Home › For developers › Choosing suppliers
Choosing suppliers: the public evidence on modules, inverters, trackers, batteries and transformers
This site does not rank vendors. What it can do is put the public evidence in one place: the independent reliability scorecards and what they test, the market reports and whose list each is, and the rules that decide eligibility before any quote is compared: prohibited-foreign-entity limits, domestic content, trade cases, forced-labor enforcement, fire-safety standards and inverter ride-through requirements.
Jump to: Independent reliability testing · Market reports and supply conditions · Rules that decide what can be bought · Diligence and contract terms
Independent reliability testing
What the module, inverter and battery scorecards test, how they define a top performer, and what the latest editions found.
- Kiwa PVEL's 12th PV Module Reliability Scorecard (May 2026) names 43 manufacturers as Top Performers in at least one test. (Kiwa PVEL press release via AAP/Cision, May 27, 2026)
- The 2026 Scorecard recorded record failure rates: 87% of manufacturers and 61% of BOMs had at least one test failure. (Kiwa PVEL press release via AAP/Cision, May 27, 2026)
- Delamination rose sharply in 2026 PQP testing; 45% of manufacturers had at least one major delamination defect. (Solar Power World, May 27, 2026)
- For the first time no single module model was a Top Performer in every 2026 Scorecard test; UVID was added as a Top Performer category. (Solar Power World, May 27, 2026)
- Kiwa PVEL's public manufacturer page lists 15 companies with Top Performer models in 7-8 tests (Adani, Jinko, LONGi, Phono, HT-SAAE, ZNShine, Elite, Canadian Solar, Aiko, ReNew, Thornova, Tongwei, RenewSys, Fellow Energy, Illuminate USA). (Kiwa PVEL 2026 Scorecard manufacturer page, 2026)
- Scorecard Top Performer thresholds: under 2% power degradation for TC, DH, MSS, PID and UVID; under 1% for LID+LETID. (Kiwa PVEL 2026 Scorecard Executive Summary, 2026)
- Scorecard tests extend IEC/UL certification: thermal cycling runs 600 cycles versus 200, damp heat 2,000 hours versus 1,000. (Kiwa PVEL 2026 Scorecard Executive Summary, 2026)
- Kiwa PVEL released an inverter scorecard in 2019; it no longer offers indoor inverter testing but keeps that report available. (Kiwa PVEL website (2019 Inverter Scorecard page), accessed Oct 2026)
- RETC's 2026 PV Module Index recognized 19 manufacturers, 13 as Overall Highest Achievers, after testing from Q2 2025 to Q1 2026. (RETC via Business Wire, June 2, 2026)
- RETC's 2026 Overall Highest Achievers: Imperial Star, JA Solar, JinkoSolar, Longi, Qcells, Runergy, SolarSpace, Thornova, Trina, VSUN, TW Solar, Waaree, Yingli. (pv magazine USA, June 3, 2026)
- RETC 2026: 11% of BOMs failed damp heat testing (over 5% power loss), up from 6%; hail high-achiever share fell from 70% to 25%. (pv magazine USA, June 3, 2026)
- RETC's CEO frames certification as a floor, not a procurement answer. (RETC via Business Wire, June 2, 2026)
- DNV's Battery Scorecard (2022, fourth edition) drew on independent testing of 19 battery cell types and urged buyers to require independent test data. (DNV press release, Sept 1, 2022)
- DNV's fifth-edition Battery Scorecard (2024) does not name individual cells; the 2022 edition had named CATL and Narada among top performers. (Energy-Storage.news, April 24, 2024)
Market reports and supply conditions
Published rankings and market-share statements (reported as whose list each is), installation volumes, and lead-time evidence for transformers.
