Marshall County, Illinois: solar, wind, and storage projects and permits

Queue data downloaded October 7, 2026 · Rules checked October 17, 2026

Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Marshall County, county seat Lacon.

Check land in Marshall CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

What energy projects are proposed in Marshall County?

The MISO interconnection queue lists 2 proposed projects in Marshall County (1 solar, 1 wind), about 213 MW in all. 0 have a signed interconnection agreement.

What stands out in Marshall County

By capacity, wind leads in Marshall County with 178 MW across 1 project, followed by solar (1 project, 35 MW). The largest is queue number J2247, a 178 MW wind request in the MISO queue, in study (Phase 2), filed Mar 2022, with a target in-service date of Sep 2024. Of the 2, 2 are still in study. All of them are in the MISO queue, which covers the Ameren Illinois side of the state. The requests were filed between Mar 2022 and Sep 2022. Target in-service dates for those not yet under construction span Sep 2023 to Sep 2024; 2 of them have already passed, which means those schedules slipped.

A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.

Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 2 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.

Scroll the table sideways to see every column.

Queue number and connectionTypeMWStageRequestedTarget in-service
iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built.
J2247MISO · Ameren Illinois · WoodhallWind178In study (Phase 2)Mar 2022Sep 2024 date passed; status per the operator
J3188MISO · · Hallock 138 kVSolar35In study (Phase 2)Sep 2022Sep 2023 date passed; status per the operator

Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.

What can Marshall County require of a project?

Illinois law sets the ceiling: Marshall County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.

State siting standardsFarmland agreement (AIMA)Property taxes

Who to contact in Marshall County

Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Lacon. A drainage district, if the land is in one, must receive the developer's drainage plan.

Marshall County website

Solar for homes and businesses in Marshall County

Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; Ameren Illinois sets the application steps here: Illinois home and business solar rules · utility application links.

State and federal reviews

Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Marshall County: Illinois agency list.

Get the land report for a spot

Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).

Check this land

Check before you file. Queue entries change monthly and county rules change often. General information, not a substitute for the advice of an attorney. Found an error? Let us know.