Iroquois County, Illinois: solar, wind, and storage projects and permits
Proposed projects, county offices, and the state rules for a solar, wind, or battery storage project in Iroquois County, county seat Watseka.
Check land in Iroquois CountyOpens the land report with the map on the county; click a spot for its flood, wetland, habitat, line-distance and parcel check.
What energy projects are proposed in Iroquois County?
The MISO interconnection queue lists 8 proposed projects in Iroquois County (3 solar, 4 wind, 1 hybrid), about 1,778 MW in all. 0 have a signed interconnection agreement.
What stands out in Iroquois County
By capacity, wind leads in Iroquois County with 789 MW across 4 projects, followed by solar (3 projects, 589 MW) and hybrid (1 project, 400 MW). The largest is queue number J3015, a 400 MW hybrid request in the MISO queue, in study (Phase 2), filed Sep 2022, with a target in-service date of Jun 2027. Of the 8, 8 are still in study. All of them are in the MISO queue, which covers the Ameren Illinois side of the state. Ameren Transmission Company Of Illinois is the transmission owner named most often (4 of 8). The requests were filed between Mar 2022 and Dec 2024. Target in-service dates for those not yet under construction span Sep 2024 to Jun 2029; 3 of them have already passed, which means those schedules slipped.
A listing means a developer asked the grid operator to study connecting a project; many are never built, and the status column says where each one stands.
Reading the table: the queue number is the operator's ID for the request (MISO J-numbers, PJM AE/AF/AG-numbers); operators do not publish developer names in these files. Connection is the transmission owner and, where listed, the substation or line; "Other_" is the operator's own placeholder. In study (Phase 1/2) are MISO's definitive-planning study phases; "moved to TC1" means a PJM request was carried into Transition Cycle 1; "CIR Increase" is a request to add capacity rights to an existing project; "LRTP" names a MISO long-range transmission project. For PJM rows, MW is the figure in the megawatt column of PJM's public queue export; PJM also tracks maximum facility output and capacity rights separately, so a project's study documents can show a different number. 3 target in-service dates below have already passed while the request is still open: operators keep the developer's last reported date until the developer changes it, so a past date means the schedule slipped, not that the project was built.
Scroll the table sideways to see every column.
| Queue number and connection | Type | MW | Stage | Requested | Target in-service iThe in-service date the developer gave the grid operator. Developers set and change it, many projects slip, and some are never built. |
|---|---|---|---|---|---|
| J3015MISO · · Gilman - Watseka 138kV | Hybrid (solar, wind, or storage) | 400 | In study (Phase 2) | Sep 2022 | Jun 2027 |
| J2565MISO · Ameren Illinois · 4GILMAN-4PAXTON E 138kV | Solar | 265 | In study (Phase 2) | Sep 2022 | Sep 2026 date passed; status per the operator |
| J3753MISO · Ameren Transmission Company Of Illinois · Other_ | Wind | 196 | In study (Phase 2) | Apr 2024 | Sep 2028 |
| J2136MISO · Ameren Illinois · Gilman South | Solar | 191 | In study (Phase 2) | Mar 2022 | Sep 2024 date passed; status per the operator |
| J3755MISO · Ameren Transmission Company Of Illinois · Other_ | Wind | 147 | In study (Phase 2) | Apr 2024 | Sep 2028 |
| J3754MISO · Ameren Transmission Company Of Illinois · Other_ | Wind | 147 | In study (Phase 2) | Apr 2024 | Sep 2028 |
| J2809MISO · · 4GILMAN - 4PAXTON E 138 kV | Solar | 133 | In study (Phase 2) | Sep 2022 | Sep 2026 date passed; status per the operator |
| J3853MISO · Ameren Transmission Company Of Illinois · Other_ | Wind | 300 | In study (Phase 1) | Dec 2024 | Jun 2029 |
Sources: MISO generator interconnection queue and PJM interconnection queue, downloaded October 7, 2026; withdrawn and operating projects are left out, and the operators do not publish developer names. What the stages mean.
What can Iroquois County require of a project?
Illinois law sets the ceiling: Iroquois County must approve a commercial wind or solar project that meets the state standards, must finish its public hearing within 60 days, and may not ban them in agricultural or industrial zones (55 ILCS 5/5-12020); battery storage has had its own statewide standards since June 1, 2026 (55 ILCS 5/5-12024). Land inside a city or village falls under municipal zoning instead.
Recent local action: The county adopted a commercial solar ordinance on May 13, 2025, and has posted draft solar and battery storage ordinance revisions dated April 21, 2026. (adopted ordinance)
State siting standardsFarmland agreement (AIMA)Property taxes
Who to contact in Iroquois County
Assessment questions go to the supervisor of assessments, special use applications to the zoning office, and road use agreements to the county engineer; the county seat is Watseka. A drainage district, if the land is in one, must receive the developer's drainage plan.
Solar for homes and businesses in Iroquois County
Illinois net metering, the Illinois Shines incentive, and HOA rules are the same statewide; Ameren Illinois sets the application steps here: Illinois home and business solar rules · utility application links.
State and federal reviews
Illinois EPA stormwater coverage, IDNR's EcoCAT review, historic preservation review, and federal wildlife screening can apply to a site in Iroquois County: Illinois agency list.