- Wood Mackenzie's 2026 module ranking put LONGi first and awarded 25 manufacturers Grade A; nine of twelve top-ten companies are China-headquartered. (Wood Mackenzie press release, June 2, 2026)
- Wood Mackenzie reports leading Chinese module makers lost a combined US$5.5 billion in 2025. (Wood Mackenzie press release, June 2, 2026)
- Wood Mackenzie's 2026 inverter ranking: Sungrow and Huawei share the top position, SMA is third, with GoodWe and Enphase also in the top five; 21 of 23 earned Grade A. (Wood Mackenzie press release, June 11, 2026)
- Wood Mackenzie notes grid-security and software-integrity concerns shape inverter supplier selection in North America and Europe. (Wood Mackenzie press release, June 11, 2026)
- Wood Mackenzie's 2026 tracker ranking placed Nextpower first; three US-headquartered firms are in the top ten; 16 vendors got Grade A. (Wood Mackenzie press release, June 8, 2026)
- Wood Mackenzie: tracker buyers now weigh bankability as heavily as technology. (Wood Mackenzie press release, June 8, 2026)
- Wood Mackenzie 2025 BESS market share: Chinese integrators held 76% globally; Tesla and Sungrow top two; Tesla leads North America, NextEra entered top three. (Wood Mackenzie press release, June 29, 2026)
- Wood Mackenzie's 2026 BESS integrator comprehensive ranking: Sungrow first, Tesla second, CATL third; 18 integrators Grade A; ten criteria assessed. (Wood Mackenzie press release, July 14, 2026)
- SEIA/Wood Mackenzie: U.S. installed 43 GW of solar in 2025; Texas led all states with 11 GW; module capacity reached 65.5 GW. (SEIA press release, March 10, 2026)
- SEIA/WoodMac 2025 Year in Review: domestic module output still trails demand, and Q4 saw module shortages and delivery delays. (SEIA/Wood Mackenzie US SMI 2025 Year in Review exec summary, 2026)
- Q2 2026: U.S. added 11.4 GW of solar; utility-scale installed 9.6 GW, up 61% year over year. (Solar Power World (reporting SEIA/WoodMac Q3 2026 SMI), Sept 10, 2026)
- WoodMac/ACP Q2 2026 Energy Storage Monitor: U.S. utility-scale storage added 2,337 MW / 6,804 MWh in Q1 2026; FEOC rules now affect sourcing. (pv magazine USA, June 23, 2026)
- Wood Mackenzie Q2 2025 survey: power transformers averaged 128-week lead times, GSUs 144 weeks; power transformer prices up 77% since 2019. (POWER Magazine, Jan 2, 2026)
- GSU transformer demand rose 274% from 2019 to 2025; lead times for high-capacity units reach four years (PwC, via Reuters Events). (pv magazine USA, May 11, 2026)
- NREL (Feb 2024) reported utility transformer lead times up to two years and prices up by as much as 4-9 times over three years. (NREL/TP-6A40-87653, Feb 2024)
Rules that decide what can be bought
Tax-credit eligibility (prohibited foreign entity and domestic content), trade remedies, forced-labor enforcement, battery fire-safety standards, and inverter ride-through requirements.
- SEIA/WoodMac describe Treasury's Notice 2026-15 as leaving PFE definitions unresolved. (SEIA/Wood Mackenzie US SMI 2025 Year in Review exec summary, 2026)
- OBBBA (Pub. L. 119-21, signed July 4, 2025): wind/solar beginning construction after July 4, 2026 must be placed in service by Dec 31, 2027. (K&L Gates client alert, July 23, 2025)
- OBBBA: projects beginning construction after Dec 31, 2025 lose 45Y/48E credits if they include material assistance from a prohibited foreign entity. (K&L Gates client alert, July 23, 2025)
- OBBBA domestic content thresholds (the share of manufactured-product cost that must be U.S.-made to earn the 10% domestic-content bonus; a bonus, not an eligibility test) rise by construction start: 40% before June 16, 2025; 45% interim 2025; 50% in 2026; 55% after 2026. (K&L Gates client alert, July 23, 2025 (Appendix B))
- Treasury/IRS Notice 2026-15 (Feb 12, 2026) gives interim rules and safe harbors for the material assistance cost ratio (MACR, the share of a project's manufactured-product cost that is not from a prohibited foreign entity); the PFE definition is deferred to proposed regulations. (IRS news release IR-2026-23, Feb 12, 2026)
- Notice 2026-15 MACR thresholds for 2026 construction starts: 40% non-PFE share for qualified facilities (solar), 55% for energy storage. (pv magazine USA, Feb 13, 2026)
- Notice 2026-15 has three safe harbors (Identification, Cost Percentage, Certification); supplier certifications must be attached to the credit form. (K&L Gates client alert, March 2, 2026)
- Under Notice 2026-15, taxpayers may generally rely on direct supplier certifications of no PFE material assistance. (Jones Day client alert, Feb 2026)
- Notice 2024-41 (May 16, 2024) created the New Elective Safe Harbor using DOE cost percentages for the domestic content manufactured-products test. (Gibson Dunn client alert, May 20, 2024)
- Notice 2025-08 (effective Jan 16, 2025) issued the First Updated Elective Safe Harbor for domestic content, covering grid-scale and distributed BESS. (IRS Notice 2025-08, Jan 2025)
- Commerce final AD/CVD on cells from Cambodia, Malaysia, Thailand, Vietnam announced April 21, 2025, among the first CVD investigations with affirmative transnational-subsidy findings. (U.S. Department of Commerce press release, April 21, 2025)
