Ogle County, Illinois: solar, wind, and storage projects and permits
Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Ogle County, county seat Oregon.
Check land in Ogle CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
What energy projects are proposed in Ogle County?
The PJM interconnection queue lists 13 proposed projects in Ogle County (9 solar, 1 wind, 3 battery storage), about 3,775 MW in all. 1 has a signed interconnection agreement.
What stands out in Ogle County
By capacity, solar leads in Ogle County with 1,825 MW across 9 projects, followed by battery storage (3 projects, 1,800 MW) and wind (1 project, 150 MW). The largest is queue number AH1-148, a 600 MW solar request in the PJM queue, in study, filed Aug 2021, with a target in-service date of Dec 2025. Of the 13, 12 are still in study and 1 has a signed agreement. All of them are in the PJM queue, which covers the ComEd side of the state. The requests were filed between Apr 2017 and Mar 2023. Target in-service dates for those not yet under construction span Sep 2021 to Dec 2026; 12 of them have already passed, which means those schedules slipped.
A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.
Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 12 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.
Scroll the table sideways to see every column.
| Queue number and connection | Type | MW | Stage | Requested | Target in-service iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built. |
|---|---|---|---|---|---|
| AD1-013PJM · ComEd · Twombly Road 138kV | Solar | 40 | Agreement signed | Apr 2017 | Apr 2026 date passed; status per the operator |
| AH1-148PJM · ComEd · Byron-Wayne 345 kV | Solar | 600 | In study | Aug 2021 | Dec 2025 date passed; status per the operator |
| AH2-086PJM · ComEd · Byron – Wayne 345 kV | Storage | 600 | In study | Feb 2022 | Dec 2025 date passed; status per the operator |
| AH2-087PJM · ComEd · Byron - Wayne 345 kV | Storage | 600 | In study | Jan 2022 | Dec 2025 date passed; status per the operator |
| AH2-088PJM · ComEd · Byron - Wayne 345 kV | Storage | 600 | In study | Feb 2022 | Dec 2025 date passed; status per the operator |
| AH1-147PJM · ComEd · Byron-Wayne 345 kV | Solar | 400 | In study | Aug 2021 | Dec 2025 date passed; status per the operator |
| AH1-146PJM · ComEd · Byron - Wayne 345 kV | Solar | 200 | In study | Aug 2021 | Dec 2025 date passed; status per the operator |
| AH1-540PJM · ComEd · Byron to Wayne 345 kV | Solar | 165 | In study | Sep 2021 | Mar 2025 date passed; status per the operator |
| AE1-114 - moved to TC1PJM · ComEd · Maryland-Lancaster 138 kV | Wind | 150 | In study | Sep 2018 | Dec 2021 date passed; status per the operator |
| AH1-341PJM · ComEd · ESS-H445 3B 138kv | Solar | 150 | In study | Sep 2021 | Dec 2025 date passed; status per the operator |
| AH2-173PJM · ComEd · Maryland 138 kV | Solar | 150 | In study | Mar 2022 | Dec 2026 |
| AF1-331PJM · ComEd · Twombley Road | Solar | 60 | In study | Sep 2019 | Sep 2021 date passed; status per the operator |
| AI2-370PJM · ComEd · Twombley Road 138kV (CIR Increase) | Solar | 60 | In study | Mar 2023 | Apr 2026 date passed; status per the operator |
Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.
What can Ogle County require of a project?
Illinois law sets the ceiling: Ogle County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.
Recent local action: On February 18, 2025 the Ogle County Board approved by voice vote a special-use permit for Lupine Solar 2, a 2 MWac community solar facility proposed by OneEnergy Development LLC on 16 acres of a 75-acre AG-1 site in the 3200 block of South Union Road southeast of Polo. The Zoning Board of Appeals had voted 5–0 on January 30 and the board committee 8–1 on February 11 to recommend approval. (Shaw Local (Sauk Valley))
State siting standardsFarmland agreement (AIMA)Property taxes
Who to contact in Ogle County
Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Oregon. A drainage district, if the land is in one, must receive the developer's drainage plan.
Ogle County websiteSupervisor of assessmentsZoning and planningCounty engineer and highways
Solar for homes and businesses in Ogle County
Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; ComEd sets the application steps here: Illinois home and business solar rules · utility application links.
State and federal reviews
Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Ogle County: Illinois agency list.
Get the land report for a spot
Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).