARRY
Albuquerque, New Mexico · SEC filings (EDGAR)
- Array's 2025 10-K describes 25% across-the-board duties on steel and aluminum imports, a 50% tariff on copper imports, and a 10% baseline reciprocal tariff with country rates up to 50%.
“resulting in across-the-board 25% duties on steel and aluminum imports.”
Array Technologies 10-K for 2025, Item 1A, Changes in the global trade environment · 2026-02-26 - Array's 2025 10-K states the solar ITC terminates for facilities placed in service after December 31, 2027 under the OBBB unless construction begins before July 4, 2026, and that Treasury guidance on 'material assistance' calculations was released February 13, 2026.
“the solar ITC now terminates for facilities that are placed in service after December 31, 2027”
Array Technologies 10-K for 2025, Item 1, Government Incentives · 2026-02-26 - Array's own U.S. manufacturing facilities are in New Mexico (an approximately 283,000 sq ft Albuquerque plant plus a new facility in Bernalillo County with ~176,000 sq ft of manufacturing space), and it leases offices, manufacturing facilities and warehouses in Ohio and Connecticut from the APA Acquisition, whose total purchase consideration was approximately $185.4 million.
“In the U.S., we operate an approximately 283,000 square foot manufacturing facility in Albuquerque, New Mexico.”
Array Technologies 10-K for 2025, Item 1, Resources: Manufacturing and APA Acquisition · 2026-02-26
Shoals Technologies Group, Inc. Nasdaq: SHLS
Portland, Tennessee · SEC filings (EDGAR)
- As of December 31, 2025, Shoals had $747.6 million of backlog and awarded orders (awarded orders $421.4 million).
“As of December 31, 2025, we had $747.6 million of backlog and awarded orders.”
Shoals Technologies 10-K for 2025, Item 1A, Risk Factors · 2026-02-27 - Shoals' 2025 10-K cites the OBBBA placed-in-service deadline of December 31, 2027 for solar and wind projects and says FEOC guidance is still forthcoming and expected to be finalized in 2026.
“Additional guidance around FEOC provisions is still forthcoming and expected to be finalized in 2026.”
Shoals Technologies 10-K for 2025, Item 1, Government Regulation · 2026-02-27 - Shoals' 2025 10-K notes the U.S. and China suspended heightened tariff imposition until November 2026 and that Shoals is pursuing the CC&I, BESS and data center markets.
“Both the U.S. and China have suspended heightened tariff imposition until November 2026.”
Shoals Technologies 10-K for 2025, Item 1A, trade restrictions and tariffs · 2026-02-27
Tesla, Inc. (Energy Generation and Storage segment) Nasdaq: TSLA
Austin, Texas · SEC filings (EDGAR)
- Tesla deployed 13.5 GWh of energy storage in Q2 2026, up 41% from 9.6 GWh in Q2 2025; Energy generation and storage revenue was $3,139 million in Q2 2026 vs $2,789 million a year earlier.
“Storage deployed (GWh) 9.6 12.5 14.2 8.8 13.5 41%”
Tesla Q2 2026 Update (shareholder deck), July 22, 2026, Operational Summary p. 5 and Financial Summary p. 4 · 2026-07-22 - As of July 22, 2026, Tesla's Megafactory Texas was in commissioning with Megapack 3 and Megablock production planned to start there in 2026, alongside 40 GWh (California) and 20 GWh (Shanghai) of Megapack production capacity.
“We are also on track to begin production of Megapack 3 and Megablock this year at our new Megafactory Texas.”
Tesla Q2 2026 Update (shareholder deck), July 22, 2026, Manufacturing & Hardware p. 6 · 2026-07-22 - Tesla's in-house lithium refinery in Texas began operations in January 2026, and Tesla lists Texas among its U.S. manufacturing locations (2025 10-K).
“such as our in-house lithium refinery in Texas, which began operations in January 2026.”
Tesla 10-K for 2025, Item 1, Supply Chain · 2026-01-29 - Tesla's 2025 10-K flags 2025 U.S. trade-policy changes, including heightened import tariffs and retaliatory measures, as a supplier risk.
“U.S. trade policy alterations in 2025, including heightened import tariffs and subsequent retaliatory measures,”
Tesla 10-K for 2025, Item 1A, supplier risk factor · 2026-01-29
GE Vernova Inc. NYSE: GEV
Cambridge, Massachusetts · SEC filings (EDGAR)
- As of June 30, 2026, GE Vernova's Gas Power equipment backlog plus slot reservation agreements had grown to 116 GW from 100 GW, after 20 GW of new gas contracts in the quarter (18 GW slot reservations, 2 GW orders).
“Gas Power equipment backlog and slot reservation agreements grew from 100 to 116 GW”
GE Vernova Q2 2026 earnings press release, July 22, 2026, Second Quarter 2026 Highlights · 2026-07-22 - GE Vernova says it remains on track to reach 20 GW of annual gas turbine output in Q3 2026, with Electrification data center orders over $5 billion year-to-date through Q2 2026 (more than double its 2025 total).
“we remain on track to deliver 20 GW of annual gas turbine output in the third quarter of 2026”
GE Vernova Q2 2026 earnings press release, July 22, 2026, CEO statement · 2026-07-22 - GE Vernova's Electrification equipment backlog reached $40.6 billion at June 30, 2026, up $16.6 billion (69%) year over year; 2026 revenue guidance was raised to $45.5–$46.5 billion.
“Increased equipment backlog to $40.6 billion, up $16.6 billion, or 69% year-over-year”
GE Vernova Q2 2026 earnings press release, July 22, 2026, Electrification and 2026 Guidance · 2026-07-22
Eos Energy Enterprises, Inc. Nasdaq: EOSE
Edison, New Jersey · SEC filings (EDGAR)
- As of December 31, 2025, Eos had drawn $90.9 million of a DOE loan facility of up to $303.5 million that is expected to fund expansion of manufacturing capacity to 8 GWh by 2027.
“The DOE Loan Facility provides for up to $303.5 million in funding, including capitalized interest.”
Eos Energy 10-K for 2025, Item 1, Governmental Programs – DOE Loan Facility · 2026-03-04 - Eos states it believes its current Z3 battery module's raw-material sourcing is sufficient to qualify for the IRA domestic-content bonus, describes its Indensity offering as supported by a domestic FEOC-compliant supply chain, and notes the OBBBA introduces new limitations on sourcing materials from a prohibited foreign entity.
“our current Z3 battery module feature raw materials sourcing sufficient to qualify for the Domestic Content Bonus”
Eos Energy 10-K for 2025, Item 1, Availability of Raw Materials and OBBBA · 2026-03-04 - Eos's 2025 10-K flags significant U.S. import tariffs imposed beginning in early 2025 as a risk; two customers accounted for 51.5% and 18.8% of 2025 revenue.
“Beginning in early 2025, the current U.S. administration has imposed significant tariffs on imports”
Eos Energy 10-K for 2025, Item 1A, Risk Factors (customer concentration from Item 1, Customers) · 2026-03-04
How this page was made
Each statement is one claim tied to one document on sec.gov or a company's own investor site, with the document's words quoted beneath it. A second, independent pass loaded every linked document and kept only the statements it supports; statements it could not reach or confirm were dropped. Long filings were read in part (the business section, the earnings exhibits and the investor decks), so property tables and management's discussion are under-represented; the EDGAR link on each company leads to the full filing. Nothing here is investment, legal, or tax advice. Found an error? Say so.