- Commerce final AD/CVD on cells from India, Indonesia, Laos (Sept 11, 2026): weighted-average AD margins 123.04% India, 94.36% Indonesia, 65.43% Laos; the fact sheet notes the ITC was running its injury investigations concurrently. The ITC's final affirmative determination followed on Oct 14, 2026. (International Trade Administration fact sheet, Sept 11, 2026)
- Section 201 safeguard tariffs on imported solar modules expired Feb 6, 2026 after eight years; the final rate was 14% for 2025. (Solar Power World, Feb 9, 2026)
- In the earlier Cambodia, Malaysia, Thailand and Vietnam case, Commerce's antidumping duty orders became applicable June 24, 2025, after the ITC notified Commerce of its final affirmative determinations on June 9, 2025. (White & Case client alert, Sept 2024)
- UFLPA enforcement 2025: CBP stopped over 16,700 shipments worth nearly $3.7 billion through Aug 1; Qcells' Korean cells were detained then released. (pv magazine USA, Sept 24, 2025)
- CBP expects detailed bills of materials and product-specific documentation under UFLPA; generic supplier certifications, form letters and basic invoices are inadequate in high-risk sectors, and battery supply chains are especially susceptible to scrutiny. (Troutman Pepper Locke client alert, Feb 2, 2026)
- NFPA 855 2026 edition makes hazard mitigation analysis the default expectation for most ESS installations and explicitly requires large-scale fire testing alongside UL 9540A. (Energy-Storage.news, April 29, 2026)
- UL 9540A sixth edition (2026) adds system-level large-scale fire testing with pass/fail criteria barring unit-to-unit propagation. (Energy-Storage.news, April 1, 2026)
- UL describes UL 9540A as the standard test method for thermal runaway fire propagation, aligned with NFPA 855 Annex G.11. (UL Solutions, The Code Authority, 2026)
- FERC Order 909 approved NERC PRC-029-1 (IBR ride-through) and PRC-024-4, effective Aug 28, 2025. (Federal Register, FERC Order No. 909, July 29, 2025)
- PUCT approved ERCOT NOGRR 245 effective Oct 1, 2024; post-Aug 1, 2024 SGIA IBRs must meet IEEE 2800-2022 voltage ride-through. (ERCOT Market Notice M-A010825-01, Jan 8, 2025)
- ERCOT set Sept 15, 2025 as the final deadline for NOGRR245 ride-through extension submissions and exemption notices; it has passed. (ERCOT Market Notice M-A010825-06, July 24, 2025)
- IEEE 2800-2022 (published April 22, 2022) sets IBR interconnection performance criteria including VRT/FRT; adoption is by the governing authority. (NRECA Business & Technology Strategies advisory, July 2022)
- USITC final affirmative injury determination, Oct 14, 2026, in the crystalline silicon PV cells and modules investigations covering India, Indonesia and Laos (Inv. Nos. 701-TA-772-774 and 731-TA-1756-1758): Commerce will issue antidumping and countervailing duty orders; the Commission's report (Publication 5804) is due on its website by Nov 23, 2026. (USITC News Release 26-147, Oct 14, 2026)
- In the earlier Cambodia, Malaysia, Thailand and Vietnam case, Commerce's antidumping duty orders became applicable June 24, 2025, after the ITC notified Commerce of its final affirmative determinations on June 9, 2025. (Federal Register, June 24, 2025, doc. 2025-11588 (antidumping duty orders))
- The ITC's vote in the Cambodia, Malaysia, Thailand and Vietnam case was May 20, 2025: material injury from imports from Malaysia and Vietnam, threat of material injury from Cambodia and Thailand. (USITC News Release, May 20, 2025)
Diligence and contract terms
What published procurement guides say buyers inspect, warrant and allocate: factory audits, pre-shipment inspection, warranty terms and backing, force majeure and change-in-law.
- Utility-scale buyers increasingly require independent, BOM-specific durability data, factory inspections and pre-shipment inspections beyond certification. (op-ed by a test lab executive) (pv magazine USA (op-ed by Cherif Kedir), Aug 21, 2026)
- Large developers keep approved vendor lists; certification confirms a minimum, not product fit. (pv magazine USA (op-ed by Cherif Kedir), Aug 21, 2026)
- NREL's due-diligence workshop lists IEC 61215 plus extended testing, pre-production audits and pre-shipment inspection (visual, EL, flash) as standard items. (NREL workshop slides, Sept 10, 2017)
- Norton Rose Fulbright advises closed force majeure lists and explicit treatment of tariff change-in-law in solar procurement contracts. (Norton Rose Fulbright Project Finance blog, April 26, 2022)
- Typical module warranties: 10-12 year product, 25-30 year performance; inverter and tracker warranties often extendable from five to ten years. (North American Clean Energy (PCL Construction author), Sept 15, 2025)
- BESS capacity warranties run 10-20 years with cycling, SOC, C-rate and temperature conditions; no industry standard yet exists. (DNV article, April 27, 2021)
- ABA primer: warranty insurance backstops module performance warranties for 20-25 years if the manufacturer becomes insolvent. (American Bar Association Litigation Section, 2025)
How this page was made
Each entry is one statement tied to one public page; a second, independent pass loaded every cited page and kept only the statements that page supports. Secondary reports (trade press, law-firm alerts) are cited as what they are. Nothing here is advice, and this site does not rank, recommend or endorse any company; where a third party publishes a ranking, the entry says whose ranking it is. Found an error? Say so and it will be fixed.