Energy land, checked. Solar, wind, battery, and data-center projects, the permits they need, and the grid they plug into. Start here →
Parcel & Grid

Home › Illinois › Woodford County

Woodford County, Illinois: solar, wind, and storage projects and permits

Queue data downloaded October 7, 2026 · Rules checked October 17, 2026

Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Woodford County, county seat Eureka.

Check land in Woodford CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

What energy projects are proposed in Woodford County?

The PJM interconnection queue lists 11 proposed projects in Woodford County (1 solar, 9 wind, 1 battery storage), about 2,900 MW in all. 4 have a signed interconnection agreement.

What stands out in Woodford County

By capacity, wind leads in Woodford County with 2,450 MW across 9 projects, followed by battery storage (1 project, 250 MW) and solar (1 project, 200 MW). The largest is queue number AE2-255, a 400 MW wind request in the PJM queue, agreement signed, filed Mar 2019, with a target in-service date of Jan 2027. Of the 11, 7 are still in study and 4 have a signed agreement. All of them are in the PJM queue, which covers the ComEd side of the state. The requests were filed between Sep 2018 and Mar 2023. Target in-service dates for those not yet under construction span Apr 2023 to Jun 2028; 6 of them have already passed, which means those schedules slipped.

A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.

Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 6 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.

Scroll the table sideways to see every column.

Queue number and connectionTypeMWStageRequestedTarget in-service
iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built.
AE2-255PJM · ComEd · Molecreek 345 kVWind400Agreement signedMar 2019Jan 2027
AE2-281PJM · ComEd · Powerton-Nevada 345 kVWind400Agreement signedMar 2019Feb 2027
AE1-163PJM · ComEd · Powerton-Nevada 345 kVWind350Agreement signedSep 2018Feb 2027
AE1-113PJM · ComEd · Mole Creek 345 kVWind300Agreement signedSep 2018Jan 2027
AI2-317PJM · ComEd · Powertn - Goodings Grove 345 kV (CIR Increase)Wind350In studyMar 2023Dec 2024 date passed; status per the operator
AI2-315PJM · ComEd · Mole Creek 345 kVWind300In studyMar 2023Dec 2025 date passed; status per the operator
AH1-361PJM · ComEd · Minonk 345 kVStorage250In studySep 2021Sep 2024 date passed; status per the operator
AI2-234PJM · ComEd · Mole Creek 345kV (CIR Increase)Wind200In studyMar 2023Apr 2023 date passed; status per the operator
AI2-245PJM · ComEd · TSS 968 345 kV (CIR Increase)Solar200In studyMar 2023Jun 2028
AI2-314PJM · ComEd · Molecreek 345kV (CIR Increase)Wind100In studyMar 2023Dec 2025 date passed; status per the operator
AI2-316PJM · ComEd · Powerton 345 kV (CIR increase)Wind50In studyMar 2023Dec 2024 date passed; status per the operator

Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.

What can Woodford County require of a project?

Illinois law sets the ceiling: Woodford County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.

Recent local action: Woodford County posts its Chapter 154 Zoning Ordinance, which includes Section 27, Small Wind Energy Systems, and Section 30, Solar Energy Systems, with an amendment history through August 20, 2024; Section 154.05.3.B.8, amended April 18, 2023, requires applicants for commercial wind and solar projects to show compliance with state requirements. (Woodford County Zoning Ordinance (Chapter 154))

State siting standardsFarmland agreement (AIMA)Property taxes

Who to contact in Woodford County

Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Eureka. A drainage district, if the land is in one, must receive the developer's drainage plan.

Woodford County websiteSupervisor of assessmentsZoning and planning

Solar for homes and businesses in Woodford County

Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; ComEd sets the application steps here: Illinois home and business solar rules · utility application links.

State and federal reviews

Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Woodford County: Illinois agency list.

Get the land report for a spot

Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).

Check this land

Check before you file. Queue entries change monthly and county rules change often. General information, not a substitute for the advice of an attorney. Found an error? Let us know.

Browse resources