Will County, Illinois: solar, wind, and storage projects and permits

Queue data downloaded October 7, 2026 · Rules checked October 17, 2026

Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Will County, county seat Joliet.

Check land in Will CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

What energy projects are proposed in Will County?

The PJM interconnection queue lists 16 proposed projects in Will County (3 solar, 2 solar plus storage, 8 battery storage, 3 gas), about 7,506 MW in all. 2 have a signed interconnection agreement.

What stands out in Will County

By capacity, gas leads in Will County with 3,449 MW across 3 projects, followed by battery storage (8 projects, 3,345 MW) and solar (3 projects, 640 MW). The largest is queue number AE1-070 - moved to TC1, a 1,610 MW gas request in the PJM queue, in study, filed Jul 2018, with a target in-service date of Dec 2020. Of the 16, 13 are still in study, 1 has a signed agreement, 1 is under construction and 1 is suspended. All of them are in the PJM queue, which covers the ComEd side of the state. The requests were filed between Mar 2018 and May 2023. Target in-service dates for those not yet under construction span Dec 2020 to Jun 2028; 9 of them have already passed, which means those schedules slipped.

A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.

Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 9 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.

Scroll the table sideways to see every column.

Queue number and connectionTypeMWStageRequestedTarget in-service
iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built.
AD2-194PJM · ComEd · Elwood 345 kVGas1,261Under constructionMar 2018Jan 2027
AG1-478PJM · ComEd · Wilmington 34.5 kVSolar + storage20Agreement signedSep 2020Apr 2026 date passed; status per the operator
AE1-070 - moved to TC1PJM · ComEd · Elwood 345 kVGas1,610In studyJul 2018Dec 2020 date passed; status per the operator
AG1-512PJM · ComEd · University Park North 345 kVStorage646In studySep 2020Jun 2024 date passed; status per the operator
AH1-567PJM · ComEd · University Park 138 kVGas578In studySep 2021Jun 2025 date passed; status per the operator
AH1-560PJM · ComEd · University Park 138 kVStorage573In studySep 2021Jun 2025 date passed; status per the operator
AF2-096 - moved to TC1PJM · ComEd · Braidwood-East Frankfort 345 kVSolar300In studyFeb 2020May 2022 date passed; status per the operator
AJ1-014PJM · ComEd · Will County Unit 4 CIR TransferStorage260In studyMay 2023Jun 2027
AG2-357PJM · ComEd · Wilton 345 kVStorage250In studyMar 2021Nov 2024 date passed; status per the operator
AJ1-013PJM · ComEd · Will County Unit 4 CIR TransferStorage250In studyMay 2023Jun 2027
AI1-154PJM · ComEd · Goodings Grove 138 kVStorage230In studySep 2022Jan 2027
AH2-172PJM · ComEd · Wilton 345 kVSolar200In studyMar 2022Dec 2026
AH2-170PJM · ComEd · Byron 345Solar140In studyMar 2022Dec 2026
AH1-165PJM · ComEd · Will County 138 kVStorage80In studyAug 2021Jun 2025 date passed; status per the operator
AH2-199PJM · ComEd · Shorewood 138 kVSolar + storage52In studyMar 2022Jun 2026 date passed; status per the operator
AG1-513PJM · ComEd · Aurora 138 kVStorage1,056SuspendedOct 2020Jun 2028

Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.

What can Will County require of a project?

Illinois law sets the ceiling: Will County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.

Recent local action: On May 21, 2026, the county board voted 12–8 to approve a special use permit for a 600 MW solar project, after a circuit court in April 2026 ordered the county to approve permits for six other solar projects. (NBC Chicago) (court order)

State siting standardsFarmland agreement (AIMA)Property taxes

Who to contact in Will County

Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Joliet. A drainage district, if the land is in one, must receive the developer's drainage plan.

Will County websiteSupervisor of assessmentsZoning and planningCounty engineer and highways

Solar for homes and businesses in Will County

Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; ComEd sets the application steps here: Illinois home and business solar rules · utility application links.

State and federal reviews

Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Will County: Illinois agency list.

Get the land report for a spot

Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).

Check this land

Check before you file. Queue entries change monthly and county rules change often. General information, not a substitute for the advice of an attorney. Found an error? Let us know.