McDonough County, Illinois: solar, wind, and storage projects and permits

Queue data downloaded October 7, 2026 · Rules checked October 17, 2026

Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in McDonough County, county seat Macomb.

Check land in McDonough CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

What energy projects are proposed in McDonough County?

The MISO interconnection queue lists 3 proposed projects in McDonough County (3 wind), about 416 MW in all. 1 has a signed interconnection agreement.

What stands out in McDonough County

By capacity, wind leads in McDonough County with 416 MW across 3 projects. The largest is queue number J3493, a 200 MW wind request in the MISO queue, in study (Phase 2), filed Apr 2024, with a target in-service date of Sep 2028. Of the 3, 2 are still in study and 1 has a signed agreement. All of them are in the MISO queue, which covers the Ameren Illinois side of the state. Ameren Illinois is the transmission owner named most often (2 of 3). The requests were filed between Aug 2021 and Apr 2024. Target in-service dates for those not yet under construction span Dec 2019 to Sep 2028; 2 of them have already passed, which means those schedules slipped.

A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.

Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 2 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.

Scroll the table sideways to see every column.

Queue number and connectionTypeMWStageRequestedTarget in-service
iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built.
J1701MISO · Ameren Illinois · Macomb to Ipava 138kV lineWind200Agreement signedDec 2021Sep 2023 date passed; status per the operator
J3493MISO · Ameren Transmission Company Of Illinois · Other_Wind200In study (Phase 2)Apr 2024Sep 2028
J2189MISO · Ameren Illinois · Hornsby Switching StationWind16In study (Phase 2)Aug 2021Dec 2019 date passed; status per the operator

Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.

What can McDonough County require of a project?

Illinois law sets the ceiling: McDonough County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.

Local rules: as of October 17, 2026, we found no 2024–2026 county board action on solar, wind, or battery storage posted on McDonough County's website or reported by local news. That does not mean the county has no ordinance: the state standards above apply everywhere, and the county zoning office can say whether a local ordinance or special use process exists.

State siting standardsFarmland agreement (AIMA)Property taxes

Who to contact in McDonough County

Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Macomb. A drainage district, if the land is in one, must receive the developer's drainage plan.

County engineer and highways

Solar for homes and businesses in McDonough County

Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; Ameren Illinois sets the application steps here: Illinois home and business solar rules · utility application links.

State and federal reviews

Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in McDonough County: Illinois agency list.

Get the land report for a spot

Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).

Check this land

Check before you file. Queue entries change monthly and county rules change often. General information, not a substitute for the advice of an attorney. Found an error? Let us know.