LaSalle County, Illinois: solar, wind, and storage projects and permits

Queue data downloaded October 7, 2026 · Rules checked October 17, 2026

Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in LaSalle County, county seat Ottawa.

Check land in LaSalle CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.

What energy projects are proposed in LaSalle County?

The PJM interconnection queue lists 11 proposed projects in LaSalle County (3 solar, 5 wind, 3 battery storage), about 1,224 MW in all. 1 has a signed interconnection agreement.

What stands out in LaSalle County

By capacity, wind leads in LaSalle County with 707 MW across 5 projects, followed by solar (3 projects, 368 MW) and battery storage (3 projects, 150 MW). The largest is queue number AI2-180, a 191 MW wind request in the PJM queue, in study, filed Feb 2023, with a target in-service date of Feb 2023. Of the 11, 10 are still in study and 1 is under construction. All of them are in the PJM queue, which covers the ComEd side of the state. The requests were filed between Jan 2018 and Feb 2023. Target in-service dates for those not yet under construction span Feb 2023 to Mar 2025; 10 of them have already passed, which means those schedules slipped.

A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.

Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 10 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.

Scroll the table sideways to see every column.

Queue number and connectionTypeMWStageRequestedTarget in-service
iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built.
AD2-038PJM · ComEd · Powerton-Nevada 345 kVWind150Under constructionJan 2018Oct 2026
AI2-180PJM · ComEd · LaSalle 138kVWind191In studyFeb 2023Feb 2023 date passed; status per the operator
AF2-142 - moved to TC1PJM · ComEd · Nevada 345 kVSolar150In studyMar 2020Dec 2023 date passed; status per the operator
AF2-143 - moved to TC1PJM · ComEd · Powerton-Nevada 345 kVSolar150In studyMar 2020Dec 2023 date passed; status per the operator
AH1-003PJM · ComEd · Tazewell - AB1-122 345 kVWind130In studyApr 2021Dec 2024 date passed; status per the operator
AI2-122PJM · ComEd · Tazewell - AB1-122 345 kVWind130In studyFeb 2023Dec 2024 date passed; status per the operator
AI2-178PJM · ComEd · LaSalle 138 kVWind106In studyFeb 2023Mar 2023 date passed; status per the operator
AH1-544PJM · ComEd · La Salle 345 kVSolar68In studySep 2021Mar 2025 date passed; status per the operator
AF2-226 - moved to TC1PJM · ComEd · Katydid Road 345 kVStorage50In studyMar 2020Oct 2023 date passed; status per the operator
AF2-319 - moved to TC1PJM · ComEd · Katydid Road 345 kVStorage50In studyMar 2020Oct 2023 date passed; status per the operator
AG2-061PJM · ComEd · Powerton-Nevada 345 kVStorage50In studyDec 2020Dec 2023 date passed; status per the operator

Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.

What can LaSalle County require of a project?

Illinois law sets the ceiling: LaSalle County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.

Recent local action: On April 10, 2025 the La Salle County Board passed a resolution, 21–5, asserting the county's right to control siting approval for wind and solar projects and urging the General Assembly to repeal Public Act 102-1123. In February 2025, 17 of 29 members abstained or voted present on a 76-acre Utica Township solar farm, which passed with eight yes votes. (Shaw Local (NewsTribune))

State siting standardsFarmland agreement (AIMA)Property taxes

Who to contact in LaSalle County

Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Ottawa. A drainage district, if the land is in one, must receive the developer's drainage plan.

LaSalle County websiteCounty engineer and highways

Solar for homes and businesses in LaSalle County

Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; ComEd sets the application steps here: Illinois home and business solar rules · utility application links.

State and federal reviews

Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in LaSalle County: Illinois agency list.

Get the land report for a spot

Flood zone, wetlands, nearest power line, soils, and more for any point. Parcel acreage fills in automatically in Texas and 26 other states (not Illinois, which has no statewide parcel layer).

Check this land

Check before you file. Queue entries change monthly and county rules change often. General information, not a substitute for the advice of an attorney. Found an error? Let us know.